Albini v. Stanco

61 Misc. 2d 813, 306 N.Y.S.2d 731, 1968 N.Y. Misc. LEXIS 992
CourtNew York Supreme Court
DecidedDecember 12, 1968
StatusPublished
Cited by8 cases

This text of 61 Misc. 2d 813 (Albini v. Stanco) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albini v. Stanco, 61 Misc. 2d 813, 306 N.Y.S.2d 731, 1968 N.Y. Misc. LEXIS 992 (N.Y. Super. Ct. 1968).

Opinion

Frank A. Gttlotta, J.

The plaintiff Albini and Ms wholly-owned corporation, Hallad Construction Corp., are united in interest and will be so treated throughout this opinion.

The action is one for a declaratory judgment in which the plaintiff seeks an adjudication that a Building Zone Ordinance of the defendant city under which he was given a building per[815]*815mit for an apartment house is valid, that the permit itself is likewise valid, and that he has a vested right to continue building thereunder.

Beside denials, the answer pleads as an affirmative defense, that plaintiff was warned by an order of this court on October 17, 1967, by Pittoni, J., that continued construction would be at his own risk.

It appears that in or about November, 1966, plaintiff became interested in a 4%-acre parcel of land at Pearsall Avenue and Glen Street, Glen Cove, known as the Titus property, as a site for a four-story apartment house. It was then being used as a lumber yard, although the City Council at the time was considering amending its ordinance so as to permit an apartment house use of the site in question. It was already under contract of sale to Ben David Pearl Corp., and on December 30, 1966, plaintiff agreed to purchase the contract from Ben David, the future assignment being contingent upon the change of zone being finalized.

On January 18, 1967, the City Council adopted new zoning requirements for apartment houses which, among many other changes, permitted construction to a height of four stories, and also adopted a notice of intention to amend the zoning map of the city and sent the latter to the Planning Board for its consideration and recommendations in accordance with section 24-21 of the Code of Ordinances.

On March 28, 1967, the Council adopted amendments to the zoning map, following the modifications recommended by the Planning Board. On the new map the Titus parcel is included in the R-5A, Central Apartment House Overlay District as a “G” parcel.

Before proceeding with the apartment house project it was necessary that Albini obtain site approval of the plot plan from the Planning Board and he continued with the architect who had been hired by Ben David for that purpose. Site approval was obtained on July 11, 1967, and building plans were then filed with the Building Department. These were processed for over a month and then approved on August 24, 1967, and a permit issued. The latter takes the form of stamping ‘ approved ” on a copy of the original plans which are then returned to the applicant.

Title to the land was conveyed August 31, 1967, the plaintiff paying $370,000 cash therefor. Plaintiff had been lining up subcontractors from March onward and after title closed he entered into contracts with them covering most of the work to be done, since he does none of it himself in his own organiza[816]*816tion. Ground was broken, the existing structures demolished and footings and foundations put in. A large amount of soil had to be moved first, since the site approval had required lowering the grade of the parcel some 12 feet.

In the meantime on August 26, 1967," and unknown to Albini, one Andrew J. Pilla and others commenced an action against the city and the then owner, Titus, attacking the validity of the amendments to the zoning ordinance. This information was withheld by the seller at the closing five days later and Albini did not learn of it until September 27,1967, when he was served with motion papers to add him to the Pilla case as a party defendant. He had already done a considerable amount of physical work on the property in addition to having obligated himself by contract to numerous subcontractors and suppliers. The proof shows that as of October 17, 1967, when Justice Pittoni’s decision referred to in defendants’ answer was rendered, plaintiff had made actual out-of-pocket payments of $579,804 which included the cost of the land, or about $200,000 if the lánd is excluded. Firm contract obligations by that time amounted to $1,531,751. Pictures of the project show the stage it had reached on October 17. These photographs show footings and foundations in various stages of installation and were estimated moneywise by witnesses at the trial to constitute 10% completion of Building A and 20% of Building B.

After Albini became a party to the Pilla action, his efforts were directed toward obtaining a prompt trial on the merits, whereas the plaintiff sought to delay it. When the case came on for trial before Justice Brennan on December 12, 1967, he refused to grant plaintiff any further adjournments and the parties thereupon entered into a stipulation in open court discontinuing the action as against Albini “with prejudice ” and an order was entered to that effect on December 14, 1967. The order also canceled the Us pendens.

A new administration took over in Glen Cove on January 1, 1968, and on February 26, 1968, plaintiff received a letter from the Building Inspector, sent at the direction of the Mayor, revoking his building permit for two reasons: (1) that the fees paid for it were insufficient; (2) that the plans violated the zoning ordinance in providing for “fire protected” construction instead of “fireproof” construction. Plaintiff promptly commenced the present action and made a motion for a temporary injunction restraining the defendant from interfering with his operation pendente lite, which came on for argument before Justice Suluvan on March 15, 1968. He denied the [817]*817motion on March 26, referring to a decision which had been made by Justice Albert in the Pilla case on March 5 and which held the ordinance amendment of January 18, 1967, “void and of no effect” principally because the resolution had never been voted upon by the City Council. Justice Sullivan pointed out that since this was a holding that the ordinance was void ab initio, the plaintiff had shown no clear legal right to relief and therefore could not obtain same in advance of a trial. He, of course, had no way of knowing that factually the basis for Justice Albert’s holding did not exist and that on June 18, 1968, he would amend his decision by eliminating that basis for it and relying only on the second ground, to wit: that there were substantial differences in the zoning amendment as enacted and the prior notice of public hearings advertised. Justice Albert did not amend the judgment itself and there was no one to urge him to do so, since at the same time he denied a motion by Albini to intervene, thus foreclosing any direct attack on the judgment by appeal or otherwise, by the only person interested in doing so.

On April 3, 1968, plaintiff was served with a criminal summons for building without a permit and construction has been halted since that time.

Turning first to the merits of the revocation: Plaintiff’s Exhibit No. 39 shows that plaintiff paid fees of $4,758 for the permit on the basis of estimated construction costs of $1,184,000. The city’s contention that this was inadequate is based on an affidavit which plaintiff’s attorneys filed in connection with this litigation showing that his entire investment would be substantially more than that sum. This, of course, included the land, architect’s fees, attorneys’ fees, overhead, interest, taxes, etc. which are not considered construction costs. Nothing was offered by the city on this trial to show what the actual cost of construction would be.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hertz Corp. v. Corcoran
137 Misc. 2d 403 (New York Supreme Court, 1987)
Ratner v. Fountains Clove Road Apartments, Inc.
118 A.D.2d 843 (Appellate Division of the Supreme Court of New York, 1986)
Village of Northbrook v. County of Cook
410 N.E.2d 925 (Appellate Court of Illinois, 1980)
Coutant v. Town of Poughkeepsie
69 A.D.2d 506 (Appellate Division of the Supreme Court of New York, 1979)
Reizel, Inc. v. Exxon Corp.
42 A.D.2d 500 (Appellate Division of the Supreme Court of New York, 1973)
Trifaro v. Zoning Board of Appeals
73 Misc. 2d 483 (New York Supreme Court, 1973)
Vizzi v. Town of Islip
71 Misc. 2d 483 (New York Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
61 Misc. 2d 813, 306 N.Y.S.2d 731, 1968 N.Y. Misc. LEXIS 992, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albini-v-stanco-nysupct-1968.