Albin v. Harvey & Jones

162 So. 658, 1935 La. App. LEXIS 346
Louisiana Court of Appeal·Decided July 15, 1935·No. No. 4975.·Published·Cited by 3 cases

Opinion

TALIAFERRO, Judge.

This appeal was heretofore dismissed because the transcript did not disclose that an order of appeal had been- granted. The transcript was incomplete in this, respect as the appeal had been moved for and granted by the lower court. The record has been supplemented by adding the order of appeal, and the case has again been submitted to us for consideration.

Defendant Harvey & Jones, a copartnership, contracted with the Louisiana highway commission in September, 1931, to construct the road and bridge work designated as sections A and B, state project No. 819⅛ of routes 545 and 547, Jackson parish, on a definite unit price basis, and to furnish all material and provide all labor- therefor. Statutory bond for the faithful performance of the contract and payment of all labor and material bills incurred in prosecuting the work was given by the contractor, with the now extinct Union Indemnity Company as surety. Plaintiff sold and delivered to sa'id contractor lumber and piling used in the construction of permanent bridges on said roads, of the price of which there is now *659 due a balance of $298.94. This suit was brought against the contractor, the individual members thereof, and the Louisiana highway commission, to recover judgment for said amount and to have recognized and enforced the lien and privilege asserted by plaintiff, as a furnisher of material and supplies on said road proj ect, and on the funds due the contractor in the hands of the commission.

It is alleged that the commission, after being notified of the filing of plaintiff’s lien, paid out to other creditors of the contractor, from the funds held by it for the contractor, amounts greatly in excess of the balance due plaintiff. It is not alleged, however, when the commission was notified of the filing of the purported lien; neither is the date of the filing or registry of the lien stated. It also is not alleged that there were any funds in the hands of the commission belonging to the contractor when the suit was filed; nor is it alleged that there are ■unsatisfied liens or lienable claims or accounts against the completed road and bridge project, or against the funds due on the price thereof, if any, in the hands of the commission, excepting plaintiff’s own account.

It is further alleged that the Union Indemnity Company, in January, 1933, was dissolved by decree of the civil district court in New Orleans, its affairs placed in receivership, and that it is hopelessly insolvent; therefore, as surety on the contractor’s bond, it cannot be made to respond for the contractor’s liabilities. It is because of the alleged insolvency and insufficiency of said surety that plaintiff seeks to hold the commission personally responsible for the amount sued for, section 6, Act No. 224 of 1918, being relied upon. Objection to said surety for these reasons is set up in the petition.

The commission- excepted to the petition on the ground that it did not disclose any right or cause of action against it. The exception was overruled. Harvey & Jones did not answer. As to them, issue was joined by default. The commission in its answer denied any liability whatever to plaintiff in connection with the account sued on, and averred that the total contract price was paid to the contractor, in accordance with the terms of the contract, prior to its knowledge that any amount was due to plaintiff. The allegations that the Union Indemnity Company was insolvent and its worthlessness as surety on the bond of the contractor, are also denied.

On March 13, 1934, the case was tried and taken under advisement, and two weeks thereafter judgment was rendered rejecting the demands of plaintiff. No judgment was then signed. On May 31st, plaintiff filed motion for rehearing and/or new trial. It does not appear that any objection was made to consideration of the motion for rehearing on account of its belated filing. On June 30th, the following minute entry appears :

“The motion for a new trial in this case having been tried and submitted, the same is this day sustained to the extent of granting a rehearing.”

The case was again considered “on rehearing,” September 14th, argued and submitted, and taken under advisement, no objection being made to this procedure. Thereafter judgment was awarded plaintiff, as by him prayed for. The commission appealed.

Appellant urges here that the exception of no cause and no right of action filed by it should have been sustained. In support of this contention, it is argued that plaintiff has no direct action against the commission, but should have provoked a concursus proceeding to which all creditors of the contractor, on account of work done or material furnished to enable it to complete the contract, and the commission, should have been made parties.

The petition does not disclose that there are any unsatisfied liens or claims against this road and bridge construction work, except that of plaintiff, and in these circumstances a concursus proceeding is not authorized. The exception had to be passed upon solely from the allegations of the petition. It is only when there are two or more creditors or lienors that concursus may be resorted to in order to fix and determine the respective rights, rank, and class of the claims of such creditors. It would be absurd to contend otherwise. The case of Mahoney v. Louisiana Highway Commission, 154 La. 383, 97 So. 582, 583, is authority for the doctrine that “where there are claims against the indebtedness [fund in hands of Commissioñ], a concursus may be provoked.” The plural “claims” is used in this statement.

Section 3 of Act No. 271 of 1926, amending section 2 of Act No. 224 of 1918, pro *660 vides that any person to whom any money shall be due for work or labor on, or for furnishing any material or supplies in the construction of, a road or other improvement, “may file with the said authority having the said work done, and record in the office of the Recorder of Mortgages for the parish in which the said work is being done, any time after the maturity of his claim, a sworn statement of the amount due him, and any payments made thereafter by -said authority without deducting the amount of the claims so served on it, shall make said authority liable for the amount of such claim.”

Plaintiff’s allegations bring him within the protective features of this statute. He says that after the commission had notice of the existence of his lien and the filing of his account, it paid out to other claimants funds belonging to the contractor greatly in excess of the amount sued for. If these allegations are true in fact, the commission would be personally bound to pay plaintiff the balance due him by the contractor, if the amount cannot be collected from the contractor. In addition to this, the petition discloses facts rendering the commission responsible to plaintiff because of the insolvency of the said surety. We do not think the exception well founded. The lower court’s ruling thereon is affirmed.

Merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Albin v. Harvey & Jones, 162 So. 658, 1935 La. App. LEXIS 346 (La. Ct. App. 1935).

162 So. 658 (Albin v. Harvey & Jones) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kewaunee Scientific Corp. v. RAGUSA & SON
723 So. 2d 470 (Louisiana Court of Appeal, 1998)
George A. Fuller Company v. Coastal Plains, Inc.
290 F. Supp. 911 (E.D. Louisiana, 1968)
Guess & Albin v. Worman
162 So. 662 (Louisiana Court of Appeal, 1935)