Albano v. Jordan Marsh Co.

311 N.E.2d 568, 2 Mass. App. Ct. 304, 1974 Mass. App. LEXIS 638
CourtMassachusetts Appeals Court
DecidedMay 24, 1974
StatusPublished
Cited by4 cases

This text of 311 N.E.2d 568 (Albano v. Jordan Marsh Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albano v. Jordan Marsh Co., 311 N.E.2d 568, 2 Mass. App. Ct. 304, 1974 Mass. App. LEXIS 638 (Mass. Ct. App. 1974).

Opinion

Hale, C.J.

This is a petition for declaratory judgment (G. L. c. 231 A) which seeks a determination of the rights of the parties under a lease executed in 1964. The plaintiff has appealed from a final decree which adjudged, among other things, that the lease in question had been effectively terminated.

The evidence is reported and there is a report of material facts. The evidence is both oral and documentary. Our duty is to examine the entire evidence and to decide the case according to our own judgment. Findings of fact based wholly or partly upon oral testimony, however, will not be set aside unless they are plainly wrong. Berry v. Kyes, 304 Mass. 56, 57-58 (1939). We summarize the material facts found by the trial judge.

The plaintiff Albano, a real estate developer, acquired sixty-three acres of land in the Springfield area upon which he planned to erect a regional shopping center to be known as the Springfield Mall. On April 28, 1964, Albano and Jordan Marsh entered into an indenture of lease (the lease) whereby Albano agreed to lease to Jordan Marsh for a term of thirty-five years a department store building to be erected by Albano on the site. The lease provided that the store was to be substantially completed by May 1, 1967. The date of substantial completion is known as the “fixturing date,” the date upon which the tenant may begin installing its fixtures and stocking its store with merchandise. A store of the size contemplated here would usually be ready for fix- *306 turing approximately fourteen months after the commencement of construction. Such a store could be opened for business three to four months after the fixtur-ing date.

Albano encountered difficulties in obtaining the financing required for the project; by March, 1966 (fourteen months prior to the contemplated fixturing date), he had not secured permanent or construction financing, had not secured other tenants for the shopping center as required under the lease, and did not have the necessary construction plans and contracts. After negotiations with Jordan Marsh, an amendment to the lease was executed on May 10, 1966. The amendment postponed the fixtur-ing date to February 1, 1968. The amendment also required Albano to complete a store for Filene’s, to the east of the Jordan Marsh store site, no later than the commencement of the term of the lease to Jordan Marsh. The management of Jordan Marsh felt that the addition of a Filene’s store would help give the shopping center an advantage over anticipated competition from other shopping centers.

During the summer of 1966 Albano began to obtain certain financing and construction commitments. His application for a mortgage loan was approved. He entered into a construction agreement with a contractor, and his application for a construction loan was accepted on August 11, 1966. The construction financing arrangement required Albano to submit to the lender evidence of his agreements with Jordan Marsh, Filene’s, and other prospective tenants concerning the commencement of construction of their respective stores. The arrangement also required Albano to begin drawing down the promised funds within sixty days following August 12, 1966.

By the fall of 1966 Albano had obtained several leases, but his efforts to negotiate a lease with Filene’s during the above-described sixty-day period were unsuccessful. In September of 1966 he had been notified by Jordan *307 Marsh that it would insist upon literal compliance with the amended lease. In early October he requested an extension of time from the construction lender, explaining that the Filene’s lease was being prepared but would not be available before the end of the sixty-day period. The lender refused to grant an extension, and subsequently cancelled his loan application. Albano never obtained an executed lease from Filene’s.

Late in November, 1966, certain taxpayers and residents of Springfield brought proceedings in Hampden Superior Court seeking to block the construction of the Outer Belt Highway, an artery which all parties considered essential to the success of the proposed shopping center. Demurrers were sustained in each of these proceedings, but two cases were appealed to the Supreme Judicial Court. It was found that while such appeals were pending, “no construction lender would take any risks on financing the Center.” Albano notified Jordán Marsh in December, 1966, that the pending proceedings (and certain other events) rendered it impossible for him to proceed with the construction plans; his position was that those factors constituted “unavoidable causes and delays” as defined in the lease, and therefore that he was entitled to an extension of time as provided for under the lease. Jordan Marsh responded that it did not agree with his position, and subsequently advised him again that it would look to strict compliance with the lease, including delivery of a substantially completed building by February 1, 1968, as agreed to in May, 1966.

In February, 1967, Albano amended his construction agreement; the guaranteed maximum cost of the project was now about ten per cent higher than the original figure set forth in the 1966 agreement. In March, 1967, he informed the parent company of Jordan Marsh that a new lender was willing to provide construction financing. He requested a three-month extension, explaining that construction could now be started and could be completed to meet a fixturing date of May 1, 1968. A representa *308 tive of the parent company replied that Jordan Marsh wanted a store ready for fixturing in February as specified in the lease’as amended.

Albano then brought a bill in equity in Suffolk Superior Court, seeking a determination of his right to continue performance under the lease. On September 1, 1967, a decree was entered declaring that, under the terms of the lease, time still remained for him to render performance. Albano then wrote Jordan Marsh that he had secured, among other things, permanent financing, construction financing, and leases with other tenants; he also stated that “[i]t is urgent that we proceed with the Springfield Mall construction now.” Jordan Marsh, however, decided to appeal the Superior Court decision to the Supreme Judicial Court. It was found that “Jordan’s decision to appeal . . . was based on competent legal advice and was made in good faith and not in an effort to frustrate Albano’s rights under the lease.”

During the fall of 1967 several prospective tenants asked to be released from their leases. Some of these tenants negotiated with a competing shopping center located about four miles away. It was found that “Jordan played no part in inducing these tenants to leave.” Late in the fall Albano surrendered his permanent financing commitment.

On June 5, 1968, the opinions of the Supreme Judicial Court in the taxpayers’ appeals and in Jordan Marsh’s appeal were released. In the taxpayers’ actions, the decrees sustaining the demurrers were affirmed. Poremba v. Springfield, 354 Mass. 432 (1968). Omartian v. Mayor of Springfield, 354 Mass. 439 (1968). In Albano’s action against Jordan Marsh, the decree granting Albano further time to perform was also affirmed. Albano v. Jordan Marsh Co. 354 Mass. 445 (1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petti v. Putignano
393 N.E.2d 935 (Massachusetts Appeals Court, 1979)
Albano v. Jordan Marsh Co.
362 N.E.2d 219 (Massachusetts Appeals Court, 1977)
George v. Quincy Co-operative Bank
359 N.E.2d 317 (Massachusetts Appeals Court, 1977)
Albano v. Jordan Marsh Co.
327 N.E.2d 739 (Massachusetts Supreme Judicial Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
311 N.E.2d 568, 2 Mass. App. Ct. 304, 1974 Mass. App. LEXIS 638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albano-v-jordan-marsh-co-massappct-1974.