Alaska Energy Authority v. Fairmont Insurance Co.

845 P.2d 420, 1993 Alas. LEXIS 4
CourtAlaska Supreme Court
DecidedJanuary 22, 1993
DocketS-4862
StatusPublished
Cited by17 cases

This text of 845 P.2d 420 (Alaska Energy Authority v. Fairmont Insurance Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alaska Energy Authority v. Fairmont Insurance Co., 845 P.2d 420, 1993 Alas. LEXIS 4 (Ala. 1993).

Opinion

OPINION

COMPTON, Justice.

This case arises out of a claim by the Alaska Energy Authority (AEA), formerly the Alaska Power Authority, against a contractor’s performance bond issued by Fair-mont Insurance Company (Fairmont). AEA appeals a summary judgment holding that the time limitation in the performance bond barred AEA from bringing suit. We reverse.

I. FACTUAL AND PROCEDURAL BACKGROUND

AEA entered into a contract with Wy-man Construction Company (Wyman) for the repair and reconstruction of the Chester Lake Dam. The contract was for the sum of $1,527,000. Fairmont executed performance and payment bonds in the amount of $1,527,000.

In June 1986 the repair to the dam was substantially complete at considerably lower cost than the engineer’s estimate. Wy-man and AEA then reached an agreement for the design and construction of a new water line to transport water from the dam to the community of Metlakatla. The *421 change order was for $1,119,000. It gave Wyman an extension of time to November 1, 1986 to complete the entire project.

Wyman completed the work. In November 1986 the pipeline was pressure tested and accepted by AEA. On November 10, 1987 final payment on the contract was made to Wyman by AEA.

In the interim Fairmont wrote the president of Wyman, noting that the amount of the bond was $1,527,000, but that the final contract price was $2,676,051. Fairmont stated that with the increase in the contract price the bonding company was entitled to an additional premium to cover the overrun. Fairmont later collected the premium requested.

In August 1988 a penstock support installed into the underlying rock failed. AEA claimed the failure was due to improper grouting of anchors. At the request of AEA, Wyman repaired the support.

In December 1988 AEA notified Wyman and Fairmont that lab results on the failed support indicated the grout material used to install the rock anchors was not mixed as required. AEA feared all of the anchors might be deficient for the same reason. In July 1989 further testing by AEA confirmed that the process used for the installation of the failed anchors was not acceptable. AEA concluded that all similarly installed anchors were faulty.

Wyman failed to respond to AEA’s request to repair the anchors. In August AEA declared Wyman in default of its contract and called upon Fairmont to remedy the default. In October Fairmont wrote AEA stating that tests had been conducted only on the failed support, and that no tests showed deficiencies actually existed in any other supports. Fairmont suggested that AEA was premature in finding Wyman in default.

In February 1990 Fairmont concluded that it was not liable on the bond because of the time limitations in the bond. 1 Fair-mont filed a complaint against AEA for declaratory relief. AEA filed a counterclaim based on Fairmont’s refusal to honor its bond. In due course Superior Court Judge Dana Fabe granted Fairmont’s motion for summary judgment.

AEA moved for reconsideration of the summary judgment. Also it filed a First Amended Answer and a counterclaim for breach of the duty of good faith and fair dealing. Judge Fabe denied AEA’s motion for reconsideration, entered final judgment in favor of Fairmont, and awarded Fair-mont $15,000 for attorney’s fees. This appeal followed.

II. STANDARD OF REVIEW

The superior court granted summary judgment to Fairmont based on the two-year limitation period in the bond. This is a matter of contract interpretation. Interpretation of a contract is a question of law for which the reviewing court uses independent judgment. Jackson v. Barbero, 776 P.2d 786, 788 (Alaska 1989). “On questions of law, this court is not bound by the lower court’s decision; ... Our duty is to adopt the rule of law that is most persuasive in light of precedent, reason, and policy.” Guin v. Ha, 591 P.2d 1281, 1284 n. 6 (Alaska 1979).

III. DISCUSSION

A. THE TWO-YEAR TIME LIMITATION IN THE PERFORMANCE BOND.

The performance bond includes the following clause:

Any suit under this bond shall be instituted before the expiration of two years from the date on which final payment under the [cjontract falls due.

*422 The superior court found the final payment on the contract was paid on November 10, 1987. No law suit was filed on the bond before November 10, 1989. As AEA failed to sue within two years of the final payment, the superior court ruled AEA’s suit on the bond was time barred.

AEA asserts that the time limitation did not begin to run until Fairmont denied liability on the claim. 2 In Fireman’s Fund Ins. Co. v. Sand Lake Lounge, Inc., 514 P.2d 223, 227 (Alaska 1973), this court concluded that insurance clauses requiring suit to be filed within twelve months of “the inception of the loss” mean that suit must be filed within a year after notification of the decision to deny coverage.

In Fireman’s, the court drew upon the Uniform Commercial Code (UCC) for its analysis. Under the UCC, “parties may reduce the period of limitation to not less than one year” from the time the cause of action accrues. Id. at 227, quoting AS 45.05.042(a) (renumbered as AS 45.02.-725(a)). The court reasoned that the cause of action does not accrue until the claim is denied, and the contract may not limit the right to bring suit to less than a year from that time. Id.

AEA points out that its claim was not denied until February 1990. AEA filed its counterclaim to the declaratory judgment action in July 1990, only six months after the “claim arose.” AEA argues that the contractual time limit may not limit the ability to bring suit to less than one year from the date the claim is denied.

Fairmont argues that the two-year limitation clause is clear and unambiguous. The bond does not create a limit from the date a claim arises, but from the date of the final payment on the contract. Fair-mont argues that as this is a performance bond, the bond’s liability is limited by the date the contract is completed. Fairmont claims there is no dispute that “final payment occurred November 1987.” Fairmont asserts AEA did not institute suit within two years of the final payment, and therefore its exposure had ended.

We agree with Fairmont that the time limitation to bring suit on the bond began running on the day of the final payment. The time limitation provides for two years after the final payment on the contract to file suit if any problems are discovered with the project.

However, our prior decisions have held contractual time limitations to bring suit will not be enforced without some showing of prejudice. Estes v. Alaska Ins. Guar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Courville
368 P.3d 838 (Court of Appeals of Oregon, 2016)
McDonnell v. State Farm Mutual Automobile Insurance Company
299 P.3d 715 (Alaska Supreme Court, 2013)
AAA Valley Gravel, Inc. v. Totaro
219 P.3d 153 (Alaska Supreme Court, 2009)
Pagenkopf v. Chatham Electric, Inc.
165 P.3d 634 (Alaska Supreme Court, 2007)
Old Harbor Native Corp. v. Afognak Joint Venture
30 P.3d 101 (Alaska Supreme Court, 2001)
Long v. Holland America Line Westours, Inc.
26 P.3d 430 (Alaska Supreme Court, 2001)
Alaska Housing Finance Corp. v. Salvucci
950 P.2d 1106 (Alaska Supreme Court, 1997)
Wahl v. Wahl
945 P.2d 1229 (Alaska Supreme Court, 1997)
Second Injury Fund v. Arctic Bowl
928 P.2d 590 (Alaska Supreme Court, 1996)
Jaso v. McCarthy
923 P.2d 795 (Alaska Supreme Court, 1996)
Hillman v. Nationwide Mutual Fire Insurance Co.
855 P.2d 1321 (Alaska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
845 P.2d 420, 1993 Alas. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alaska-energy-authority-v-fairmont-insurance-co-alaska-1993.