Al Johnson Construction Co. v. State

29 Ill. Ct. Cl. 461, 1974 Ill. Ct. Cl. LEXIS 418
CourtCourt of Claims of Illinois
DecidedJune 24, 1974
DocketNo. 6130
StatusPublished

This text of 29 Ill. Ct. Cl. 461 (Al Johnson Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Johnson Construction Co. v. State, 29 Ill. Ct. Cl. 461, 1974 Ill. Ct. Cl. LEXIS 418 (Ill. Super. Ct. 1974).

Opinion

Burks, J.

Claimants in this action seek damages from the State in the amount of $477,894.93. The claim is found upon a contract entered into on June 20, 1967, by and between the respondent and the claimants for bridge pier construction work which was to be performed and which was performed by the claimants.

The issues involved are primarily questions of fact.

A1 Johnson Construction Company of Minneapolis, Minnesota, and the Massman Construction Company of Kansas City, Missouri, engaged in a joint venture under the trade name and style of A1 Johnson-Massman, [hereinafter referred to as "contractor” or "claimants”] for the purpose of bidding on a contract with the State of Illinois, [hereinafter referred to as the "State” or "respondent”] of a substructure of a highway bridge over the Illinois River at Hennepin, [hereafter, "Hennepin Bridge”].

This job was officially known as "Federal Aid Interstate Route No. 180, Project No. 1-180-7(5)0, Sec. (06-3, 78-l)B, in Bureau-Putman Counties, bridge substructure, Contract No. 25074”.

The substructure of the bridge, the subject matter of this contract, consisted of 14 reinforced concrete piers, with abutments on the east and west banks of the Illinois River. These piers were to support a steel superstruction (the roadway portion of the bridge) which would be erected by others under separate contracts.

The State retained Alfred Benesch and Company [hereafter "Benesch”] of Chicago, as design engineer and consultant.

Benesch is an experienced bridge engineer, and the Contractor has over 40 years experience in the heavy construction business.

Early in 1967, the State informed Benesch that it needed a complete design of the Hennepin Bridge within four months so that the bridge could be opened to traffic within a year and a half. Benesch advised the State that it was impossible to procure a complete design in four months, but that it was feasible to have both design and construction completed in a year and a half. Benesch believed that this could be accomplished if the job were bid on preliminary drawings and the final plans furnished as the job progressed after the contract was awarded. It was decided to let the job out for bids on this basis.

In its plans to stimulate the economic development of the Hennepin area, the State had embarked upon the project of constructing a four-lane pavement, including the bridge in question, to an area close to a site where the Jones and Laughlin Steel Company was to place a large plant.

Prior to the opening of the bids, the Contractor had received a letter from the respondent stating this project had been given high priority by the Governor; that the construction had been placed on an expedited schedule; and that, while the Division of Highways would continue to expend every effort to help the Contractor, the completion date must be met.

In order to construct this bridge in the shortest possible time, it was decided to allow the bid to be let on the basis of preliminary typical detailed plans on a unit cost basis, and to furnish the final plans as the work progressed in accordance with a "critical path” to be followed by the contractor and the bridge designer.

Bids were opened on May 26, 1967, and the contract awarded to the claimants, the low bidder, for their bid price of $2,342,186. The contract called for a completion date of April 1, 1968, and provided for liquidated damages of $2,000 per day for late completion.

This job was unusual in that it was the first time the Contractor had bid a job for a governmental agency based upon preliminary plans. It was also the first time the State of Illinois had let a bridge job out for bids without having first completed final construction drawings. [At this point, the court takes notice that this unusual feature of the contract distinguishes the case at bar to some extent from Illinois Steel Bridge Company v. State, 7 C.C.R 75, cited in respondent’s brief.]

The work included in this contract was for the construction and removal of temporary cofferdams;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snead & Co. Iron Works v. Merchants Loan & Trust Co.
80 N.E. 237 (Illinois Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
29 Ill. Ct. Cl. 461, 1974 Ill. Ct. Cl. LEXIS 418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-johnson-construction-co-v-state-ilclaimsct-1974.