Akron Concrete Corp. v. Medina City School Dist. Bd. of Edn.

2012 Ohio 2971
CourtOhio Court of Appeals
DecidedJune 29, 2012
Docket11CA0089-M
StatusPublished
Cited by1 cases

This text of 2012 Ohio 2971 (Akron Concrete Corp. v. Medina City School Dist. Bd. of Edn.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Akron Concrete Corp. v. Medina City School Dist. Bd. of Edn., 2012 Ohio 2971 (Ohio Ct. App. 2012).

Opinion

[Cite as Akron Concrete Corp. v. Medina City School Dist. Bd. of Edn., 2012-Ohio-2971.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF MEDINA )

AKRON CONCRETE CORPORATION C.A. No. 11CA0089-M

Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE THE BOARD OF EDUCATION FOR THE COURT OF COMMON PLEAS MEDINA CITY SCHOOL DISTRICT, et al. COUNTY OF MEDINA, OHIO CASE No. 09CIV2021 Appellant

DECISION AND JOURNAL ENTRY

Dated: June 29, 2012

DICKINSON, Judge.

INTRODUCTION

{¶1} Having worked as a subcontractor for Moser Construction Company Inc. on the

Medina High School building project in 2000, Akron Concrete Corporation filed a mechanic’s

lien against the public funds remaining to be paid on the project after Moser failed to pay Akron

Concrete’s final bill. Akron Concrete waited for years while Moser and the Medina City School

District Board of Education litigated the final amount to be paid on the project. When the School

Board settled that litigation in 2009 by paying Moser from the escrowed funds without paying

the lien, Akron Concrete sued the School Board for violating the lien. After denying the School

Board summary judgment based on the statute of limitations, the trial court found in favor of

Akron Concrete at trial. The School Board has appealed. This Court affirms because Akron

Concrete’s cause of action for violation of the public mechanic’s lien did not accrue, and the 2

statutory time did not begin to run, until the School Board violated the lien by disbursing the

detained funds without satisfying the statutory prerequisites.

BACKGROUND

{¶2} In 2000, the Medina City School Board hired Moser Construction Company to

build the concrete foundations for an addition at the high school. Moser in turn entered into a

contract for Akron Concrete to complete some work on the project. Moser obtained a bond for

the project from Merchants Bonding Company. Although Akron Concrete invoiced Moser every

thirty days, at times Moser made only partial payments, resulting in a deficit to Akron Concrete.

In June 2001, when Akron Concrete completed its work on the project, Moser owed Akron

Concrete a total of $124,146.36 for work on the project.

{¶3} At about the same time, a dispute developed between Moser and the School Board

regarding whether the Board owed Moser any additional money under the contract. Moser

submitted an application for payment of over $35,000, but the School Board disputed that

amount and refused to pay any additional funds to Moser. Having learned of the dispute

between the School Board and the general contractor, Akron Concrete filed an affidavit under

Section 1311.26 of the Ohio Revised Code on September 21, 2001, indicating that Moser owed it

$124,146.36 on the project. The parties agree that Moser did not dispute that claim and later

consented to it via letter dated October 14, 2003.

{¶4} Sometime in 2003, Moser sued the School Board for final payment on the high

school project. Although the parties seem to agree that Akron Concrete’s claim was listed as

part of the damages in that suit, Akron Concrete was never made a party to that litigation. In

March 2009, without admitting liability, the School Board settled the lawsuit with Moser, paying

it $27,428.21 from the escrow account and transferred the remainder of the project funds to its 3

own general fund. The parties agree that the School Board issued a final payment via check

dated March 17, 2009, to Moser Construction Company. They also agree that Akron Concrete

did not consent to that payment from the School Board’s escrow account and there was no court

order authorizing the payment. Seven months later, Akron Concrete sued the School Board and

the bonding company to recover the money it was allegedly owed for work done in 2000 and

2001. Merchants Bonding Company settled with Akron Concrete before trial and, therefore, is

not a part of this appeal.

{¶5} The School Board moved to dismiss Akron Concrete’s complaint under Rule

12(B)(6) of the Ohio Rules of Civil Procedure, arguing that the suit was barred by the statute of

limitations. It argued that, under Section 2305.07 of the Ohio Revised Code, the statute of

limitations expired six years after the cause of action accrued. According to the School Board,

the cause of action accrued in October 2001, after Akron Concrete had perfected its lien and the

statutory time within which the general contractor could dispute the claim had passed. Akron

Concrete opposed the School Board’s motion to dismiss, arguing that the cause of action did not

accrue until the School Board violated the lien by disbursing funds from the escrow account

without paying Akron Concrete the amount of the lien. The trial court denied the School

Board’s motion to dismiss the complaint. Each party filed a motion for summary judgment,

which the trial court also denied.

{¶6} Following a bench trial, the trial court determined that the School Board violated

the public mechanics’ lien laws by paying the settlement amount to Moser from the escrow

account without regard to the valid lien from Akron Concrete. It also held that the action was

not barred by the statute of limitations. Although it determined that the six-year limitations

period provided by Section 2305.07 of the Ohio Revised Code began to run when the lien was 4

perfected in 2001, it also determined that the statute was tolled from 2003 to March 2009 while

the School Board and Moser litigated the issue of how much money remained due and owing to

Moser on the contract. The trial court entered judgment against the School Board in the amount

of $34,146.36. The School Board has appealed.

OHIO’S PUBLIC MECHANICS’ LIEN LAWS

{¶7} Under Ohio law, unpaid subcontractors on a public improvement project may

assert a lien against public funds that are due and payable to the principal contractor by serving

on the public authority an affidavit describing the amount due and when the last work was

performed. R.C. 1311.26. Receipt of the affidavit requires the public authority to detain and

place in escrow the amount stated in the affidavit from subsequent payments to the principal

contractor up to the balance remaining in the contract. R.C. 1311.28. Within five days of

receiving the affidavit, the public authority must serve on the principal contractor a copy of the

affidavit, together with a notice that the principal contractor has twenty days to give notice of its

intention to dispute the claim. R.C. 1311.31. “If the principal contractor fails within twenty

days after receipt of the affidavit to serve to the public authority written notice of his intention to

dispute the claim, he has assented to its correctness . . . .” Id.

{¶8} Under Section 1311.28 of the Ohio Revised Code, once the funds are detained in

an escrow account, they may be released by (1) order of a court of competent jurisdiction, (2)

agreement of the principal contractor and the claimant subcontractor, or (3) default if the

claimant fails to commence suit within sixty days of service of a “notice to commence suit” by

the principal contractor or the public authority as authorized by Section 1311.31.1. The money

may also be released if the principal contractor gives notice to commence suit and secures a bond

in favor of the claimant in an amount equal to one and one-half times the value of the claim. 5

R.C. 1311.31.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cessna v. Landers
2016 Ohio 5551 (Ohio Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 2971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/akron-concrete-corp-v-medina-city-school-dist-bd-o-ohioctapp-2012.