Aja Associates v. Army Corps of Engineers and Charles T. Myers, III

817 F.2d 1070, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20657, 25 ERC (BNA) 2005, 1987 U.S. App. LEXIS 5714, 25 ERC 2005
CourtCourt of Appeals for the Third Circuit
DecidedMay 5, 1987
Docket86-1377
StatusPublished
Cited by31 cases

This text of 817 F.2d 1070 (Aja Associates v. Army Corps of Engineers and Charles T. Myers, III) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aja Associates v. Army Corps of Engineers and Charles T. Myers, III, 817 F.2d 1070, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20657, 25 ERC (BNA) 2005, 1987 U.S. App. LEXIS 5714, 25 ERC 2005 (3d Cir. 1987).

Opinion

OPINION OF THE COURT

STAPLETON, Circuit Judge:

The Army Corps of Engineers (“the Corps”) appeals from the district court’s remand order concerning an application for a dredge-and-fill permit by AJA Associates (“AJA”). Because the applicant has already been given the meaningful opportunity to be heard that due process requires, *1071 we conclude that the district court erred in remanding to the Corps for “an informal oral hearing.” Accordingly, we will instruct the district court to vacate its remand order and consider AJA’s remaining assertions of impropriety in the processing of its application.

I.

AJA owns property on a canal in Key Colony Beach, Florida. On September 21, 1983, the prior owner of AJA’s lot, Glen Cafferty, filed an application with the Corps for a permit to construct a seawall (or “bulkhead”), to backfill behind the seawall, and to dredge the base of the seawall. These activities require a permit under § 404 of the Clean Water Act, 33 U.S.C. § 1344 (1986), and § 10 of the Rivers and Harbors Act of 1899, 33 U.S.C. § 403 (1986). The Jacksonville District of the Corps published a notice describing the application on November 2, 1984. Consideration of the application, number 84R-4588, had been delayed by the Corps until that time because it was negotiating with the City of Key Colony Beach to secure modification of a city ordinance that required seawall construction in the manner presented in the application.

On November 27, 1984, a Corps Area Engineer submitted a report that considered this permit application along with 15 other similar proposals for the construction of bulkheads. The report concluded with respect to application 84R-4588: “Recommend bulkhead be placed at landward edge of wetland zone and a pile supported pier for boat access. Recommend no dredging waterward of bulkhead line.” Record at 51. Thus the report did not support construction of the seawall as proposed.

In response to the public notice, the Environmental Protection Agency, the Fish and Wildlife Service of the Department of the Interior, and the National Marine Fisheries Service of the National Oceanic and Atmospheric Administration submitted comments. Each agency recommended denial of the AJA permit application as well as denial of permits for the 15 other similar projects under consideration. The EPA comment, for example, describes the wetlands at issue in the permit applications as “a valuable public resource.” Wetlands provide “fish and wildlife habitat, hydrological buffering, shoreline stabilization, water purification, pollution and erosion traps, and food chain production.” According to the EPA, “[although the proposed projects would impact only a relatively small area of wetlands, the cumulative effects of many such projects would have a devastating impact on the wetland resources of the Florida Keys.” Record at 67.

Albert Ciardi, a principal in the AJA partnership, then received a letter from an official in the Corps Permit Section dated February 5, 1985, and addressed to Glen Boe, the manager who had actually submitted the permit application for the AJA lot. The letter requested a written response from the applicant addressing the three agency reports that had recommended denial of the application; copies of the three reports were sent along with the letter. In addition to addressing the agency reports, the Corps letter directed the applicant to provide a discussion of (1) the public and private need for the project, (2) why the proposed fill must be located in the wetland resource, and (3) alternative plans that have been considered and why the alternatives are not feasible.

Ciardi’s response states that the private need “is so that I can construct a home.” The public need “is that the project be constructed safely and that a monstrous pier not jut out in the middle of the waterway which can be dangerous to boat traffic.” Ciardi wrote that the seawall must be located in the wetland resource “[bjecause that is where it is.” He stated that he had not considered an alternative site “because I have spent good money for this site; ergo, it would not be feasible to spend money for another site.” Record at 86. Ciardi also wrote:

Having this information in your possession, why don’t you deny the permit so that we can take the matter before the courts and let a Judge make a decision that will determine once and for all the *1072 wisdom of your denial of a permit on a lot which is totally enclosed by two (2) built-up lots with bulkheads on a lagoon which has been in existence for many years without any significant environmental impact whatsoever.

Record at 87. Glen Boe submitted a five-page response to the agency reports, but began with the statement:

The issues surrounding the applications in question, as you well know, have been discussed at great and tedious length for at least a decade. It is difficult to believe that you really want to rehash the hours of discussions, letters, arguments, contentions, inspections, claims, counterclaims, allegations, opinions, suggestions, demands and lamentations that have spewed forth for lo these many years.

Record at 88. A July 30, 1985, letter from Ciardi to the Corps of Engineers complained about the length of time the application process was taking. Ciardi stated, “I am commencing with the construction of my seawall. See you in court!” Record at 119. In all, Ciardi wrote four threatening letters to the Corps. See Record at 86-87, 101-02, 104, 118-19.

On August 5, 1985, the Corps completed its evaluation of the permit application and notified Ciardi that it would not grant a permit. The Corps had prepared a seven-page “Statement of Findings on 84R-4588” for the administrative record. Ciardi apparently received a copy of this statement, which summarized all the information before the Corps and the basis for its decision, along with his notice of permit denial. The Corps found Ciardi’s proposed project “not in compliance with the Corps wetland policy since the area to be filled is considered a vital wetland that constitutes a valuable and productive public resource.” The Corps also concluded that the project was “not in accordance with the 404(b)(1) guidelines since practical alternatives are available for shoreline protection.” The permit was denied because the proposed work “would have an unacceptable adverse impact on an important public resource by destroying wetland vegetation and productive seagrasses.” Record at 127. The notice to Ciardi, signed by Colonel Charles Myers of the Corps, stated, “I have evaluated your application and the cumulative impacts of permitting many other such applications in the city of Key Colony Beach and have determined there would be an adverse cumulative impact on the environment if these permits were issued.” Record at 128.

On September 4, 1985, AJA filed suit in district court, seeking to set aside the permit denial. AJA asserted that the Corps’ action was arbitrary and thus not in accordance with law, and that the Corps unlawfully delayed evaluation of the permit application.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisa Papotto v. Hartford Life & Accident Insur
731 F.3d 265 (Third Circuit, 2013)
Hard Rock Café v. Lee
54 V.I. 622 (Supreme Court of The Virgin Islands, 2011)
Government of the Virgin Islands Ex Rel. Larsen v. Ruiz
145 F. Supp. 2d 681 (Virgin Islands, 2000)
Kreider Dairy Farms, Inc. v. Glickman
190 F.3d 113 (Third Circuit, 1999)
Torres v. Chater
Third Circuit, 1997
Employers Insurance of Wausau v. Browner
848 F. Supp. 1369 (N.D. Illinois, 1994)
Bridge v. United States Parole Commission
981 F.2d 97 (Third Circuit, 1992)
O'Connor v. Corps of Engineers, United States Army
801 F. Supp. 185 (N.D. Indiana, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
817 F.2d 1070, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20657, 25 ERC (BNA) 2005, 1987 U.S. App. LEXIS 5714, 25 ERC 2005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aja-associates-v-army-corps-of-engineers-and-charles-t-myers-iii-ca3-1987.