AISG, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 23, 2015
DocketASBCA No. 58696, 59151
StatusPublished

This text of AISG, Inc. (AISG, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AISG, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) AISG, Inc. ) ASBCA Nos. 58696, 59151 ) Under Contract No. W5J9JE-10-C-0039 )

APPEARANCES FOR THE APPELLANT: Karl Dix, Jr., Esq. J. Daniel Puckett, Esq. Steven J. Stuart, Esq. Smith Currie & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney James A. Wallace, Esq. Daniel B. McConnell, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE DICKINSON ON APPELLANT'S SUPPLEMENTAL MOTION FOR SUMMARY JUDGMENT

This appeal 1 arises under a contract awarded by the Corps of Engineers (government) to AISG, Inc. (AISG or appellant), for the construction of a secure walled police station in Sar Hawza, Paktika Province, Afghanistan. Appellant has moved for summary judgment, arguing that there are no material facts in dispute and that it is entitled, as a matter of law, to an equitable adjustment for additional costs in the amount of $841,243.39 incurred as a result of the government's alleged failure to provide an appropriate building site for construction of the police station. The government opposes the motion. The record before us on the motion consists of the Rule 4 file and exhibits to the parties' filings on the motion.

1 This appeal is from a deemed denial (SOF if 30). Appellant's initial motion for summary judgement was filed prior to receipt of a contracting officer's final decision (COFD). After receipt of a COFD, appellant requested and, without objection, was granted permission to file this supplemental motion for summary judgement which replaces the original motion. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. Firm-fixed-price Contract No. W5J9JE-10-C-0039 was awarded by the government to AISG on 3 September 2010 in the amount of $2,148,243 for the construction of a one-story police station in Sar Hawza, Paktika Province, Afghanistan, and $52,000 for demolition of some existing structures. The period of performance was 365 days plus 65 weather days for a total of 430 days. (R4, tab 2 at 3) AISG was required to commence work under the contract within 10 days after issuance of the Notice to Proceed (id. at 10).

2. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 2 at 8-9).

3. The record before us on the motion does not contain the Statement of Work (SOW) or more than a very few isolated pages of the contract specifications, either as originally awarded or as modified. It is undisputed that the site upon which the police station was to be constructed was to be provided by the government and that AISG was to adapt the provided site to meet the contract requirements (R4, tabs 4, 7, 12, 14-16, 19, 34, 37, 57; SOF ~ 17).

4. It is also undisputed that, after award of the contract, it was discovered that the adjacent coalition forces installation had encroached on the planned building site (Location #1) (R4, tab 19, see also tab 35). By letter dated 5 November 2010 the government issued a suspension of work notice, citing FAR 52.242-14.

You are also hereby restricted from incurring any additional cost against this portion of the contract. It is the intention of the U.S. Army Corps of Engineers to follow up this letter with additional technical direction concerning this project site. The Suspension of Work will end upon written notice from the Contracting Officer or Administrative Contracting Officer.

(R4, tab 11, see also tab 35) The notice was acknowledged in writing by AISG.

5. In a 5 March 2011 Site Investigation Report, Corps project engineer Sokoloski stated that the "local Sub Governor" had requested that the site for the police station "should be located at the hill location closer to the village" and included the coordinates for the hill location as well as photos of the site. This location is hereinafter referred to as Location #2. The 5 March 2011 Site Investigation Report stated:

2 5. Benefits of moving ANP HQ to site location on top of hill:

5.1 Site is preferred by local officials and US Army. 5.2 Site is closer to village of Sar Hawza and will most likely improve security for citizens. 5 .3 The site has little to no obstructions for construction activities. 5 .4 Construction activities can begin as soon as new site assessment is completed.

6. Potential cost of moving site to hill location:

6.1 Cost of bring [sic] materials up the hill, the road is not level and erodes rapidly during heavy rain and snow. 6.2 Possible time lost when road is not passable for materials and supplies.

7. The proposed new site location appears to be an acceptable location if water is readily available at the. site. The presence of water in the nearby area seems [to] be an indication that water could be found on the proposed site. The project could move forward if this site is chosen and the site assessment is completed in a timely manner. Project Engineer recommends relocating the site to hill location if site assessment agrees that no adverse land ownership issues are present and water can be expected at site location.

(R4, tab 14 at 3-4, see also tab 19)

6. The 28 May 2011 Site Assessment Report, prepared for the government by JQ Builders, states in pertinent part:

1. INTRODUCTION

JQ [B]uilders have completed Site Assessment of approximately 6400[]sqm parcel land for SAR HAWZA UP DHQ facility in SAR HA WZA District, Pakti[k]a Province Afghanistan, for the Ministry of Interior (Mol). The site is located at the District Center; currently there is an ANP police post at the center of the proposed site.

3 The site visit was conducted at the end of April 2011 for the Uniform Police District Headquarter (UP DHQ)

This effort was preliminary to a Master Planning effort including assessment of the following

1. Land Ownership 2. Adjacent Land Use 3. General Availability of Utilities on Site 4. Site Condition 5. Access Roads 6. Availability of Construction Materials and Labor 7. Availability [of] Clinics, Fuel and Public Transportation

3.2. Site Ownership

The proposed site is Government property belongs to Mol according Government officials, Land Documents are signed by the following Government officials.

Government officials and Coalition forces officials at the region proved that the proposed land is Government property and Mol should proceed for construction at the same site.

1. Verified and signed by - Mol facility Department Director 2. Verified and signed by - CPT Dale Marrou 3. Verified and signed by - Deputy Provincial Governor - Haji Mohamad Zadran 4. Verified and signed by - Sub-Governor - Haji Khan 5. Verified and signed by - District Police Commander - Abdul Wahid Kandari 6. Verified and signed by - Provincial Police Chief - Daulat Khan 7. Verified and signed by - Zone Commander - "Gul Nabi" Ahmad Zai 8. Verified and signed by - Member of Agriculture Department - Mir Zajan 9. Verified and signed by - Member of Amlam Department - Mr. Agha Mohammad

4 10. Verified and signed by- Director of Agriculture: Hamidulluah

JO team has verified the Land from every aspect and signed by all possible government officials and local elders.

3.8 ... Over all security situation is bad at the region.

(R4, tab 15) The Site Assessment Report includes 20 pages of copies of "GOVERNMENT LETTERS & LAND OWNER SHIP CERTIFICATES" (R4, tab 15 at 5-24), as well as various photos of the site.

7.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
AISG, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aisg-inc-asbca-2015.