Airtex Manufacturing LLLP v. Boneso Brothers Construction, Inc.

CourtDistrict Court, D. Kansas
DecidedJuly 28, 2021
Docket2:19-cv-02269
StatusUnknown

This text of Airtex Manufacturing LLLP v. Boneso Brothers Construction, Inc. (Airtex Manufacturing LLLP v. Boneso Brothers Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airtex Manufacturing LLLP v. Boneso Brothers Construction, Inc., (D. Kan. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS

AIRTEX MANUFACTURING LLLP,

Plaintiff,

v. Case No. 2:19-cv-02269-HLT-JPO

BONESO BROTHERS CONSTRUCTION, INC.,

Defendant.

MEMORANDUM AND ORDER This is a contract dispute between Plaintiff Airtex Manufacturing and Defendant Boneso Brothers Construction. Airtex alleges breach of contract and unjust enrichment against Boneso. Boneso asserts various counterclaims, including a claim for declaratory judgment regarding which document is the controlling contract between the parties. Boneso seeks partial summary judgment that a 2012 agreement controls and contends that ruling would require this case to either be sent to arbitration or transferred to California. For the reasons stated below, the Court denies Boneso’s motion because it seeks a ruling on a claim it has not asserted and there are disputed questions of fact. The Court also finds that neither arbitration nor transfer is appropriate given disputed questions of fact. Boneso’s request for attorneys’ fees is denied. I. BACKGROUND1 This dispute arises out of a construction project for the United States Army Corps of Engineers (“USACE”) in California. The project was originally bid in 2012. But it was canceled

1 For purposes of summary judgment, the Court considers the following undisputed facts. The Court notes that it appears Boneso’s response to Airtex’s additional statement of facts is off by one beginning at additional fact 17. This is based on the fact that Boneso’s reply contains responses to 35 additional facts where there are only 34 and also on the context of the responses. Although the Court concludes there are disputed issues of fact, this is not based on the apparent misnumbering. and rebid in 2014. The USACE entered into a contract with Watts Constructors, LLC. Watts then subcontracted with Boneso. Boneso subsequently sought an agreement with Airtex for Airtex to supply HVAC units for the project. In other words, Watts is the contractor, Boneso is the sub- contractor, and Airtex is the sub-sub-contractor. See Doc. 73 at 1. A. 2012 Negotiations

In 2012, Airtex sent a quote to Boneso to manufacture and supply HVAC units for the project. In response, Boneso sent a purchase order to Airtex. Airtex then sent a purchase order acknowledgement to Boneso. Airtex, through its division manager Henry Berman, also sent Boneso a memorandum stating that the terms of Boneso’s purchase order were in conflict with the terms of Airtex’s quote and purchase order acknowledgment. Airtex rejected Boneso’s purchase order. In response, Boneso rejected Airtex’s purchase order acknowledgment. Airtex, again through Berman, then sent another memorandum to Boneso, which addressed some terms and conditions the parties disagreed on and tried to reach a mutual solution. Boneso sent Airtex a revised purchase order (“2012 Revised Purchase Order”), along with an email stating,

“As discussed previously we not be [sic] incorporating your Purchase Order Acknowledgement and or EA Terms and Conditions as an attachment to our Purchase Order as that is not consistent with our Company Policies.” No one from Boneso ever told Berman that Boneso would accept Airtex’s purchase order acknowledgment or Airtex’s additional terms and conditions. But Boneso’s 2012 Revised Purchase Order did reflect the changes requested by Airtex to Boneso’s original purchase order. Airtex did not make any other revisions to the 2012 Revised Purchase Order, and it was approved by Airtex’s president. The 2012 Revised Purchase Order included a term regarding attorneys’ fees arising out of disputes. The 2012 Revised Purchase Order also included the following provision: “This purchase order consists of this Agreement, and the applicable terms, conditions, plans and specifications of the Prim [sic] Contract.” As discussed below, the parties dispute what “Prim Contract” refers to.2 The USACE eventually shut down the project in 2012. B. 2014 Negotiations In 2014, the USACE renewed the project. Airtex again sent Boneso a quote to supply

HVAC units. The quote stated, “Buyer may offer to purchase the goods quoted herein by submitting a purchase order. Such purchase order is subject to the Terms established by any financing of this order by [Airtex] and the Terms and Conditions of [Airtex]’s Purchase Order Acknowledgment.” In response, Boneso sent Airtex a purchase order (“2014 Purchase Order”). There are differences between the 2014 Purchase Order and the 2012 Revised Purchase Order. The total price of the 2014 Purchase Order was $1,449,398.40, while the total price in the 2012 Revised Purchase Order was $1,117,200. The shipping instructions were “FOB Truck” in the 2014 Purchase Order, while the instructions were “FOB Destination” in the 2012 Revised Purchase Order.” The 2012 Revised Purchase Order also included a reference to “S.C. Anderson,

Inc.” And the 2012 Revised Purchase Order identifies different equipment model numbers than what Airtex ultimately manufactured and supplied for the project in 2014. But like the 2012 Purchase Order, the 2014 Purchase Order included a provision regarding attorneys’ fees arising out of disputes and stated: “This purchase order consists of this Agreement, and the applicable terms, conditions, plans and specifications of the Prim [sic] Contract.” Again, the parties dispute what the “Prim Contract” is. Airtex contends it refers to the contract between the USACE and Watts (which does not contain an arbitration provision). Boneso contends it refers

2 The parties seem to agree that “Prim Contract” is a typo, and that the intended phrase is “Prime Contract.” But as discussed below, the parties dispute which contract is the prime contract. to the contract between Watts and Boneso (which does contain an arbitration provision). Airtex and Boneso never discussed arbitration when negotiating the project in 2012 or 2014. The parties also dispute whether Airtex sent Boneso a 2014 Purchase Order Acknowledgment (hereinafter referred to as the “2014 Acknowledgment”) in response to the 2014 Purchase Order. Airtex maintains it sends out acknowledgements as a matter of course for every

transaction, and Airtex has a copy of the 2014 Acknowledgment in its files. But it has searched its records to find evidence that the 2014 Acknowledgment was sent to Boneso and cannot find any evidence it was. Airtex has provided an affidavit by Berman stating that it “would not surprise [him]” if the 2014 Acknowledgment was mailed or emailed to Boneso, that it was lost in the mail, that it was sent via email but later deleted by both parties, or that Boneso did in fact receive it but has not produced it in discovery. See Doc. 97-6 at 3. But Berman also testified that it would not surprise him if the 2014 Acknowledgment had never even been sent to Boneso. Berman was the only Airtex representative communicating with Boneso about this contract. The 2014 Acknowledgment also states: “ANY MODIFICATIONS OF THIS PURCHASE

ORDER ACKNOWLEDGMENT MUST BE NOTED AND RETURNED TO SALES OFFICE ABOVE WITHIN THREE (3) DAYS OF RECEIPT OF THIS ACKNOWLEDGEMENT.” Airtex never received any written objections, though again, the parties dispute whether the 2014 Acknowledgment was ever sent to Boneso. The 2014 Acknowledgement also states that a signature from a buyer is not required if the buyer’s credit application is on file. As of the date of the 2014 Acknowledgement, Airtex had Boneso’s credit application on file. The credit application states that “Buyer agrees to be bound by the terms and conditions of [Airtex’s] Purchase Order Acknowledgement (‘POA’).” But Boneso had crossed out “conditions of [Airtex’s] Purchase Order Acknowledgment,” and crossed out other provisions that said, “Buyer expressly agrees to said terms and conditions” and “upon Buyer’s acceptance of said terms and conditions.” C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Airtex Manufacturing LLLP v. Boneso Brothers Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/airtex-manufacturing-lllp-v-boneso-brothers-construction-inc-ksd-2021.