Air Energy TCI, Inc. v. County of Cortland

39 Misc. 3d 234
CourtNew York Supreme Court
DecidedDecember 14, 2012
StatusPublished

This text of 39 Misc. 3d 234 (Air Energy TCI, Inc. v. County of Cortland) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air Energy TCI, Inc. v. County of Cortland, 39 Misc. 3d 234 (N.Y. Super. Ct. 2012).

Opinion

OPINION OF THE COURT

Phillip R. Rumsey, J.

Petitioner proposes to develop a project in the Towns of Cortlandville, Homer, Solon and Truxton in Cortland County, to generate electricity from wind, which it identifies as the Crown City Wind Energy Project (the project). The project is believed to be the largest ever proposed for Cortland County and includes construction of 44 wind turbines that are 492 feet tall, over 20 miles of access roads, 30 miles of buried high-voltage electric transmission lines and one-half mile of overhead electric transmission lines. Approximately 56 acres of land would be permanently occupied by the project. It would also have significant temporary impacts during the anticipated nine-month construction phase; for example, the existing public roads leading to the project site are not adequate to permit transportation of the necessary components — expected to require more than 21,000 loaded truck trips — requiring widening of six road intersections and reinforcement of three culverts or bridges.

Petitioner first identified the opportunity to develop the project in 2007. It commenced the State Environmental Quality Review Act (SEQRA) process by submitting an environmental assessment form (EAF) to respondent in November 2008, which declared itself lead agency on December 18, 2008. As lead agency, respondent has acted through its County Legislature which, in turn, has referred matters to its Agriculture, Planning and Environment Committee for consideration prior to action. Petitioner represents that the project is financially viable only if it obtains a renewable energy credit (REC) contract from the New York State Energy Research and Development Agency (NYSERDA) which, in turn, requires that the project achieve commercial operation — i.e., sale of electricity — by the end of 2015. To connect to New York’s high-voltage electricity transmission network, petitioner must obtain a permit from the New York Independent System Operator (NYISO). Petitioner filed an interconnection application with NYISO in November 2008 and undertook the required feasibility study and system reliability impact study (SRIS) at a' cost exceeding $200,000. NYISO ac[236]*236cepted the SRIS on October 7, 2010. NYISO’s tariff requires that an applicant notify NYISO, within two years from acceptance of the SRIS, that it has received from the lead agency conducting SEQRA review a determination that a draft environmental impact statement (DEIS) is adequate (notification of NYISO that the lead agency has determined that the DEIS is adequate is referred to by petitioner as a regulatory milestone).1 An interconnection application is deemed withdrawn upon a failure to meet the regulatory milestone. In this case, petitioner’s failure to meet the regulatory milestone will prevent it from achieving commercial operation by the end of 2015 as required to obtain the REC from NYSERDA.

Petitioner claims that respondent agreed in June 2009 that scoping would not be required. Respondent denies that it ever agreed to forgo scoping, and notes that the Public Service Commission reviewed the EAF and recommended a full public scoping process (see aff of Kathie Arnold, sworn to Dec. 3, 2012 [Arnold aff] ¶ 8, exhibit D). Petitioner had little contact with respondent or its representatives regarding SEQRA from 2009 until April 2012 (see aff of Patrick M. Snyder, sworn to Dec. 3, 2012 [Snyder aff] ¶ 9; aff of Brett O’Connor, sworn to Nov. 20, 2012 [O’Connor aff] ¶¶ 32, 40, 44). Petitioner alleges that it began meeting with county officials, beginning in April 2012, to discuss the procedure for obtaining the necessary approvals. In May 2012, petitioner engaged “edr Companies” to complete the DEIS on its behalf. On May 30, 2012, respondent determined that scoping would be required. Petitioner agreed to submit a draft scoping document, which was submitted to the Agriculture, Planning and Environment Committee on July 3, 2012. A final scope was adopted by the legislature on September 13, 2012. On September 17, 2012, petitioner submitted a proposed DEIS comprised of four volumes of material.

By letter dated October 11, 2012 (see petition, exhibit 4), NYISO formally notified petitioner that its interconnection application had been deemed withdrawn for failure to meet the regulatory milestone and advised that it had a 15-business-day grace period to cure the deficiency, which would expire on November 1, 2012. Petitioner requested action on the proposed DEIS prior to expiration of the grace period, inasmuch as a determination of adequacy within that time frame would permit it [237]*237to satisfy the regulatory milestone. At a special meeting held on October 30, 2012, the legislature — by a vote of 17-2 — adopted Resolution No. 342-12 determining that the DEIS was incomplete.

On November 1, 2012, petitioner applied to the Federal Energy Regulatory Commission (FERC) seeking a 45-day extension of the regulatory milestone. If granted, the waiver application would extend petitioner’s deadline for meeting the regulatory milestone through December 16, 2012.2 Petitioner submitted revisions to the DEIS to respondent and, by letter received by respondent on November 16, 2012, requested a determination of adequacy for public review of the DEIS as supplemented by its revisions. Under applicable SEQRA guidelines, respondent is required to make a determination on petitioner’s resubmission by December 16, 2012 — the same day that the extended regulatory milestone will expire if the waiver application is granted.

Petitioner commenced this proceeding on November 21, 2012 seeking a judgment annulling the legislature’s resolution of October 30, 2012 that declared the DEIS to be incomplete (Resolution No. 342-12) and a declaration that the DEIS is adequate for public review under SEQRA. Petitioner asserts that further resort to administrative procedure would be futile and, furthermore, that it would be irreparably harmed if an adequacy determination is not made prior to December 16, 2012, because failure to satisfy the regulatory milestone means that it would be unable to meet the requirements necessary to obtain the REC, which is necessary for the project to be financially viable.

The first question presented is whether the issues presented in this proceeding are ripe for review, which depends upon several considerations.

“First, the action must ‘impose an obligation, deny a right or fix some legal relationship as a consummation of the administrative process’ (Matter of Essex County v Zagata, 91 NY2d 447, 453 [1998], quoting Chicago & S. Air Lines v Waterman S.S. Corp., 333 US 103, 113 [1948]). In other words, ‘ “a pragmatic evaluation [must be made] of whether the ‘decisionmaker has arrived at a definitive posi[238]*238tion on the issue that inflicts an actual, concrete injury’ ” ’ (Essex County, 91 NY2d at 453 [citations omitted]). Further, there must be a finding that the apparent harm inflicted by the action ‘may not be “prevented or significantly ameliorated by further administrative action or by steps available to the complaining party” ’ (Essex County, 91 NY2d at 453 [citations omitted]).” (Matter of Gordon v Rush, 100 NY2d 236, 242 [2003] [footnote omitted].)

Under the foregoing standards, a decision to reject an applicant’s proposed DEIS as inadequate is an interim ruling that is not ripe for review until the decision making process is completed (see Matter of Sour Mtn. Realty v New York State Dept. of Envtl. Conservation,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Homefront Organization, Inc. v. Motz
570 F. Supp. 2d 398 (E.D. New York, 2008)
Essex County v. Zagata
695 N.E.2d 232 (New York Court of Appeals, 1998)
Missere v. Gross
826 F. Supp. 2d 542 (S.D. New York, 2011)
Honess 52 Corp. v. Town of Fishkill
1 F. Supp. 2d 294 (S.D. New York, 1998)
New York Public Interest Research Group, Inc. v. Carey
369 N.E.2d 1155 (New York Court of Appeals, 1977)
Gordon v. Rush
792 N.E.2d 168 (New York Court of Appeals, 2003)
Demers v. New York State Department of Environmental Conservation
3 A.D.3d 744 (Appellate Division of the Supreme Court of New York, 2004)
Guido v. Town of Ulster Town Board
74 A.D.3d 1536 (Appellate Division of the Supreme Court of New York, 2010)
East Clinton Developers, Inc. v. Town of Clinton
88 A.D.2d 416 (Appellate Division of the Supreme Court of New York, 1982)
Wal-Mart Stores, Inc. v. Campbell
238 A.D.2d 831 (Appellate Division of the Supreme Court of New York, 1997)
Sour Mountain Realty, Inc. v. New York State Department of Environmental Conservation
260 A.D.2d 920 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
39 Misc. 3d 234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-energy-tci-inc-v-county-of-cortland-nysupct-2012.