Ahwatukee Custom Estates Management Ass'n v. Bach

952 P.2d 325, 191 Ariz. 87
CourtCourt of Appeals of Arizona
DecidedMarch 17, 1998
Docket1 CA-CV 96-0573
StatusPublished
Cited by3 cases

This text of 952 P.2d 325 (Ahwatukee Custom Estates Management Ass'n v. Bach) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahwatukee Custom Estates Management Ass'n v. Bach, 952 P.2d 325, 191 Ariz. 87 (Ark. Ct. App. 1998).

Opinion

OPINION

LANKFORD, Judge.

Daniel Bach (“Bach”) appeals from the permanent injunction and judgment entered in favor of the Ahwatukee Custom Estates Management Association, Inc. (“ACEMA”). For the reasons discussed below, we affirm the judgment against Bach on the property issue, as well as the award of non-taxable costs to ACEMA.

At the time of the trial court proceedings, Bach owned two lots in Ahwatukee Custom Estates-8. Both properties are subject to the ACEMA Declaration of Covenants, Conditions and Restrictions (“CC & Rs”). In January 1995, the ACEMA Property Manager discovered that Bach had built perimeter fences on each property that exceeded eleven feet in height. The CC & Rs limit the height of such fences to six feet. Additionally, Bach built the fences and brick pilasters on one of the properties without first obtaining approval from the ACEMA as required by the CC & Rs.

Between February and June 1995, ACE-MA made five requests to Bach to submit the plans and specifications for the disputed improvements to the ACEMA Board for possible retroactive approval. On July 12, 1995, Bach submitted plans to ACEMA that did not provide sufficient detail, such as the height of the fence walls. The parties were unable to resolve the dispute and ACEMA filed this lawsuit against Bach seeking injunctive relief requiring him to bring his properties into compliance with the CC & Rs. Bach counterclaimed, arguing that ACEMA had arbitrarily failed to adequately consider and approve the improvements.

In December 1995, the court held a consolidated preliminary and permanent injunction hearing and trial on the merits. At this proceeding, the parties agreed to resubmit the issues to the ACEMA Board for reconsideration. Pursuant to this stipulation, the trial court issued an order: (1) resetting the trial for February 9, 1996; (2) requiring Bach to submit the as-built plans of the fence and pilasters to ACEMA by December 29, 1995; (3) requiring the ACEMA Board to schedule an on-site inspection of Bach’s property by January 6, 1996; and (4) requiring the Board to consider Bach’s request for a variance on January 6, 1996. The order stated that a “willful failure to comply with any provision by any party will result in a citation for contempt.” The order did not specify a deadline for ACEMA’s written decision to Bach.

Bach submitted the documentation as required, and ACEMA inspected his property on January 6, 1996. On February 2, 1996, ACEMA informed Bach that it was granting some of his requested variances, but requiring him to remove the pilasters and decrease the height of certain parts of the fence.

The case proceeded to a bench trial. Because of time constraints, the parties submit *89 ted written closing argument memoranda. In Bach’s memorandum, he argued for the first time that the CC & Rs required ACE-MA to issue a decision on his requested improvements within thirty days from the date of his submission of the plans, and that ACEMA’s failure to do so resulted in mandatory approval of the improvements. 1 Bach relies on Article II, paragraph 7 of the CC & Rs, the provision governing a homeowner’s submission of plans to the ACEMA Board for approval.

The trial court ruled in ACEMA’s favor on the fence height issue, and in Bach’s favor on the pilaster issue. The court’s ruling did not specifically address Bach’s argument that his plans were “deemed approved” by the ACE-MA’s late ruling.

Thereafter, ACEMA moved for its attorney’s fees and costs as the prevailing party in an action arising out of contract, relying on both a provision in the CC & Rs and Arizona Revised Statutes Annotated (“A.R.S.”) section 12-341.01(A). Bach objected to that request, particularly to ACEMA’s request for non-taxable costs, arguing that they were not recoverable under either the CC & Rs or the statute. 2 The trial court granted ACEMA’s motion and awarded it fees and costs, including $1,813.27 in non-taxable costs, and entered judgment in its favor. Bach filed this appeal. We have jurisdiction pursuant to A.R.S. section 12-2101(B).

We address the following issues on appeal:

1. Were the improvements deemed approved when ACEMA failed to give written disapproval within thirty days after Bach’s submission of his plans?
2. Did the trial court err in awarding non-taxable costs to ACEMA?

I.

We first address Bach’s argument that the CC & Rs required ACEMA to issue a decision on his requested improvements within thirty days from the date of his submission of the plans, and that ACEMA’s failure to do so resulted in mandatory retroactive approval of his improvements. In support of this argument, he relies on Article II, paragraph 7 of the CC & Rs, which provides in pertinent part:

The Board shall have wide discretion in approving or disapproving plans and specifications to aid and promote the harmonious development and maintenance of the Custom Estates for the benefit of Developer and all lot owners.
In the event the Board does not give written disapproval within thirty (30) days after plans and specifications have been submitted to it at its business address the said plans and specifications shall be deemed approved and this restriction satisfied.

We disagree with Bach’s contention for several reasons.

First, Bach did not timely raise this issue and therefore waived its review. ACE-MA issued its decision on the improvements on February 2,1996. Bach did not challenge the timeliness of ACEMA’s decision until he filed his closing argument memorandum on June 17, 1996, after the close of the trial. The parties filed contemporaneous closing argument memoranda, 3 and ACEMA never had an opportunity to address this issue.

Because Bach did not diligently pursue this argument and forced ACEMA to incur the expense of a trial which he now effectively claims was unnecessary, and because he failed to provide ACEMA with an opportuni *90 ty to respond to this argument in the lower court, it would have been inequitable for the trial court to have ruled in his favor on this issue. See, e.g., Payne v. Payne, 12 Ariz. App. 434, 435, 471 P.2d 319, 320 (1970) (“[A] party must timely present his legal theories to the trial court so as to give the trial court an opportunity to rule properly[;] ... a matter raised for the first time on appeal will not be considered.”).

Bach, not ACEMA, first breached the CC & Rs by failing to submit plans for the improvements to ACEMA for approval prior to their construction as required by the CC & Rs, and by building fences which violated the height limitation set forth in the CC & Rs. He also initially failed to submit his plans for the improvements for retroactive approval post-construction despite repeated requests by ACEMA, and the plans he finally submitted to ACEMA failed to provide sufficient detail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage of Fuentes v. Fuentes
97 P.3d 876 (Court of Appeals of Arizona, 2004)
Ahwatukee Custom Estates Management Ass'n v. Bach
973 P.2d 106 (Arizona Supreme Court, 1999)
Inzunza-Ortega v. Superior Court
968 P.2d 631 (Court of Appeals of Arizona, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
952 P.2d 325, 191 Ariz. 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahwatukee-custom-estates-management-assn-v-bach-arizctapp-1998.