Ago

Florida Attorney General Reports·Decided April 29, 1980·Published

Opinion

Elton Gissendanner Executive Director, Department of Natural Resources Tallahassee

QUESTIONS:

1. Does the 1-year period of time required under s. 4(2)(b), ch. 79-167, Laws of Florida, run from the effective date of the act (upon deauthorization by the United States Congress), or does it run from July 1, 1979, both as provided in s. 16 of the act?

2. Pursuant to s. 15 of the act in question, can the canal authority at the present time expend authority funds by entering into a contract with the Department of Natural Resources for the development of the management plan required by s. 4(2)(b) of this act, and, if so, what funds can the canal authority utilize for this purpose?

3. Does that resolution restrict use of the funds beyond statutory requirements and, if so, how can this be corrected?

SUMMARY:

There is no specific deadline for the management plan regarding Lake Ocklawaha or Rodman Reservoir as required by s.253.783(2)(b), F. S.; the canal authority may expend authority funds for a contract with the Department of Natural Resources for the development of the management plan.

AS TO QUESTION 1:

Your first question asks my opinion whether the management plan required by s. 4(2)(b), ch. 79-167, Laws of Florida, concerning the retention of Rodman Reservoir, also known as Lake Oklawaha, is to be developed within 1 year of July 1, 1979, or within 1 year of the effective date of ch. 79-167, which date is the effective date of deauthorization by the United States Congress of the Cross Florida Barge Canal Project.

Section 4(2) of ch. 79-167, supra, now codified as s. 253.783(2), provides for the development of two different management plans relative to the retention or disposition of lands owned by the Cross Florida Barge Canal Authority. Section 253.783(2)(a), F. S., requires a management plan to be developed for the retention or disposition of lands acquired for the Cross Florida Barge Canal and not disposed of by ch. 79-167. Specifically, this statute describes a geographical area of lands not disposed of by said chapter and appears to exclude in this geographical description the lands included for study in the management plan described in s. 253.783(2)(b) relating to Lake Ocklawaha. Furthermore, the lands included for study in the management plan described in s.253.783(2)(b) relating to Lake Ocklawaha have been effectively `disposed of' pursuant to s. 2, ch. 79-167. See s. 253.781, F. S. Thus, it is evident that the two management plans are separate plans dealing with separate parcels of land.

The second management plan relating to Lake Ocklawaha, s.253.783(2)(b), F. S., is described as follows:

[The Department of Natural Resources shall d]evelop a management plan for the lands comprising the Rodman Dam and Rodman Reservoir, also known as Lake Ocklawaha, identifying the recreational and scientific management options which are most environmentally desirable and cost-effective. Such management plan shall contain a specific determination regarding the continued maintenance of the Rodman Dam and Reservoir (Lake Oklawaha) or the drainage of the reservoir and restoration of the area to its former natural state, as the case may be.

Section 253.783(2)(a), F. S., provides that the management plan required by this paragraph be submitted to the Legislature no later than 1 year from the effective date of ch. 79-167, Laws of Florida, which date is the effective date of the deauthorization of the Cross Florida Barge Canal Project by the United States Congress. On the other hand, the management plan required with regard to the study of Lake Ocklawaha, s. 253.783(2)(b), contains no such time limitation. No time constraints are specified for development of the latter management plan, nor can I infer any time limitation on such development based on the contextual placement of this provision in the statute. Instead, the Legislature provided as follows:

The Canal Authority is authorized to enter into a contract with the Department of Natural Resources for development of the management plans required by s. 253.783(2)(a) and (b). [Section 374.002, F. S.]

Said s. 374.002, F. S., by the terms of s. 16, ch. 79-167, became effective on July 1, 1979. Thus, effective July 1, 1979, the canal authority is authorized to contract with the Department of Natural Resources so that the department can develop both management plans required by s. 253.783(2). However, the only time constraint imposed on the canal authority and the Department of Natural Resources is that contained in s. 253.783(2)(a), that is, a time limit to develop the management plan for disposition or retention of lands specified in s. 253.783(2)(a) no later than 1 year from the effective date of ch. 79-167, which date is the effective date of the congressional deauthorization of the Cross Florida Barge Canal Project. Stated another way, the authorization for development of the management plan regarding Lake Ocklawaha or Rodman Reservoir is granted, effective July 1, 1979, with no specific deadline imposed by the Legislature within which to complete such management plan.

AS TO QUESTIONS 2 AND 3:

The first part of question 2 relating to expenditure of funds to contract with the Department of Natural Resources is answered in the affirmative.

Section 374.002, F. S., provides as follows:

The Canal Authority is authorized to enter into a contract with the Department of Natural Resources for the development of the management plans required by s. 253.783(2)(a) and (b).

Section 253.783(2)(a) and (b) provides:

(2) It is declared to be in the public interest that the department shall do and is hereby authorized to do any and all things and incur and pay from the Cross Florida Barge Canal Trust Fund, for the public purposes described herein, any and all expenses necessary, convenient, and proper to:

(a) Develop a management plan to be submitted to the Legislature no later than 1 year from the effective date of this act for the retention or disposition of lands acquired for the Cross Florida Barge Canal and not disposed of by this act, which plan shall reflect a consideration of alternatives for disposition of all lands in fee or less than fee owned by the Board of Trustees of the Internal Improvement Trust Fund, including those previously owned by the Canal Authority and the U.S. Army Corps of Engineers, from the western boundary of the expanded Ocala National Forest west to U.S. Highway 41, the Cross Florida Barge Canal right-of-way from the Withlacoochee River west to the Gulf of Mexico, and from the eastern boundary of the expanded Ocala National Forest, as depicted by the map referred to in s. 253.781(2), east to the St. Johns River. Such alternatives for disposition will include possible retention by any interested state agency for specific public purposes and a declaration of lands not to be retained as surplus lands to be disposed of pursuant to paragraph (d), paragraph (e), or paragraph (f).

Free access — add to your briefcase to read the full text and ask questions with AI

Ago, (Fla. 1980).

Ago (Ago) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Town of North Miami
59 So. 2d 779 (Supreme Court of Florida, 1952)
O'NEILL v. Burns
198 So. 2d 1 (Supreme Court of Florida, 1967)
State Ex Rel. Martin v. Michell
188 So. 2d 684 (District Court of Appeal of Florida, 1966)
Davis v. Keen
192 So. 200 (Supreme Court of Florida, 1939)