In the Missouri Court of Appeals Western District
AG PROCESSING, INC., ) Appellant, ) v. ) ) KCP&L GREATER MISSOURI ) WD76353 OPERATIONS COMPANY, ) FILED: March 25, 2014 and ) MISSOURI PUBLIC SERVICE ) COMMISSION, ) Respondents, ) TRIUMPH FOODS, LLC, ) Intervenor-Respondent. )
APPEAL FROM THE PUBLIC SERVICE COMMISSION
BEFORE DIVISION THREE: GARY D. WITT, PRESIDING JUDGE, LISA WHITE HARDWICK AND ALOK AHUJA, JUDGES AG Processing, Inc. ("AGP") appeals from the Missouri Public Service
Commission's ("Commission") Order Regarding Remand in which it: (1) vacated a prior
report and order finding that KCP&L Greater Missouri Operations Company ("KCP&L")
had imprudently operated its hedging program and, as a result, was required to pay
AGP and other customers refunds; (2) ordered a temporary rate adjustment to return to
KCP&L the amount of the refunds; and (3) ordered that a separate complaint case that
AGP had initiated against KCP&L involving different allegations of imprudence be
consolidated with the present complaint case. AGP contends the Order Regarding
Remand is unlawful for several reasons. Because the Order Regarding Remand is not a terminal and complete resolution of the two complaint cases it concerns, it is not a
final and appealable administrative order. Therefore, we dismiss AGP's appeal.
FACTUAL AND PROCEDURAL HISTORY1
KCP&L is the successor company to Aquila, Inc., which provided industrial steam
utility service from its Lake Road Generating Station in St. Joseph. The steam was
produced primarily from a coal-fired boiler, but natural gas was also used as a fuel
source. AGP was one of Aquila's five industrial steam customers served by the Lake
Road Generating Station.
Aquila initiated a ratemaking case before the Commission in 2005, seeking a rate
increase for its steam service in St. Joseph. Pursuant to a negotiated settlement of the
case, the Commission approved a stipulation that authorized Aquila to implement a
quarterly cost adjustment ("QCA") and a price hedging program for fuel costs. Gains
and losses from the hedging program were passed through to customers through the
use of the QCA.
In January 2010, AGP filed a complaint case ("2010 complaint case") alleging
that Aquila was imprudent for initiating such a hedging program and that the program
was imprudently designed and imprudently operated because Aquila purchased
substantially more gas than it actually burned, which resulted in Aquila's steam
customers being "excessively charged." The 2010 complaint case was filed against
KCP&L as Aquila's successor. AGP sought an order requiring KCP&L to refund the
costs of the hedging program that were paid by Aquila's five industrial steam customers.
1 Several facts are adopted from this court's opinion in AG Processing, Inc. v. KCP&L Greater Missouri Operations Co., 385 S.W.3d 511, 513-14 (Mo. App. 2012), without further citation.
2 After an evidentiary hearing, the Commission issued its report and order on
September 28, 2011. In the report and order, the Commission found that it was not
imprudent for Aquila to adopt a natural gas hedging program and that the hedging
program was prudently designed. The Commission further found, however, that KCP&L
had the burden of proving that Aquila operated the hedging program in a prudent
manner and that it failed to meet that burden. As a result, the Commission concluded
that the entire net cost of operating the natural gas price hedging program in 2006 and
2007 was imprudently incurred. Therefore, the Commission ordered that KCP&L refund
the net cost of operating Aquila's natural gas hedging program, in the amount of
$931,968 for 2006 and $1,953,488 for 2007, to its five industrial steam customers
through the QCA.
KCP&L appealed the Commission's September 28, 2011 report and order to this
court. In AG Processing, Inc. v. KCP&L Greater Missouri Operations Co., 385 S.W.3d
511 (Mo. App. 2012), we reversed the Commission's decision, finding that the
Commission erred by shifting the burden of proof to KCP&L and by ordering KCP&L to
pay customer refunds because it failed to meet that burden. Id. at 516. We held that
AGP, as the complainant who initiated the action, had the burden to prove its claims of
imprudence regarding Aquila's expenditures on the natural gas hedging program. Id.
Accordingly, we reversed the Commission's September 28, 2011 report and order and
remanded the cause "for further consideration under the appropriate burden of proof."
Id. While awaiting the issuance of our mandate, KCP&L completed the refunds to
Aquila's steam customers pursuant to the Commission's September 28, 2011 report and
order.
3 On remand, the Commission requested that the parties re-brief the case on the
existing record but properly apply the preponderance of the evidence standard. In its
reply to KCP&L's brief, AGP argued for the first time that, even if it failed to meet its
burden of proof, Aquila's customers could not be compelled to return the refunded
money to KCP&L as a matter of law. The Commission gave KCP&L and Staff an
opportunity to respond to this new legal argument.
Following the parties' re-briefing, the Commission reviewed its September 28,
2011 report and order and issued its Order Regarding Remand on February 27, 2013.
In its Order Regarding Remand, the Commission determined that it would vacate the
September 28, 2011 report and order in its entirety as a matter of due process. The
Commission explained that, when AGP initially presented its case, it was operating
under the assumption that the burden of proof would shift to KCP&L if AGP raised
"serious doubt" as to KCP&L's adoption and management of the hedging program.
Because this court determined in AG Processing, 385 S.W.3d 511, that the burden does
not shift to KCP&L but remains with AGP, the Commission decided that, to ensure due
process, it would reopen the record to take additional evidence now that all of the
parties were fully informed as to the proper burden of proof and who bears that burden.
Additionally, the Commission found that it erred in the September 28, 2011 report
and order when it ordered the refunds to Aquila's customers because there was
insufficient evidence as to how much net hedging costs Aquila would have incurred if it
had properly forecasted the amount of natural gas it needed to purchase. Because
there was no evidence from which to determine the correct amount of costs to be
passed through to each of the customers, there was no evidence to determine the
4 correct amount of the refunds. Consequently, the Commission found that it needed to
make a temporary rate adjustment under Section 386.520.2(3).2 The Commission
relied upon Section 386.520.2(3)'s provision that, if an unlawful or unreasonable
decision of the Commission results in a decrease in the public utility's rates and charges
in a greater amount than what would have occurred had the Commission not erred, the
Commission shall be instructed on remand to approve temporary rate adjustments
Free access — add to your briefcase to read the full text and ask questions with AI
In the Missouri Court of Appeals Western District
AG PROCESSING, INC., ) Appellant, ) v. ) ) KCP&L GREATER MISSOURI ) WD76353 OPERATIONS COMPANY, ) FILED: March 25, 2014 and ) MISSOURI PUBLIC SERVICE ) COMMISSION, ) Respondents, ) TRIUMPH FOODS, LLC, ) Intervenor-Respondent. )
APPEAL FROM THE PUBLIC SERVICE COMMISSION
BEFORE DIVISION THREE: GARY D. WITT, PRESIDING JUDGE, LISA WHITE HARDWICK AND ALOK AHUJA, JUDGES AG Processing, Inc. ("AGP") appeals from the Missouri Public Service
Commission's ("Commission") Order Regarding Remand in which it: (1) vacated a prior
report and order finding that KCP&L Greater Missouri Operations Company ("KCP&L")
had imprudently operated its hedging program and, as a result, was required to pay
AGP and other customers refunds; (2) ordered a temporary rate adjustment to return to
KCP&L the amount of the refunds; and (3) ordered that a separate complaint case that
AGP had initiated against KCP&L involving different allegations of imprudence be
consolidated with the present complaint case. AGP contends the Order Regarding
Remand is unlawful for several reasons. Because the Order Regarding Remand is not a terminal and complete resolution of the two complaint cases it concerns, it is not a
final and appealable administrative order. Therefore, we dismiss AGP's appeal.
FACTUAL AND PROCEDURAL HISTORY1
KCP&L is the successor company to Aquila, Inc., which provided industrial steam
utility service from its Lake Road Generating Station in St. Joseph. The steam was
produced primarily from a coal-fired boiler, but natural gas was also used as a fuel
source. AGP was one of Aquila's five industrial steam customers served by the Lake
Road Generating Station.
Aquila initiated a ratemaking case before the Commission in 2005, seeking a rate
increase for its steam service in St. Joseph. Pursuant to a negotiated settlement of the
case, the Commission approved a stipulation that authorized Aquila to implement a
quarterly cost adjustment ("QCA") and a price hedging program for fuel costs. Gains
and losses from the hedging program were passed through to customers through the
use of the QCA.
In January 2010, AGP filed a complaint case ("2010 complaint case") alleging
that Aquila was imprudent for initiating such a hedging program and that the program
was imprudently designed and imprudently operated because Aquila purchased
substantially more gas than it actually burned, which resulted in Aquila's steam
customers being "excessively charged." The 2010 complaint case was filed against
KCP&L as Aquila's successor. AGP sought an order requiring KCP&L to refund the
costs of the hedging program that were paid by Aquila's five industrial steam customers.
1 Several facts are adopted from this court's opinion in AG Processing, Inc. v. KCP&L Greater Missouri Operations Co., 385 S.W.3d 511, 513-14 (Mo. App. 2012), without further citation.
2 After an evidentiary hearing, the Commission issued its report and order on
September 28, 2011. In the report and order, the Commission found that it was not
imprudent for Aquila to adopt a natural gas hedging program and that the hedging
program was prudently designed. The Commission further found, however, that KCP&L
had the burden of proving that Aquila operated the hedging program in a prudent
manner and that it failed to meet that burden. As a result, the Commission concluded
that the entire net cost of operating the natural gas price hedging program in 2006 and
2007 was imprudently incurred. Therefore, the Commission ordered that KCP&L refund
the net cost of operating Aquila's natural gas hedging program, in the amount of
$931,968 for 2006 and $1,953,488 for 2007, to its five industrial steam customers
through the QCA.
KCP&L appealed the Commission's September 28, 2011 report and order to this
court. In AG Processing, Inc. v. KCP&L Greater Missouri Operations Co., 385 S.W.3d
511 (Mo. App. 2012), we reversed the Commission's decision, finding that the
Commission erred by shifting the burden of proof to KCP&L and by ordering KCP&L to
pay customer refunds because it failed to meet that burden. Id. at 516. We held that
AGP, as the complainant who initiated the action, had the burden to prove its claims of
imprudence regarding Aquila's expenditures on the natural gas hedging program. Id.
Accordingly, we reversed the Commission's September 28, 2011 report and order and
remanded the cause "for further consideration under the appropriate burden of proof."
Id. While awaiting the issuance of our mandate, KCP&L completed the refunds to
Aquila's steam customers pursuant to the Commission's September 28, 2011 report and
order.
3 On remand, the Commission requested that the parties re-brief the case on the
existing record but properly apply the preponderance of the evidence standard. In its
reply to KCP&L's brief, AGP argued for the first time that, even if it failed to meet its
burden of proof, Aquila's customers could not be compelled to return the refunded
money to KCP&L as a matter of law. The Commission gave KCP&L and Staff an
opportunity to respond to this new legal argument.
Following the parties' re-briefing, the Commission reviewed its September 28,
2011 report and order and issued its Order Regarding Remand on February 27, 2013.
In its Order Regarding Remand, the Commission determined that it would vacate the
September 28, 2011 report and order in its entirety as a matter of due process. The
Commission explained that, when AGP initially presented its case, it was operating
under the assumption that the burden of proof would shift to KCP&L if AGP raised
"serious doubt" as to KCP&L's adoption and management of the hedging program.
Because this court determined in AG Processing, 385 S.W.3d 511, that the burden does
not shift to KCP&L but remains with AGP, the Commission decided that, to ensure due
process, it would reopen the record to take additional evidence now that all of the
parties were fully informed as to the proper burden of proof and who bears that burden.
Additionally, the Commission found that it erred in the September 28, 2011 report
and order when it ordered the refunds to Aquila's customers because there was
insufficient evidence as to how much net hedging costs Aquila would have incurred if it
had properly forecasted the amount of natural gas it needed to purchase. Because
there was no evidence from which to determine the correct amount of costs to be
passed through to each of the customers, there was no evidence to determine the
4 correct amount of the refunds. Consequently, the Commission found that it needed to
make a temporary rate adjustment under Section 386.520.2(3).2 The Commission
relied upon Section 386.520.2(3)'s provision that, if an unlawful or unreasonable
decision of the Commission results in a decrease in the public utility's rates and charges
in a greater amount than what would have occurred had the Commission not erred, the
Commission shall be instructed on remand to approve temporary rate adjustments
designed to allow the utility to recover from its customers the amounts it should have
collected plus interest.
Section 386.520.2(3) requires that such temporary rate adjustments be made no
more than 120 days from the issuance of the court of appeals' mandate. The
Commission determined, however, that it did not have sufficient time to conduct a new
hearing and render a decision before the expiration of the 120 days. Therefore, the
Commission decided to order a temporary rate adjustment during the pendency of the
new hearing.
The Commission believed that this temporary rate adjustment would not
prejudice any party because the QCA is a two-way cost adjustment mechanism. The
Commission explained that, if it is later determined that Aquila's actions were, in fact,
imprudent, then any amounts returned to KCP&L that should have been retained by the
customers could simply be flowed back through the QCA to the customers. The
Commission ordered KCP&L to file a new QCA tariff that initiated the return of the
improvidently-ordered refunds to Aquila's steam customers.
2 All statutory references are to the Revised Statutes of Missouri 2000, as updated by the Cumulative Supplement 2013.
5 Also in its Order Regarding Remand, the Commission consolidated the 2010
complaint case with another complaint case that AGP had filed. This other complaint
case ("2012 complaint case") raised allegations of imprudence in KCP&L's hedging
program during the 2009 QCA period. The 2012 complaint case had been stayed by
the Commission pending the outcome of the appeal concerning the 2010 complaint
case.3 The Commission directed the parties to coordinate the presentation of the
evidence for both of the consolidated cases.
AGP filed an application for rehearing from the Commission's Order Regarding
Remand. Additionally, AGP filed a motion for a stay and a motion for approval of a
reconciliation. Before ruling on the motions, the Commission noted that its Order
Regarding Remand was only an interlocutory, procedural order that was not final and
did not dispose of either of the consolidated 2010 and 2012 complaint cases.
Therefore, the Commission stated that the application for rehearing was incorrectly
captioned and should be treated as a motion for reconsideration. Rule 4 CSR 240-
2.160(2) allows a party to file a motion for reconsideration from procedural and
interlocutory orders. The Commission then denied the motion for reconsideration and
the motions for a stay and approval of a reconciliation. Subsequently, KCP&L filed new
tariffs to implement the temporary rate adjustment ordered by the Commission in the
Order Regarding Remand. The Commission took no further action on the tariffs, which
went into effect on June 1, 2013.
3 Triumph Foods, LLC, another of KCP&L's steam customers, intervened in the consolidated complaint cases. Before it intervened, Triumph Foods had no involvement in the 2010 complaint case.
6 AGP filed this appeal. While the appeal was pending, AGP filed two petitions for
a writ of mandamus and a petition for a writ of prohibition, all of which we denied. AGP
also moved for a stay of the Order Regarding Remand, which we denied.
FINALITY OF ORDER REGARDING REMAND
The Commission has filed a motion to dismiss the appeal for lack of a final order.
We took the motion with the case. In the motion, the Commission asserts that its Order
Regarding Remand is an interlocutory order that addressed only procedural issues to
guide the final disposition of the consolidated 2010 and 2012 complaint cases.
Because it is not a final order, the Commission argues that it is not appealable. AGP
contends the Order Regarding Remand is appealable because, by ordering AGP and
the other steam customers to return the refunds to KCP&L through a temporary rate
adjustment, the Commission implemented final and substantive rate changes.
Section 386.510 provides for appellate review of the Commission's "original order
or decision or the order or decision on rehearing." While this statutory language does
not limit appellate review to final orders or decisions, the Missouri Constitution does, as
it provides for judicial review of "[a]ll final decisions, findings, rules and orders on any
administrative officer or body." MO. CONST. art. V, § 18 (emphasis added); State ex rel.
Riverside Pipe Line Co. v. Pub. Serv. Comm'n, 26 S.W.3d 396, 400 (Mo. App. 2000).
Finality with regard to administrative orders occurs when "'the agency arrives at a
terminal, complete resolution of the case before it.'" City of Park Hills v. Pub. Serv.
Comm'n, 26 S.W.3d 401, 404 (Mo. App. 2000) (citation omitted). "'An order lacks
finality in this sense while it remains tentative, provisional, or contingent, subject to
recall, revision or reconsideration by the issuing agency.'" Id. (citations omitted).
7 As its name suggests, the Order Regarding Remand constituted the
Commission's response to our decision in AG Processing, 385 S.W.3d 511, which
reversed and remanded the September 28, 2011 report and order for further
reconsideration under the appropriate burden of proof. After discussing the factual and
procedural history of the 2010 complaint case, our holding in AG Processing, and the
correct preponderance of the evidence, prudence, and proof of harm standards to be
applied in the case, the Commission determined that due process required it to vacate
the September 28, 2011 report and order and reopen the record to take additional
evidence. Because it was reopening the record in the 2010 complaint case, the
Commission also decided, as a matter of administrative economy, to consolidate it with
the 2012 complaint case, which had been stayed. The Commission directed the parties
to coordinate the presentation of the evidence for both of the consolidated cases and to
jointly file a proposed procedural schedule.
Based upon these provisions, it is clear that the Order Regarding Remand did
not address, let alone resolve, the allegations of imprudence that AGP raised in the
2010 and 2012 complaint cases. All of the evidence had yet to be submitted in both
cases. Indeed, at the time the Order Regarding Remand was issued, no evidence had
been adduced in the 2012 complaint case. The Order Regarding Remand was simply a
guide that explained how, in light of our reversal and remand of the 2010 complaint
case, the Commission planned to proceed going forward to bring the 2010 and 2012
complaint cases to a final resolution.
The Commission's inclusion of an order directing the steam customers to return
the refunds to KCP&L through the QCA did not transform the Order Regarding Remand
8 into a final order. The refunds were originally granted to the steam customers as relief
after the Commission found that Aquila had imprudently operated its hedging program --
a finding that this court deemed erroneous on appeal and reversed and remanded for
the Commission's further consideration. The Order Regarding Remand did not finally
decide the issue of Aquila's imprudence; therefore, it did not resolve the issue of who,
ultimately, was entitled to the refunded amounts. The Commission recognized this, as it
stated that, if it determines after the new evidentiary hearing that Aquila's actions were
imprudent and that it should not have ordered a return of the refunds, it will order
KCP&L to give the returned amounts back to the customers through the QCA. 4 Thus,
the Commission's decision to return the refunds is subject to recall or reconsideration
and is not a final administrative order.
CONCLUSION
We dismiss AGP's appeal of the Order Regarding Remand.
____________________________________ LISA W HITE HARDWICK, JUDGE
ALL CONCUR.
4 Because appellate jurisdiction is lacking, we express no view on the substantive correctness of the Commission’s order requiring that KCP&L recoup the refunds previously paid to Aquila’s steam customers pending final resolution of the 2010 complaint case.