Affordable Concrete v. Hanks

CourtCourt of Appeals of South Carolina
DecidedAugust 9, 2017
Docket2017-UP-343
StatusUnpublished

This text of Affordable Concrete v. Hanks (Affordable Concrete v. Hanks) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Affordable Concrete v. Hanks, (S.C. Ct. App. 2017).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Affordable Concrete and Masonry, Respondent,

v.

Roper Hanks, LLC, Appellant.

Appellate Case No. 2015-001788

Appeal From Charleston County Kristi Lea Harrington, Circuit Court Judge

Unpublished Opinion No. 2017-UP-343 Heard June 6, 2017 – Filed August 9, 2017

AFFIRMED

Paul Eliot Sperry and Tyler Paul Winton, both of Carlock Copeland & Stair, LLP, of Charleston, for Appellant.

Natasha M. Hanna, of Law Office of Natasha M. Hanna, P.C., of Myrtle Beach, for Respondent.

PER CURIAM: Roper Hanks, LLC appeals the circuit court's denial of its motion to dismiss, transfer venue, and compel arbitration. We affirm.

FACTS/PROCEDURAL BACKGROUND On March 7, 2013, Roper Hanks, LLC (Roper), a Georgia general contractor, accepted South Carolina subcontractor Affordable Concrete and Masonry d/b/a RSS, LLC's (Affordable's) bid to install concrete at a Haverty Furniture Companies, Inc. (Haverty) store in Charleston, South Carolina for $42,043.83.

On March 28, 2013, after completing the first phase of the project, Affordable submitted its first application for payment to Roper. At that time, Roper presented the subcontract agreement (the contract) to Affordable. The parties signed the contract on April 5, 2013, and Affordable began working on the second phase of the project. Thereafter, Roper requested Affordable perform additional work for $12,530.30.

During the project, a payment dispute arose between Roper and Affordable and Affordable was terminated. On December 23, 2013, Affordable filed a complaint against Haverty for foreclosure, breach of contract, and quantum meruit. In September 2014, a stipulation of dismissal as to Haverty was filed and Roper was added to Affordable's complaint. Affordable asserted it was owed $25,916.62 for labor and materials. Roper subsequently filed a motion to dismiss, transfer venue, and compel arbitration asserting the contract contained forum selection and arbitration clauses and was subject to the Federal Arbitration Act (FAA) 1. A hearing on Roper's motion was held on December 18, 2014.

In a March 2, 2015 order, the circuit court denied Roper's motion. The court found Roper did not introduce any evidence, other than its incorporation in Georgia, that the contract involved interstate commerce. The court noted the contract was signed in South Carolina, the materials for the project were purchased in South Carolina, and the contract was performed in South Carolina. Accordingly, the court held South Carolina law, not the FAA, applied to the arbitration agreement. The court further found the contract did not contain the requisite notice required by the South Carolina Uniform Arbitration Act (SCUAA) 2 and was unenforceable. In addition, the court held:

Due to [Affordable's] lack of bargaining power, lack of sophistication, the nature of the damages, the inconspicuous placement and form of the arbitration clause, and the timing of the contract, [Affordable] was not afforded meaningful choice to agree to arbitration.

1 9 U.S.C.A. § 1 et seq. (2012). 2 S.C. Code Ann. § 15-48-10 et seq. (2005). [Affordable's] lack of meaningful choice, in conjunction with the one-sided and oppressive terms of the agreement, makes the arbitration agreement unconscionable, and therefore unenforceable.

The circuit court further held the contract's choice of law provision was "one-sided, oppressive, [and] adhesive." The court found Affordable lacked a meaningful choice in signing the provision because the contract was not provided to Affordable until after work had begun on the project. The court held Affordable was not offered a meaningful opportunity to bargain for the terms and risked not getting paid for the work already completed if it did not sign the contract. Roper's subsequent motion for reconsideration was denied. This appeal followed.

STANDARD OF REVIEW

"The question of the arbitrability of a claim is an issue for judicial determination, unless the parties provide otherwise." Zabinski v. Bright Acres Assocs., 346 S.C. 580, 596, 553 S.E.2d 110, 118 (2001). This court reviews an arbitrability determination de novo. Hall v. Green Tree Servicing, LLC, 413 S.C. 267, 271, 776 S.E.2d 91, 94 (Ct. App. 2015). "Nevertheless, a circuit court's factual findings will not be reversed on appeal if any evidence reasonably supports the findings." Simpson v. MSA of Myrtle Beach, Inc., 373 S.C. 14, 22, 644 S.E.2d 663, 667 (2007).

LAW/ANALYSIS

Roper argues the circuit court erred in denying its motion to dismiss, transfer venue, and compel arbitration. Specifically, Roper contends the parties engaged in interstate commerce sufficient to invoke the FAA, and Georgia law applied pursuant to the contract's choice of law provision.

I. FAA

"The policy of the United States and South Carolina is to favor arbitration of disputes." Zabinski, 346 S.C. at 596, 553 S.E.2d at 118. "Arbitration is a matter of contract, and a party cannot be required to submit to arbitration any dispute which he has not agreed to submit." Id. "To decide whether an arbitration agreement encompasses a dispute, a court must determine whether the factual allegations underlying the claim are within the scope of the broad arbitration clause, regardless of the label assigned to the claim." Id. at 597, 553 S.E.2d at 118. "Any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration." Id.

The arbitration provision at issue in this case, located on page thirteen of the contract, provides as follows:

Article X Claims and Disputes

A. Any claim, dispute, or controversy between Owner or Contractor, shall be conclusively resolved and settled as follows:

Subcontractor shall conclusively be bound by and abide by Owner or Contractor's decision, unless Subcontractor shall timely commence arbitration proceedings . . . . .

Unless the parties have contracted otherwise, the FAA applies in federal or state court to any arbitration agreement involving interstate commerce. Munoz v. Green Tree Fin. Corp., 343 S.C. 531, 538, 542 S.E.2d 360, 363 (2001). The FAA provides that a written arbitration agreement in a contract involving interstate commerce "shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." 9 U.S.C.A. § 2 (2012).

"The United States Supreme Court 'has previously described the [FAA]'s reach expansively as coinciding with that of the Commerce Clause.'" Cape Romain Contractors, Inc. v. Wando E., LLC, 405 S.C. 115, 122, 747 S.E.2d 461, 464 (2013) (quoting Allied–Bruce Terminix Cos. v. Dobson, 513 U.S. 265 (1995)). Pursuant to the Commerce Clause, Congress has authority to regulate (1) use of the channels of interstate commerce; (2) persons, things or instrumentalities in interstate commerce; and (3) activities having a substantial relation to interstate commerce. Id. at 123, 747 S.E.2d at 465.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied-Bruce Terminix Cos., Inc. v. Dobson
513 U.S. 265 (Supreme Court, 1995)
Simpson v. MSA of Myrtle Beach, Inc.
644 S.E.2d 663 (Supreme Court of South Carolina, 2007)
Zabinski v. Bright Acres Associates
553 S.E.2d 110 (Supreme Court of South Carolina, 2001)
Lackey v. Green Tree Financial Corp.
498 S.E.2d 898 (Court of Appeals of South Carolina, 1998)
Munoz v. Green Tree Financial Corp.
542 S.E.2d 360 (Supreme Court of South Carolina, 2001)
TEAM IA, INC. v. Lucas
717 S.E.2d 103 (Court of Appeals of South Carolina, 2011)
Burkey v. Noce
726 S.E.2d 229 (Court of Appeals of South Carolina, 2012)
Cape Romain Contractors, Inc. v. Wando E., LLC
747 S.E.2d 461 (Supreme Court of South Carolina, 2013)
Hall v. Green Tree Servicing, LLC
776 S.E.2d 91 (Court of Appeals of South Carolina, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Affordable Concrete v. Hanks, Counsel Stack Legal Research, https://law.counselstack.com/opinion/affordable-concrete-v-hanks-scctapp-2017.