Aetna Indemnity Co. v. Baltimore, Sparrows Point & Chesapeake Railway Co.

84 A. 166, 117 Md. 523, 1912 Md. LEXIS 142
CourtCourt of Appeals of Maryland
DecidedFebruary 28, 1912
StatusPublished
Cited by3 cases

This text of 84 A. 166 (Aetna Indemnity Co. v. Baltimore, Sparrows Point & Chesapeake Railway Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Indemnity Co. v. Baltimore, Sparrows Point & Chesapeake Railway Co., 84 A. 166, 117 Md. 523, 1912 Md. LEXIS 142 (Md. 1912).

Opinion

TIeNKe, J.,

delivered the opinion of the Court.

When this case was considered on a former appeal (112 3J!d. 389) the question for decision was presented upon bill and answer, and as some of the material allegations upon which relief was prayed were either denied or not admitted, the decree below granting the prayer of the bill was reversed and the cause was remanded for further proceedings. At that time the sole object of the suit was to secure the reformation of the bond executed by the Aetna Indemnity Company as surety, and intended to be also executed by the Constructing Engineers’ Company as principal, conditioned for the due performance by the latter company of its contract with the Baltimore, Sparrows’ Point and Chesapeake Railway Company for the building of an electric railway. This relief was sought in order that an action pending at law on the bond might be successfully prosecuted. It was alleged in the bill that the bond for which the contract provided was delivered by the Constructing Company to the Railway Company and by it accepted; that the bond had been executed by the Aetna Company as surety, but by inadvertence had not been executed by the Constructing Company as principal ; that the construction work was begun and partially performed, but the railway company, finding that it would not be completed according to the terms of the contract, entered into a supplemental agreement with the constructing *526 company for tbe co-operation of the two companies in the further progress of the work; that the Aetna Company consented in writing to this arrangement, with the stipulation that its liability in any event should be limited to the payment of $10,000, as prescribed by the bond; that a receiver was shortly afterwards appointed for the constructing company, but as he was not authorized to proceed with the work, the railway company was compelled to employ other contractors for its completion; that the cost of having the road finished was largely increased over the amount the constructing company was to have received because of the fact that the unfinished work had to be done during the winter, and as a result .the railway company sustained a loss for which a suit at law had been brought on the bond; that after the bringing of that suit and within two weeks before the filing of the bill in this case, it was discovered that the bond was not executed .by the constructing company, this omission not having been noticed at the time of its delivery, and the bond having since been kept among the records of the railway company under the belief by its officers that it had been duly executed both by the principal and the surety.

The constructing company and its receiver filed answers admitting that it was the intention of the company to' deliver a good and sufficient bond, and its president and secretary stated their understanding that they had in fact executed the instrument for the company before it was delivered. The Aetna Company, however, answered separately alleging that the execution of the bond by the constructing company was a condition precedent to liability on the part of the surety; and that the railway company had been guilty of laches. It averred .that it had consented to the supplemental agreement referred to in the bill in the mistaken belief that the bond had been duly executed. It charged that the railway company as custodian of the bond knew or ought to have known that it had not been executed, but failed to disclose the fact until long after the alleged liability had occurred and the action at law had been instituted. The answer denied *527 that tbe railway company was compelled to pay for tbe completion of tbe work tbe sum mentioned in tbe bill in excess of tbe amount contracted to bo paid to the constructing company, or that there was any reason for the work to cost more than tbe amount which that company was 1o have received; and it alleged that the railway company owed the constructing company a large sum of money. One of the averments of the bill which the answer neither admitted nor denied was that the plaintiff in good faith accepted the instrument as the properly executed bond of the constructing company, with the Aetna Company as surety, given in performance of the agreement to that effect, that it was received without such scrutiny as to disclose the fact that the constructing company had not executed it, and that being regarded as a good and binding obligation on the part of both companies, it was placed among the records of the railway company for safe keeping.

In this condition of the pleadings, and in the absence of evidence to sustain the material allegations of the bill as to which the answer did not waive the necessity of proof, it was held that a decree of reformation could not properly be passed, but that tbe cause should be remanded in order that a replication might be filed and testimony taken to establish the essential facts. It was said, however, by Cintur Judgts Boyd in the opinion disposing of tbe case as then presented that “If a surety executes such a bond, and gives it to tbe principal to be executed by him, and then to deliver it to tbe obligee, and the principal does so deliver it, having simply overlooked the fact that he had not executed it, and the obligee, believing it was properly executed, and not observing that it had not been by the principal, placed it away for safe keeping with its papers, all three parties believing it had been regularly executed and intending that it should be, it would be a confession of a very limited power to do justice, if a Court of equity would have to admit that it could not require the bond to be put in the shape it was intended and believed to be by all the parties, merely because one of tbexn *528 was a surety. But we do not understand the powers of a Court of equity to be so restricted.” The- opinion suggested that upon the remanding of the proceedings it might “be better to amend the bill, so far as necessary to have the whole matter disposed of in the equity case, if the Court- concludes that the plaintiff is entitled to have the bond corrected ;” and the principle was stated that “When a Court of equity ’reforms an instrument, it can retain control and enforce- it as reformed, administering full relief.”

The present appeal is from a decree passed upon pleadings amended in consequence of the suggestion of this Court and upon evidence directed to the issues’ of fact thus raised. The relief prayed by the pending bill, and granted by the decree now under review, involves both the reformation of the bond and the payment of the sum it prescribes on account of the loss claimed and found to have been sustained by the railway company as the result of the constructing company's discontinuance of the work. We have now to determine upon the evidence whether the appellee is entitled to have the bond reformed and to enforce against it the liability asserted in the bill. There are also questions arising upon a plea of contractual limitations filed by the Aetna Company, and upon its petition that the complainant be required to elect between its suits at law and in equity. The constructing company and its receiver did not dispute the right, of the railway company to have the bond corrected. Their defence was based upon the ground that the-railway company’s conduct was responsible for the failure of the constructing company to complete the -work according to the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alderfer v. Pendergraft
448 A.2d 601 (Supreme Court of Pennsylvania, 1982)
Parkway, Inc. v. United States Fire Insurance
58 N.E.2d 646 (Massachusetts Supreme Judicial Court, 1944)
Johnson v. National Mutual Insurance
3 A.2d 460 (Court of Appeals of Maryland, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
84 A. 166, 117 Md. 523, 1912 Md. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-indemnity-co-v-baltimore-sparrows-point-chesapeake-railway-co-md-1912.