Aero-Crete, Inc. v. Superior Court

21 Cal. App. 4th 203, 25 Cal. Rptr. 2d 804, 93 Daily Journal DAR 16313, 93 Cal. Daily Op. Serv. 9542, 1993 Cal. App. LEXIS 1291
CourtCalifornia Court of Appeal
DecidedDecember 21, 1993
DocketD019450
StatusPublished
Cited by12 cases

This text of 21 Cal. App. 4th 203 (Aero-Crete, Inc. v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aero-Crete, Inc. v. Superior Court, 21 Cal. App. 4th 203, 25 Cal. Rptr. 2d 804, 93 Daily Journal DAR 16313, 93 Cal. Daily Op. Serv. 9542, 1993 Cal. App. LEXIS 1291 (Cal. Ct. App. 1993).

Opinion

*206 Opinion

WIENER, Acting P. J.

This is a complex construction defect case brought by plaintiffs Dale Village Apartment Company and related entities (Dale Village) against Pieri-Debbas Enterprises, the developer and general contractor on an apartment building project owned by Dale Village. Various subcontractors on the project have also been sued as defendants. Petitioners are certain of those subcontractors who seek writ relief after the trial court determined that a settlement between Dale Village and Pieri-Debbas was in good faith. They raise several issues related both to the court’s good faith determination and to statements it made regarding the effect of the settlement on future proceedings.

We conclude the trial court acted properly in finding the settlement to be in good faith. While the trial court is normally best served by valuing any assigned rights for the purpose of later setoffs at the time of the good faith determination, we have determined there was no mandate that it do so under the unique circumstances of this case. Finally, we explain why a prove-up hearing as to damages following Pieri-Debbas’s stipulation to liability will not bind parties later determined to be indemnitors of Pieri-Debbas. Accordingly, we deny the petition.

Factual and Procedural Background

Pieri-Debbas is a partnership with two corporate general partners, T-Bear, Inc. (solely owned by defendant James Fieri) and Debbas Construction (solely owned by defendant Nicholas Debbas). On the filing of the lawsuit by Dale Village, Pieri-Debbas tendered its defense to both its insurers and various subcontractors on the project with whom it allegedly had contractual indemnity agreements. Both the insurers and subcontractors denied responsibility and refused to defend Pieri-Debbas.

Dale Village and Pieri-Debbas later agreed to settle their lawsuit on the following terms: Pieri-Debbas stipulated to liability; a prove-up hearing would be held to establish the amount of damages; in exchange for a covenant not to execute Pieri-Debbas assigned its indemnification rights as against its insurers and the subcontractors to Dale Village. The settling parties stipulated that the value of the settlement was $50,000 representing the defense costs Pieri-Debbas had incurred but would not now recover. The assigned rights were not valued, but an obligation was imposed on Dale Village to exercise due diligence in the prosecution of the assigned rights. As is typical, the settlement was contingent on the trial court finding the agreement to be in good faith. Within two days of signing the settlement *207 agreement, Dale Village dismissed James Fieri and Nicholas Debbas as individual defendants without prejudice, allegedly because there was no basis for any alter ego claims.

In petitioning the court to confirm the settlement as being in good faith, Dale Village and Pieri-Debbas relied on declarations indicating that Pieri-Debbas had a negative net worth and would be unable to satisfy any judgment against it. Petitioners presented no significant contrary evidence. 1

The trial court confirmed the settlement, relying largely, if not exclusively, on the financial condition of Pieri-Debbas. In the course of the hearing, counsel for Dale Village explained his understanding that the separate prove-up hearing would set the damages as to each individual subcontractor to the extent liability was based on their obligation to indemnify Pieri-Debbas. The trial court agreed that the subcontractors would be “stuck with the number . . . that’s going to be the subject of a default prove-up case.” It summarily denied the subcontractors’ request to participate in the prove-up hearing.

Discussion

Petitioning subcontractors argue the trial court erred in determining that the settlement between Dale Village and Pieri-Debbas was in good faith. They also assert the court should have valued the assignment of rights received by Dale Village for the purpose of later setoff. Finally, they claim they cannot be bound by the apportionment of damages arrived at in a prove-up hearing in which they were not able to participate.

The trial court’s conclusion on the good faith issue is fully supported by the record. The remaining contentions, while they raise interesting legal questions, are not ripe for review because no subcontractor has been found liable as an indemnitor or is subject to a judgment as to which a setoff would be applicable.

Good Faith Determination

Petitioners point to a series of factors they say demonstrate the settlement was not in good faith. Some factors are simply not relevant to the *208 good faith determination. Others, while certainly relevant, do not overcome the trial court’s pragmatic conclusion that Pieri-Debbas has no assets with which to respond to a judgment for damages.

Petitioners argue and Dale Village readily concedes that defendants’ potential exposure in the case exceeds $10 million. Although they may disagree as to amount, both sides agree that the proportionate liability of Pieri-Debbas exceeds the value of the settlement. Under other circumstances this might suggest the settlement was not entered into in good faith. (See, e.g., City of Grand Terrace v. Superior Court (1987) 192 Cal.App.3d 1251, 1262 [238 Cal.Rptr. 119].) As the Supreme Court explained in the seminal case of Tech-Bilt, Inc. v. Woodward-Clyde & Associates (1985) 38 Cal.3d 488 [213 Cal.Rptr. 256, 698 P.2d 159], however, strict proportionate liability is not the sine qua non of a good faith settlement. Other relevant considerations identified by the Supreme Court include “the financial conditions . . . of settling defendants . . . .” (Id. at p. 499.) The court quoted from an earlier Court of Appeal decision which noted, “ ‘[A] disproportionately low settlement figure is often reasonable in the case of a relatively insolvent, and uninsured, or underinsured, joint tortfeasor.’ ” (Ibid., citing Stambaugh v. Superior Court (1976) 62 Cal.App.3d 231, 238 [132 Cal.Rptr. 843].)

Here, the controlling shareholders of Pieri-Debbas’s two corporate general partners submitted declarations indicating that the joint venture’s only asset had encumbrances exceeding its value. The only contrary suggestion by petitioners relied on documentation which was out of date and, in any event, de minimus. Petitioners do not assert that they sought and were denied adequate discovery on the issue of Pieri-Debbas’s financial condition. (See, e.g., Rankin v. Curtis (1986) 183 Cal.App.3d 939, 947-948 [228 Cal.Rptr. 753].)

Petitioners also contend the settlement was not in good faith because Dale Village failed to show that James Fieri and Nicholas Debbas were without personal assets which could be tapped to satisfy an adverse judgment. Petitioners’ argument is crafted as though Fieri and Debbas are general partners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garot v. County of San Diego
S.D. California, 2023
Spyksma v. Sousamian CA4/3
California Court of Appeal, 2013
TSI Seismic Tenant Space, Inc. v. Superior Court
56 Cal. Rptr. 3d 751 (California Court of Appeal, 2007)
Crawford v. Weather Shield Mfg., Inc.
38 Cal. Rptr. 3d 787 (California Court of Appeal, 2006)
Everett Associates, Inc. v. Transcontinental Insurance
159 F. Supp. 2d 1196 (N.D. California, 2001)
Fleck v. Bollinger Home Corp. Inc.
54 Cal. App. 4th 926 (California Court of Appeal, 1997)
Truck Insurance Exchange v. Superior Court
51 Cal. App. 4th 985 (California Court of Appeal, 1996)
Valley Crest Landscape, Inc. v. City Council
41 Cal. App. 4th 1432 (California Court of Appeal, 1996)
Hartford Accident & Indemnity Co. v. Superior Court
37 Cal. App. 4th 1174 (California Court of Appeal, 1995)
National Union Fire Insurance v. Lynette C.
27 Cal. App. 4th 1434 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
21 Cal. App. 4th 203, 25 Cal. Rptr. 2d 804, 93 Daily Journal DAR 16313, 93 Cal. Daily Op. Serv. 9542, 1993 Cal. App. LEXIS 1291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aero-crete-inc-v-superior-court-calctapp-1993.