A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided March 22, 2021·No. A-1791-19·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-1791-19

A&E CONSTRUCTION CO., Plaintiff-Respondent,

v.

BARRIER ELECTRIC COMPANY, INC., JOHN BARRIER, individually, and RICHARD CIRMINELLO, individually,

Defendants-Appellants.

Submitted January 21, 2021 – Decided March 22, 2021 Before Judges Ostrer and Vernoia.

On appeal from the Superior Court of New Jersey, Law Division, Union County, Docket No. L-0264-18.

Tesser & Cohen, attorneys for appellants (Francis A.

Kirk, of counsel and on the briefs).

Cohen Seglias Pallas Greenhall & Furman, PC, attorneys for respondent (Robert J. O'Brien and Robert S. Turchick, on the brief).

PER CURIAM Following a bench trial, the court entered a $228,449.20 final judgment in plaintiff A&E Construction Co.'s favor against defendants Barrier Electric Company, Inc. (Barrier), John Barrier, and Richard Cirminello. Defendants appeal from the judgment, arguing the court's findings of fact are not supported by substantial credible evidence; the court failed to address defendants' argument they are entitled to a setoff against plaintiff's damages claim because plaintiff failed to comply with the Prompt Payment Act, N.J.S.A. 2A:30A-1 to -2; and the court erred in determining its award of interest. Unpersuaded by those arguments, we affirm.

I.

This action arose over Barrier's failure to pay invoices for electrical equipment supplied to it by Turtle & Hughes, Inc. (T&H) during a construction project. T&H filed a complaint seeking damages based on Barrier's failure to pay the invoices. T&H also asserted claims against John Barrier and Cirminello, who had personally guaranteed Barrier's payment of T&H's invoices.

A&E was the project's general contractor. It entered into a series of subcontracts with Barrier to perform electrical work. Following the filing of T&H's complaint, A&E paid T&H $194,790.91 for an assignment of T&H's

A-1791-19

rights against Barrier, and A&E was then substituted as plaintiff in T&H's action against defendants.

At the ensuing bench trial, the parties stipulated to a series of facts establishing defendants' indebtedness to T&H for the unpaid invoices. They stipulated that: between May and August 2017, T&H supplied $194,790.91 of electrical materials to Barrier for the project; Barrier accepted the materials; and Barrier did not pay T&H's invoices for the materials. The parties also stipulated that on February 21, 2018, T&H assigned its rights to A&E, and the court allowed A&E's substitution for T&H as plaintiff in the litigation.

The parties also stipulated to the admission into evidence of a series of exhibits, including Barrier's "APPLICATION FOR BUSINESS CREDIT" and Barrier's purchase orders to T&H; John Barrier's and Cirminello's personal guaranties; T&H's statements of account showing $194,790.91 due from Barrier; the assignment agreement between T&H and A&E; and documents summarizing the amount A&E claimed was due to T&H—$312,978.29—under credit terms agreed to by Barrier and personally guaranteed by John Barrier and Cirminello.1

1 The $312,978.29 claimed to be due to T&H included $194,790.91 in unpaid invoices, interest at the rate of one-and-one-half percent per month on the overdue invoices, and an attorney's fees calculated at the rate of thirty percent of the unpaid invoices. The interest and attorney's fee claims were based on the

A-1791-19

As reflected in the parties' stipulations of fact, defendants conceded at trial that Barrier did not pay the T&H invoices at issue in the complaint. Defendants argued, however, that the amount A&E claimed it was due as T&H's assignee should be reduced by the sums A&E owed Barrier for work Barrier performed as A&E's electrical subcontractor on the project. In other words, defendants argued they were entitled to a setoff against T&H's unpaid invoices for sums Barrier claimed A&E owed for Barrier's electrical work on the project.

In support of the claimed setoff, Barrier relied on the testimony of its office manager, Michelle Lambos, who was in charge of Barrier's accounts payable and receivable. Lambos also testified generally concerning applications for payment Barrier submitted to A&E during the project. She explained that the applications and summaries of amounts Barrier billed to, and were paid by, A&E that were admitted in evidence demonstrated A&E owed Barrier $200,536 for its work on the project. Lambos testified Barrier submitted the applications for payment to A&E via email. However, no emails were presented at trial and Lambos did not testify when she forwarded the applications for payment to A&E.

terms and conditions of T&H's agreement to extend credit to Barrier. As noted, John Barrier and Cirminello personally guaranteed Barrier's payment of all sums due from Barrier to T&H.

A-1791-19

Lambos acknowledged A&E paid Barrier $1,336,724.20 for work performed during the project. She admitted that a Barrier ledger showed Barrier had only $68,250 in open invoices to A&E, but she testified there were additional unpaid invoices to A&E. She could not testify concerning all of the payments Barrier received from A&E because she did not have "the whole ledger" with her at trial.

She further testified that after Barrier's work on the project ended, it submitted a claim to A&E's bonding company for payments due from A&E. She acknowledged Barrier's claim to the bonding company did not assert $200,536 was due from A&E. Instead, in its claim to the bonding company, Barrier asserted A&E owed Barrier $78,000 for unpaid invoices on the project.

A&E presented its vice president of operations, Robert C. McClure, as its witness at trial. McClure explained A&E's contracts with Barrier included a "pay if paid" provision requiring that A&E pay Barrier for the electrical work only if A&E received payment from the project owner.2 McClure explained invoices received by A&E from Barrier were posted to a ledger in A&E's accounting software program, and that the ledger showed A&E received

2 McClure testified a "pay if paid" provision places the risk of non-collection of payments due from the project owner on both the prime contractor and the subcontractor.

A-1791-19

invoices totaling $1,404,974.20 from Barrier during the project. The ledger also showed A&E paid Barrier $1,336,724.20. McClure testified A&E did not pay the $68,250 balance shown on the ledger because it did not receive payment from the project owner for the work. McClure also testified Barrier's affidavits supporting its requests for payment failed to disclose that Barrier did not pay T&H for the materials it supplied to Barrier.

In a decision from the bench following the submission of written summations, the court determined Barrier's claim A&E owed it $200,536 was "overstated." The court made detailed findings concerning each of the documents Lambos and Barrier relied on to support defendants' setoff claim, and the court concluded the documents did not establish A&E owed Barrier $200,536. For example, the court found that notations on some of Barrier's applications for payment showed the work for which Barrier sought payment was rejected by A&E or was "not complete." The court also found Barrier relied on unsigned change order requests, and Barrier did not present evidence A&E approved the requests. The court relied on McClure's testimony that A&E's contracts with Barrier required payment for Barrier's work only when A&E was paid by the project owner. The court further noted Barrier submitted a $78,000

A-1791-19

claim for payment to A&E's bonding company after Barrier's work on the project ended, and Barrier did not explain how the claim later increased to $200,536.

Free access — add to your briefcase to read the full text and ask questions with AI

A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE), (N.J. Ct. App. 2021).

A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE) (A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Beneficial Finance Co. of Atl. City v. Swaggerty
432 A.2d 512 (Supreme Court of New Jersey, 1981)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Miah v. Ahmed
846 A.2d 1244 (Supreme Court of New Jersey, 2004)
Roberts v. Rich Foods, Inc.
654 A.2d 1365 (Supreme Court of New Jersey, 1995)
Cavanaugh v. Skil Corp.
751 A.2d 518 (Supreme Court of New Jersey, 2000)
Russell v. Fred G. Pohl Co.
80 A.2d 191 (Supreme Court of New Jersey, 1951)
Fagliarone v. North Bergen Tp.
188 A.2d 43 (New Jersey Superior Court App Division, 1963)
New Jersey Division of Youth & Family Services v. M.M.
914 A.2d 1265 (Supreme Court of New Jersey, 2007)
Lisa Llewelyn v. James Shewchuk
111 A.3d 1132 (New Jersey Superior Court App Division, 2015)
Tirgan v. Mega Life & Health Insurance
700 A.2d 1239 (New Jersey Superior Court App Division, 1997)