A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedMarch 22, 2021
DocketA-1791-19
StatusUnpublished

This text of A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE) (A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE), (N.J. Ct. App. 2021).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1791-19

A&E CONSTRUCTION CO.,

Plaintiff-Respondent,

v.

BARRIER ELECTRIC COMPANY, INC., JOHN BARRIER, individually, and RICHARD CIRMINELLO, individually,

Defendants-Appellants. __________________________

Submitted January 21, 2021 – Decided March 22, 2021

Before Judges Ostrer and Vernoia.

On appeal from the Superior Court of New Jersey, Law Division, Union County, Docket No. L-0264-18.

Tesser & Cohen, attorneys for appellants (Francis A. Kirk, of counsel and on the briefs).

Cohen Seglias Pallas Greenhall & Furman, PC, attorneys for respondent (Robert J. O'Brien and Robert S. Turchick, on the brief). PER CURIAM

Following a bench trial, the court entered a $228,449.20 final judgment in

plaintiff A&E Construction Co.'s favor against defendants Barrier Electric

Company, Inc. (Barrier), John Barrier, and Richard Cirminello. Defendants

appeal from the judgment, arguing the court's findings of fact are not supported

by substantial credible evidence; the court failed to address defendants'

argument they are entitled to a setoff against plaintiff's damages claim because

plaintiff failed to comply with the Prompt Payment Act, N.J.S.A. 2A:30A-1

to -2; and the court erred in determining its award of interest. Unpersuaded by

those arguments, we affirm.

I.

This action arose over Barrier's failure to pay invoices for electrical

equipment supplied to it by Turtle & Hughes, Inc. (T&H) during a construction

project. T&H filed a complaint seeking damages based on Barrier's failure to

pay the invoices. T&H also asserted claims against John Barrier and Cirminello,

who had personally guaranteed Barrier's payment of T&H's invoices.

A&E was the project's general contractor. It entered into a series of

subcontracts with Barrier to perform electrical work. Following the filing of

T&H's complaint, A&E paid T&H $194,790.91 for an assignment of T&H's

A-1791-19 2 rights against Barrier, and A&E was then substituted as plaintiff in T&H's action

against defendants.

At the ensuing bench trial, the parties stipulated to a series of facts

establishing defendants' indebtedness to T&H for the unpaid invoices. They

stipulated that: between May and August 2017, T&H supplied $194,790.91 of

electrical materials to Barrier for the project; Barrier accepted the materials; and

Barrier did not pay T&H's invoices for the materials. The parties also stipulated

that on February 21, 2018, T&H assigned its rights to A&E, and the court

allowed A&E's substitution for T&H as plaintiff in the litigation.

The parties also stipulated to the admission into evidence of a series of

exhibits, including Barrier's "APPLICATION FOR BUSINESS CREDIT" and

Barrier's purchase orders to T&H; John Barrier's and Cirminello's personal

guaranties; T&H's statements of account showing $194,790.91 due from Barrier;

the assignment agreement between T&H and A&E; and documents summarizing

the amount A&E claimed was due to T&H—$312,978.29—under credit terms

agreed to by Barrier and personally guaranteed by John Barrier and Cirminello.1

1 The $312,978.29 claimed to be due to T&H included $194,790.91 in unpaid invoices, interest at the rate of one-and-one-half percent per month on the overdue invoices, and an attorney's fees calculated at the rate of thirty percent of the unpaid invoices. The interest and attorney's fee claims were based on the

A-1791-19 3 As reflected in the parties' stipulations of fact, defendants conceded at trial

that Barrier did not pay the T&H invoices at issue in the complaint. Defendants

argued, however, that the amount A&E claimed it was due as T&H's assignee

should be reduced by the sums A&E owed Barrier for work Barrier performed

as A&E's electrical subcontractor on the project. In other words, defendants

argued they were entitled to a setoff against T&H's unpaid invoices for sums

Barrier claimed A&E owed for Barrier's electrical work on the project.

In support of the claimed setoff, Barrier relied on the testimony of its

office manager, Michelle Lambos, who was in charge of Barrier's accounts

payable and receivable. Lambos also testified generally concerning applications

for payment Barrier submitted to A&E during the project. She explained that

the applications and summaries of amounts Barrier billed to, and were paid by,

A&E that were admitted in evidence demonstrated A&E owed Barrier $200,536

for its work on the project. Lambos testified Barrier submitted the applications

for payment to A&E via email. However, no emails were presented at trial and

Lambos did not testify when she forwarded the applications for payment to

A&E.

terms and conditions of T&H's agreement to extend credit to Barrier. As noted, John Barrier and Cirminello personally guaranteed Barrier's payment of all sums due from Barrier to T&H. A-1791-19 4 Lambos acknowledged A&E paid Barrier $1,336,724.20 for work

performed during the project. She admitted that a Barrier ledger showed Barrier

had only $68,250 in open invoices to A&E, but she testified there were

additional unpaid invoices to A&E. She could not testify concerning all of the

payments Barrier received from A&E because she did not have "the whole

ledger" with her at trial.

She further testified that after Barrier's work on the project ended, it

submitted a claim to A&E's bonding company for payments due from A&E. She

acknowledged Barrier's claim to the bonding company did not assert $200,536

was due from A&E. Instead, in its claim to the bonding company, Barrier

asserted A&E owed Barrier $78,000 for unpaid invoices on the project.

A&E presented its vice president of operations, Robert C. McClure, as its

witness at trial. McClure explained A&E's contracts with Barrier included a

"pay if paid" provision requiring that A&E pay Barrier for the electrical work

only if A&E received payment from the project owner.2 McClure explained

invoices received by A&E from Barrier were posted to a ledger in A&E's

accounting software program, and that the ledger showed A&E received

2 McClure testified a "pay if paid" provision places the risk of non-collection of payments due from the project owner on both the prime contractor and the subcontractor. A-1791-19 5 invoices totaling $1,404,974.20 from Barrier during the project. The ledger also

showed A&E paid Barrier $1,336,724.20. McClure testified A&E did not pay

the $68,250 balance shown on the ledger because it did not receive payment

from the project owner for the work. McClure also testified Barrier's affidavits

supporting its requests for payment failed to disclose that Barrier did not pay

T&H for the materials it supplied to Barrier.

In a decision from the bench following the submission of written

summations, the court determined Barrier's claim A&E owed it $200,536 was

"overstated." The court made detailed findings concerning each of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beneficial Finance Co. of Atl. City v. Swaggerty
432 A.2d 512 (Supreme Court of New Jersey, 1981)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Miah v. Ahmed
846 A.2d 1244 (Supreme Court of New Jersey, 2004)
Roberts v. Rich Foods, Inc.
654 A.2d 1365 (Supreme Court of New Jersey, 1995)
Cavanaugh v. Skil Corp.
751 A.2d 518 (Supreme Court of New Jersey, 2000)
Russell v. Fred G. Pohl Co.
80 A.2d 191 (Supreme Court of New Jersey, 1951)
Fagliarone v. North Bergen Tp.
188 A.2d 43 (New Jersey Superior Court App Division, 1963)
New Jersey Division of Youth & Family Services v. M.M.
914 A.2d 1265 (Supreme Court of New Jersey, 2007)
Lisa Llewelyn v. James Shewchuk
111 A.3d 1132 (New Jersey Superior Court App Division, 2015)
Tirgan v. Mega Life & Health Insurance
700 A.2d 1239 (New Jersey Superior Court App Division, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
A&E CONSTRUCTION CO. VS. BARRIER ELECTRIC COMPANY, INC. (L-0264-18, UNION COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/ae-construction-co-vs-barrier-electric-company-inc-l-0264-18-union-njsuperctappdiv-2021.