Advantage Drilling, LLC v. Mayan Construction, Inc.

CourtNew Mexico Court of Appeals
DecidedJune 17, 2013
Docket30,845
StatusUnpublished

This text of Advantage Drilling, LLC v. Mayan Construction, Inc. (Advantage Drilling, LLC v. Mayan Construction, Inc.) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advantage Drilling, LLC v. Mayan Construction, Inc., (N.M. Ct. App. 2013).

Opinion

This memorandum opinion was not selected for publication in the New Mexico Appellate Reports. Please see Rule 12-405 NMRA for restrictions on the citation of unpublished memorandum opinions. Please also note that this electronic memorandum opinion may contain computer-generated errors or other deviations from the official paper version filed by the Court of Appeals and does not include the filing date.

1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

2 ADVANTAGE DRILLING, LLC,

3 Plaintiff-Appellee,

4 v. NO. 30,845

5 MAYAN CONSTRUCTION, INC.,

6 Defendant-Appellant,

7 GRANITE RE, INC.,

8 Defendant.

9 APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY 10 Ted Baca, District Judge

11 Bingham, Hurst & Apodaca, P.C. 12 Lillian G. Apodaca 13 Albuquerque, NM

14 for Appellee

15 Lorenz Law 16 Alice T. Lorenz 17 Albuquerque, NM 1 for Appellant

2 MEMORANDUM OPINION

3 WECHSLER, Judge.

4 {1} Appellant Mayan Construction Inc. (Mayan) appeals the district court’s order

5 awarding Appellee Advantage Drilling, LLC (Advantage) $62,959.59 for breach of

6 contract. On appeal, Mayan argues that (1) the district court erred in awarding

7 contract damages because it did not find or conclude that Mayan had breached any

8 contract, and further, that insufficient evidence supported any finding or conclusion

9 that Mayan breached a contract; (2) the district court erred to the extent that it based

10 the damages award on an unjust enrichment theory; and (3) the district court erred in

11 ordering Mayan to reimburse Advantage for half of the cost of construction materials

12 purchased and retained by Mayan and requiring Mayan to act jointly with Advantage

13 in disposing the construction materials for Mayan’s failure to mitigate the damages

14 relating to the cost of the construction materials. We affirm in part and reverse in part.

15 BACKGROUND

16 {2} Mayan filed two actions in the district court: (1) an action to cancel a lien on

17 public property by Advantage and (2) a declaratory judgment action to declare the lien

18 invalid. After Granite RE, Inc. issued a lien release bond and the lien was cancelled,

2 1 Advantage filed a complaint for damages in the lien cancellation action against

2 Mayan, asserting claims for (1) breach of contract, (2) breach of a settlement

3 agreement, (3) judgment under the lien statutes, (4) breach of the covenant of good

4 faith and fair dealing, (5) judgment against the bond, and (6) unjust enrichment or

5 quantum meruit. The proceedings following Advantage’s complaint for damages are

6 the subject of this appeal.

7 {3} The circumstances of this case arose in connection with a project known as the

8 Isleta Drain Project (the Project). Engineered Structures, Inc. (ESI) was the general

9 contractor of the Project. In January 2006, ESI and Mayan entered into a subcontract

10 for Mayan to perform work on the Project, including dewatering the area and drilling

11 secant holes to support dirt work around the Project area.

12 {4} Mayan and Advantage negotiated in late 2005 and early 2006 for Advantage

13 to subcontract to drill dewatering holes in the channel and secant holes under the road.

14 The negotiations culminated in Advantage submitting two proposals: one for drilling

15 eight dewatering holes (18 inches in diameter and 60 feet deep) and another for

16 drilling two hundred and eighty secant holes.

17 {5} Mayan and Alan Regis, the qualifying and financially responsible agent for

18 Advantage, had done business together for years and had never entered into a written

19 contract for work performed. Breaking with this past practice, Advantage asked

3 1 Mayan for a written subcontract, which Mayan drafted and provided to Advantage for

2 review. Although the parties agreed to the price and services that Advantage was to

3 perform, the parties never reached an agreement on all the terms contained in the

4 subcontracts, and the parties never signed written subcontracts for either proposal.

5 {6} Despite not having agreed to the written subcontracts, on or about January 24,

6 2006, with Mayan’s consent, Advantage mobilized for the Project by moving several

7 pieces of equipment and its drill to the Project site. Advantage began drilling on

8 February 1 and continued on February 2 and 4. During the three days, Advantage

9 worked on drilling either two or four of the holes and only achieved a depth of ten feet

10 before the holes collapsed.

11 {7} On February 2, 2006, Advantage advised Mayan that Advantage did not agree

12 to the terms proposed in the two subcontracts that Advantage had requested, that

13 Advantage needed documents to review, and that Advantage had “no choice but to

14 stop work until these issues were resolved.” Advantage subsequently left the Project

15 site and did not continue drilling on February 3, 2006, and Mayan believed that

16 Advantage had abandoned the Project. After Advantage stopped work on the Project,

17 Mayan contacted two other companies inquiring whether they could perform the

18 dewatering drilling and secant drilling.

19 {8} Advantage moved the drill back to the job site and continued drilling on

4 1 Saturday, February 4, 2006 as well as Monday, February 6, 2006. On February 4,

2 2006, a principal of Mayan went to the job site and asked Advantage to stop drilling

3 and asked to buy out the “contracts.” After Advantage indicated that it wished to

4 continue working on the Project, Mayan informed Advantage “to reconsider it and to

5 think about it.” On February 6, 2006, Advantage “went back to drilling,” and Mayan

6 again asked to buy out the contract. Later that day, Mayan wrote a letter to

7 Advantage proposing to dissolve any verbal agreements between Advantage and

8 Mayan concerning the drilling and agreeing to disburse $309,000 over the course of

9 several months. That same day, Advantage wrote to Mayan rejecting the offer but

10 proposing different terms. On February 8, 2006, Advantage wrote back to Mayan,

11 again not accepting Mayan’s previous offer. On February 13, 2006, Advantage

12 provided Mayan a “settlement agreement” proposing several different terms from

13 those in the February 6, 2006 proposal drafted by Mayan. Mayan rejected the

14 proposed settlement agreement.

15 {9} The district court found that there was never a lawful contract, or written

16 settlement agreement, signed by both parties, which would require Mayan to pay

17 Advantage $309,000 or any other sum. The district court did, however, find that the

18 parties entered into the two subcontracts for dewatering and secant drilling, despite

19 acknowledging that the parties did not sign the written agreements and disagreed

5 1 about the inclusion of certain terms. The district court found that Mayan breached the

2 subcontracts and awarded damages for mobilization expenses, labor expenses, a one-

3 month rental of a drill rig, overhead costs, lost profit, security, and the cost of gravel,

4 which totaled $43,089.09. The district court also found that Advantage expended

5 $39,741.00 for construction materials for the Project. It found that both parties failed

6 to mitigate damages with respect to the construction materials and ordered that Mayan

7 reimburse Advantage for fifty percent of the cost, $19,870.50, and that the parties, as

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandoval v. Baker Hughes Oilfield Operations, Inc.
2009 NMCA 095 (New Mexico Court of Appeals, 2009)
Orion Technical Resources, LLC v. Los Alamos National Security, LLC
2012 NMCA 97 (New Mexico Court of Appeals, 2012)
Hickey v. Griggs
738 P.2d 899 (New Mexico Supreme Court, 1987)
Pope v. Gap, Inc.
1998 NMCA 103 (New Mexico Court of Appeals, 1998)
Montoya v. Pearson
2006 NMCA 097 (New Mexico Court of Appeals, 2006)
A.D. Powers v. Miller
1999 NMCA 080 (New Mexico Court of Appeals, 1999)
Weststar Mortgage Corp. v. Jackson
2003 NMSC 002 (New Mexico Supreme Court, 2002)
State v. Milligan
2012 UT App 47 (Court of Appeals of Utah, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Advantage Drilling, LLC v. Mayan Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/advantage-drilling-llc-v-mayan-construction-inc-nmctapp-2013.