Advanced Soil Technologies, Inc. v. Grow Group, Inc., Automotive Div.

85 F.3d 628, 1996 U.S. App. LEXIS 32424, 1996 WL 250481
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 10, 1996
Docket95-1090
StatusUnpublished

This text of 85 F.3d 628 (Advanced Soil Technologies, Inc. v. Grow Group, Inc., Automotive Div.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Soil Technologies, Inc. v. Grow Group, Inc., Automotive Div., 85 F.3d 628, 1996 U.S. App. LEXIS 32424, 1996 WL 250481 (6th Cir. 1996).

Opinion

85 F.3d 628

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
ADVANCED SOIL TECHNOLOGIES, INC., a foreign corporation,
Plaintiff/Counter Defendant-Appellant,
v.
GROW GROUP, INC., AUTOMOTIVE DIVISION, a foreign
corporation, Defendant/Counter Plaintiff-Appellee.

No. 95-1090.

United States Court of Appeals, Sixth Circuit.

May 10, 1996.

Before: KENNEDY and COLE, Circuit Judges; ALDRICH, District Judge.*

PER CURIAM.

Advanced Solid Technologies, Inc., ("AST") appeals from a jury verdict denying its claim for damages resulting from a breach of contract to remediate contaminated soil. AST claims the District Court erred when it denied its motion in limine to exclude evidence as to the amount of soil that could actually be extracted from Grow's cleanup site. AST argues that since its contract with Grow specified how tonnage would be measured--"actual tonnage will be determined by the weigh scale of AST's plant"--and that AST would be paid for each ton of soil remediated, Grow's proposed evidence estimating the amount of soil that had been excavated at its cleanup site was irrelevant and thus inadmissible. For the following reasons, we affirm.

* On August 18, 1993, AST brought a complaint against Grow for damages resulting from Grow's alleged breach of contract when Grow refused to continue paying AST to remediate chemical-laden soil located on Grow's property. AST's soil remediation process heats soils to a sufficient degree such that toxic chemicals are neutralized. AST sought roughly one million dollars for unpaid soil remediation services it provided to Grow.

Provisions eight and eight-a of the January 13, 1993 Proposal for Treatment of Contaminated Soil, which were incorporated into the contract, state that AST would provide the following services:

8. Thermal treatment of soils (Excluding Area B). Supply thermal equipment and operators, burner fuels, electricity, process shredding or screening, remoisturization, corrective action plan assistance, site safety and health plan, quality assurance/quality control, Soil Remediation Unit (SRU) supervision to ensure operations are within limits and capabilities of the SRU. AST reserves the right to dilute or mix the soils to ensure that Type B clean-up objectives are met while maintaining the safe operating parameters of the SRU.

47.50 per ton

8a. AST shall charge Grow Group, Inc. a fee only once for the thermal treatment of contaminated soils unless said soil is contaminated with previously unknown constituents which are not remediated to Type B Clean-Up Criteria with once through treatment. Otherwise additional treatment necessary to meet Type B clean-up objectives will be at AST expense.

Moreover, the parties agree that there was an oral agreement affecting section eight-a that placed a twenty percent cap on the amount of treated soil AST could add to the wet untreated soil without deducting that amount from the tonnage figures it would charge Grow. However, they disagreed as to when the twenty percent cap applied. Grow officials testified that they understood AST to agree not to dilute the untreated soil by more than twenty percent ever; AST officials testified that the cap was contingent upon receiving sufficiently dry soil.

On October 13, 1994 AST filed a motion in limine to exclude Grow's evidence regarding the amount of soil excavated at its site and other similar evidence of the amount of soil needing remediation. AST argued that since the contract specified that AST would be paid on a per-ton basis and that tonnage would be determined on the basis of AST's scale, Grow's estimates of soil excavated at its site were irrelevant to the amount of soil AST could properly bill Grow for remediating. In response, Grow argued that although the contract specified that AST would bill Grow on a per-ton basis, the contract also specified that AST would not charge Grow for soil that was sent through the soil remediation unit more than once if in excess of the twenty percent referred to above.

On October 24, 1994 the District Court held a hearing on AST's motion in limine. After Grow admitted it intended to submit evidence that AST's scales did not accurately record the amount of soil actually taken out of ground at Grow's cleanup site, the District Court denied AST's motion, stating:

[Y]ou have a grain of a well-founded theory in there and I'm going to accept that part of your theory, and that is, ultimately, I certainly cannot submit to the jury a theory of damages that doesn't take into account the specified terms of the contract, but I'm not going to exclude evidence which tends to show that there was inappropriate mixing--that the material was passed twice.

Yes, ultimately, the scale is the ultimate measure upon which you were to be paid, but their theory is that you put things over that scale more than one time, that your mixed inappropriately and that, therefore, they got billed a lot more than they should have. So I think I understand quite clearly what my obligation is to the jury, and it may be that in, with more context in the course of the trial that I may find some evidence excludable, but for now, I think that their theory of defense fully supports the introduction of some evidence of what passed over, of why the numbers that were reflected on that scale were inappropriate under the contract, under other terms of the contract, so motion denied.

After a trial in which Grow introduced evidence of the amount of soil actually excavated at the site, the jury rejected AST's claim for unpaid services.1 AST filed a timely notice of appeal.

II

On appeal, AST argues that the District Court erred in denying its motion in limine because the contract expressly stated that tonnage would be determined by the weigh scale at AST's plant; since the contract specifies how AST will charge Grow for remediating soil, evidence of alternative measures of soil is irrelevant under FED.R.EVID. 401 and thus inadmissible under FED.R.EVID. 402. We review the District Court's interpretation of the contract between AST and Grow, the legal component of the District Court's decision to deny AST's motion in limine, de novo. Miller v. Field, 35 F.3d 1088, 1090 (6th Cir.1994). We would ordinarily review the District Court's denial of AST's motion in limine for abuse of discretion. Zamlen v. City of Cleveland, 906 F.2d 209, 215 (6th Cir.1990), cert. denied, 499 U.S. 936 (1991). However, since during trial AST did not renew its objection to the admission of the evidence it sought to exclude in its motion in limine, it has waived its right to challenge that evidence. Thus we review only for plain error. See United States v. Bonds, 12 F.3d 540, 569 (6th Cir.1993).

Under FED.R.EVID.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
85 F.3d 628, 1996 U.S. App. LEXIS 32424, 1996 WL 250481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-soil-technologies-inc-v-grow-group-inc-automotive-div-ca6-1996.