Advance Iron Works, Inc. v. Contegra Construction Co., LLC

2025 IL App (1st) 191525-U
CourtAppellate Court of Illinois
DecidedJanuary 24, 2025
Docket1-19-1525
StatusUnpublished

This text of 2025 IL App (1st) 191525-U (Advance Iron Works, Inc. v. Contegra Construction Co., LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advance Iron Works, Inc. v. Contegra Construction Co., LLC, 2025 IL App (1st) 191525-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (1st) 191525-U No. 1-19-1525 Order filed January 24, 2025 Fifth Division

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________

ADVANCE IRON WORKS, INC., ) Appeal from the ) Circuit Court of Plaintiff-Appellee and Cross-Appellant, ) Cook County. ) v. ) No. 13 L 9267 ) CONTEGRA CONSTRUCTION COMPANY, LLC, ) ) Honorable Defendant-Appellant and Cross-Appellee. ) Bridget A. Mitchell, ) Judge Presiding.

JUSTICE NAVARRO delivered the judgment of the court. Presiding Justice Mikva and Justice Oden Johnson concurred in the judgment.

ORDER

¶1 Held: The trial court did not err when it rejected defendant’s collateral attack, res judicata, and collateral estoppel affirmative defenses and when it denied defendant’s motion for judgment notwithstanding the verdict. The trial court did not abuse its discretion when it denied, in part, plaintiff’s petition for attorney fees and costs.

¶2 In 2011, defendant, Contegra Construction Company, LLC, and plaintiff, Advance Iron

Works, Inc. (AIW), entered into a contract involving metal fabrication for a crime lab in Bellville,

Illinois. In 2012, Contegra filed a replevin action against AIW, seeking replevin of steel and No. 1-19-1525

materials under the contract based on its allegations that it paid AIW for more fabricated steel than

AIW had delivered to the project site. Thereafter, in 2013, AIW filed the instant action against

Contegra. Following a jury trial, the jury found in favor of AIW on its claims for breach of contract,

fraud, trespass, wrongful replevin, defamation, and slander of title. The jury awarded

compensatory and punitive damages to AIW. The trial court denied Contegra’s motion for

judgment notwithstanding the verdict and for a new trial and it granted in part and denied in part

AIW’s motion for attorney fees and costs.

¶3 Contegra appeals, contending that AIW’s claims are barred by the collateral attack

doctrine, res judicata, and collateral estoppel. Contegra also raises numerous issues with the jury’s

verdict finding in favor of AIW and argues that the trial court erred when it denied Contegra’s

motion for judgment notwithstanding the verdict. AIW filed a cross-appeal challenging the trial

court’s order on its motion for attorney fees and costs. This order addresses both the appeal and

cross-appeal. For the reasons that follow, we affirm the trial court’s order denying Contegra’s

motion for judgment notwithstanding the verdict as well as its order granting in part and denying

in part AIW’s motion for attorney fees and costs.

¶4 I. BACKGROUND

¶5 This case involves issues relating to a contractual dispute between AIW and Contegra

involving the construction of the Metro East Forensic Lab (project) for the Illinois State Police in

Belleville, Illinois. The project was under the direction of the Illinois Capital Development Board

(CDB), and Contegra was the general contractor for the project. In December 2011, Contegra and

AIW, a steel fabricator, entered into a contract whereby AIW agreed to provide Contegra

fabricated steel for the project in exchange for a payment of $1,283,490.

-2- No. 1-19-1525

¶6 In January 2012, AIW began fabricating and shipping the steel for the project. The original

February 28, 2012, steel erection date for the project set forth in the contract was delayed due to

issues related to the architectural steel drawings as well as a plumbing problem at the project.

Thereafter, in August 2012, Contegra stopped making payments in response to AIW’s payment

applications, and a dispute arose between the parties relating to Contegra’s payments to AIW and

whether AIW was timely delivering fabricated steel to the project for the construction of the

building.

¶7 In October 2012, Contegra filed an action for replevin against AIW, alleging that it was

entitled to possession of the steel that AIW failed to deliver to the project site. During the replevin

action, AIW filed a petition for bankruptcy in the United States Bankruptcy Court for the Northern

District of Illinois, which was eventually dismissed. In August 2013, AIW filed the instant action

against Contegra, alleging numerous claims, including wrongful replevin, trespass, fraud,

defamation, and slander of title.

¶8 Contegra’s Action of Replevin

¶9 On October 26, 2012, Contegra filed a complaint against AIW, alleging that despite

repeated demand, AIW failed to timely deliver the fabricated materials to comply with the contract

and the contemplated timeline for the project. Contegra alleged that it had paid for 50% of the

services and materials under the contract and that AIW had delivered only 35% of the fabricated

steel under the contract. Contegra alleged that AIW’s refusal to timely deliver the fabricated

materials and drawings under the contract delayed the completion of the project.

¶ 10 Contegra alleged a claim for replevin of materials, asserting that it was the owner of the

undelivered materials and that AIW was in possession of $269,450 worth of materials that had not

been delivered to Contegra. In the alternative, Contegra alleged that if the court found that

-3- No. 1-19-1525

Contegra was not the owner of the materials, Contegra held a “properly perfected, first-priority

security interest” in the materials, as it had filed a UCC-1 financing statement (UCC-1) with the

Illinois Secretary of State on February 6, 2012. Contegra also alleged claims for conversion, breach

of contract, and unjust enrichment.

¶ 11 On November 2, 2012, the parties entered an agreed order that provided that on November

5, 2012, Contegra’s representatives would conduct an inspection at AIW’s premises, and if its

inspectors were reasonably satisfied with the inspection, it would pay $221,654.40 to AIW by

November 6, 2012.

¶ 12 On November 16, 2012, the court entered a written order, finding that Contegra was

entitled to possession of certain materials. The record also contains a “Replevin Bond” dated

November 16, 2012, and signed by Contegra and Travelers Casualty and Surety Company

(Travelers).

¶ 13 On November 19, 2012, the court entered a written order modifying the November 16,

2012, replevin order, which provided that Contegra was not entitled to “replevy any steel unless it

has been completely fabricated by AIW and marked to correspond to the project” and it was not

entitled to “any steel considered to be work in progress or raw steel.” The court also stated that

Contegra could replevy final shop drawings for the project but that it could not share shop drawings

with any competing steel fabricator for the purpose of fabricating steel for this project. The court

also denied AIW’s request for an interim stay of enforcement of the order of replevin, and it gave

AIW time to file an answer or otherwise plead to the initial complaint.

¶ 14 On November 20, 2012, Contegra proceeded with the replevin. On this same day, AIW

filed a petition for relief under chapter 11 of the United States Bankruptcy Code in the United

States Bankruptcy Court in the Northern District of Illinois. On November 30, 2012, December 4,

-4- No. 1-19-1525

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Farm Mutual Automobile Insurance v. Campbell
538 U.S. 408 (Supreme Court, 2003)
Carroll v. Curry
912 N.E.2d 272 (Appellate Court of Illinois, 2009)
Bryson v. News America Publications, Inc.
672 N.E.2d 1207 (Illinois Supreme Court, 1996)
Alton Banking & Trust Co. v. Schweitzer
460 N.E.2d 105 (Appellate Court of Illinois, 1984)
Myers v. Popp Enterprises, Inc.
576 N.E.2d 452 (Appellate Court of Illinois, 1991)
Todd W. Musburger, Ltd. v. Meier
914 N.E.2d 1195 (Appellate Court of Illinois, 2009)
Steinberg v. Chicago Medical School
371 N.E.2d 634 (Illinois Supreme Court, 1977)
Green v. Rogers
917 N.E.2d 450 (Illinois Supreme Court, 2009)
Buckholtz v. MacNeal Hospital
785 N.E.2d 162 (Appellate Court of Illinois, 2003)
General Electric Credit Auto Lease, Inc. v. Jankuski
532 N.E.2d 361 (Appellate Court of Illinois, 1988)
Heider v. Leewards Creative Crafts, Inc.
613 N.E.2d 805 (Appellate Court of Illinois, 1993)
Gaston v. Founders Insurance
847 N.E.2d 523 (Appellate Court of Illinois, 2006)
Johnson v. Tipton
431 N.E.2d 464 (Appellate Court of Illinois, 1982)
Kumaran v. Brotman
617 N.E.2d 191 (Appellate Court of Illinois, 1993)
Seith v. Chicago Sun-Times, Inc.
861 N.E.2d 1117 (Appellate Court of Illinois, 2007)
Gomez v. the Finishing Co., Inc.
861 N.E.2d 189 (Appellate Court of Illinois, 2006)
Limanowski v. Ashland Oil Co., Inc.
655 N.E.2d 1049 (Appellate Court of Illinois, 1995)
Wartalski v. JSB Construction & Consulting Co.
892 N.E.2d 122 (Appellate Court of Illinois, 2008)
Spurgeon v. Mruz
832 N.E.2d 321 (Appellate Court of Illinois, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (1st) 191525-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advance-iron-works-inc-v-contegra-construction-co-llc-illappct-2025.