Adrian Buckhannon Bank v. Sandridge & Sandridge, Inc.

9 S.E.2d 232, 122 W. Va. 343, 1940 W. Va. LEXIS 61
CourtWest Virginia Supreme Court
DecidedMay 28, 1940
Docket9040
StatusPublished
Cited by3 cases

This text of 9 S.E.2d 232 (Adrian Buckhannon Bank v. Sandridge & Sandridge, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adrian Buckhannon Bank v. Sandridge & Sandridge, Inc., 9 S.E.2d 232, 122 W. Va. 343, 1940 W. Va. LEXIS 61 (W. Va. 1940).

Opinions

*344 Hatcher, Judge:

This is a suit to recover from defendant Indemnity Company, surety on the road construction bond of Sandridge & Sandridge, contractors, money advanced by plaintiff Bank to the contractors, enabling them to complete the work. In their application for the bond, the contractors agreed to assign as collateral to Indemnity the amount finally due on the work. Indemnity has paid for the contractors a sum in excess of this amount. The final estimate check was delivered to Indemnity by the State Road Commission. That check is the real bone of contention. Bank recovered a decretal judgment in full of its claim.

The cause was referred to a commissioner, and his history thereof and findings thereon, approved by the trial chancellor, are so able that we copy from them at length, as follows:

“I find that Sandridge & Sandridge, Incorporated, was the successful bidder for building and completing, according to the plans of the State Road Commission, a road in Marion County, West Virginia, known as ‘Conaway Bridge —Farmington Project No. 847-A;’ that on June 24, (1935) it entered into a contract for the completion of said project and executed a bond as required by the statute with the Glens Falls Indemnity Company as surety thereon, * * *. The bond was signed ‘Sandridge & Sandridge, Inc., by Lee J. Sandridge, President, Glens Falls Indemnity Company, by C. R. Morgan, Attorney.’

“I find that for about two and a half months immediately preceding June, 1936, the work on the project had been completely suspended because of lack of funds; that the contractor had exhausted its ability to get funds, and could not provide or procure funds to complete the contract; that prior to or about the first of June, the commission had forced the contractor to resume work without funds to meet its payrolls; that on or about June 5, 1936, Lee J. Sandridge, president of the contractor company, took the books and records of the contractor to Morgan’s office in the City of Charleston for the purpose of turning over the books and records to Morgan and making default in the *345 contract; that Sandridge told Morgan that the surety on the bond would be compelled to take over or finance the project; that Morgan protested against any default on the part of the contractor and stated to Sandridge that the contractor would be able to complete the project at much less cost than would the surety were it forced to do so; that Morgan suggested to Sandridge that he go to the Bank of Adrian for financial assistance; that neither Sandridge nor his company had ever had any dealings with the bank, and Sandridge advised Morgan that he did not know any of the bank officials; that Morgan told Sandridge he would call the cashier of the bank and assist Sandridge in getting the bank to advance the funds; that it was agreed between Morgan and Sandridge that for’ the funds advanced, the contractor would execute to the bank assignments of the estimates on the work, and a letter authorizing the commission to deliver to Morgan the checks on these assignments, and that Morgan in turn would forward these checks to the bank.

“I further find that Morgan did call the cashier of the bank and advised him that the contractor was in need of funds to complete the contracts; that he, Morgan, represented the bonding company that was surety on the contractor’s bond; that if the bank would provide the funds and take assignments on the estimates, he would withdraw the estimate checks and mail the same to the bank; that on his way home from this conference with Morgan, Sandridge talked to the cashier of the bank briefly about the arrangement and a few days later went to the bank where the arrangements were concluded, and the first loan' of $410.00 was made, evidenced by note of Sandridge & Sandridge to the bank, payable ‘Out of State Estimate— Marion County Project.’ It is significant that the cashier of the bank says that he was not advised of the financial condition of the contractor, but Sandridge says that he so advised the cashier. Sandridge & Sandridge, as well as its president, was a stranger to the bank and its officials. No financial statement, recommendation or security on the notes representing these loans, was required. The cashier, Stump, was an experienced banker. At the time of each *346 loan an assignment of the estimate was made and forwarded to Morgan. The letter from Sandridge and Sand-ridge to Morgan authorizing him to withdraw checks on the estimates and deliver them to the bank was written to Morgan. The bank was secure if its agreement with Morgan was carried out. No loan was made without an assignment of the estimate. That the financial condition of Sandridge & Sandridge under these circumstances did not enter into the making of the loan is apparent. It is not reasonable to say that the bank would have extended this line of credit to a stranger without investigation as to financial standing, without recommendation, and without security for its loan.

“I, therefore, find that the loans were not made on the credit of Sandridge and Sandridge, Incorporated, but were made on the understanding and agreement between Morgan and the bank, and Morgan’s promise to withdraw and deliver the checks to the bank; that in making these loans, the bank relied upon the agreement and promise aforesaid; and that assignments of the estimates were secured and forwarded to Morgan and he was authorized by letter to withdraw the checks from the commission, as agreed.

“Beginning with the month of June, 1936, the plaintiff bank advanced weekly, sums aggregating $16,991.31 to meet the contractor’s payrolls until the completion of the contract. These advancements are evidenced by notes executed by the contractor, payable to the bank, ‘Out of State Estimates on Marion County Project.’ Thirteen notes dated June 8, 1936, and each week thereafter up to and including August 31, 1936, aggregating $8,532.31, were paid from the checks of the commission on current monthly estimates, issued to the contractor, and delivered to C. R. Morgan and by him to the bank. Eleven advancements or loans, as the case may be, evidenced by like notes, payable as above, bearing date of September 7, 1936, and each week thereafter, — the last November 17, 1936, were made. These eleven notes aggregating $8,459.09, exclusive of interest, represent the claim of debt of the bank. The final estimates of the commission for the period from October 1, *347 1936, to the completion of the project, show due the contractor the sum of $11,065.11, made up of work done and materials furnished, not included in previous current estimates, in the amount of $3,997.92, and retained percentage amounting to $7,531.61. All prior estimates made subsequent to June 8, 1936, under the agreement between the bank and Morgan were applied on the loans made between June and September 7, 1936.

“I further find that at the time of executing the first of the eleven notes, Sandridge & Sandridge executed the following writing: ‘For value received in the amount of $735.00 we the undersigned hereby assign and transfer to the Adrian Bank of Adrian, W. Va., the payroll beginning on Aug.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Axelrod v. Premier Photo Service, Inc.
173 S.E.2d 383 (West Virginia Supreme Court, 1970)
CENTRAL ELECTRIC CREDIT CORPORATION v. Fields
133 S.E.2d 780 (West Virginia Supreme Court, 1963)
Wright v. Shortridge
73 S.E.2d 360 (Supreme Court of Virginia, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
9 S.E.2d 232, 122 W. Va. 343, 1940 W. Va. LEXIS 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adrian-buckhannon-bank-v-sandridge-sandridge-inc-wva-1940.