Admiral Plastics Corp., and Cross-Appellant v. Trueblood, Inc., and Cross-Appellee

436 F.2d 1335, 32 Ohio Misc. 25, 8 U.C.C. Rep. Serv. (West) 753, 58 Ohio Op. 2d 147, 1971 U.S. App. LEXIS 11920
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 10, 1971
Docket20383, 20384
StatusPublished
Cited by6 cases

This text of 436 F.2d 1335 (Admiral Plastics Corp., and Cross-Appellant v. Trueblood, Inc., and Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Admiral Plastics Corp., and Cross-Appellant v. Trueblood, Inc., and Cross-Appellee, 436 F.2d 1335, 32 Ohio Misc. 25, 8 U.C.C. Rep. Serv. (West) 753, 58 Ohio Op. 2d 147, 1971 U.S. App. LEXIS 11920 (6th Cir. 1971).

Opinion

WEICK, Circuit Judge.

This appeal arose out of an action for damages filed in the District Court by Admiral Plastics Corporation (Admiral) of New York against Trueblood, Inc. (Trueblood) of Dayton, Ohio, for breach of a contract in which Trueblood agreed to design and manufacture for Admiral three injection blow mold machines, at a cost of $39,750.00 per machine. Jurisdiction was based on diversity of citizenship. The case was governed by Ohio law.

The District Court, sitting without a jury, found that both parties failed to act in good faith and failed to cooperate in the performance of the contract, thus rendering the contract void. The District Court entered judgment in favor of Admiral for $29,812.50, which was the amount of its down payment to True-blood, and dismissed Trueblood’s counterclaim. Both parties appeal. We affirm.

In 1965, Admiral was a leading manufacturer and supplier of plastic containers, which were extensively used in the food, beverage and pharmaceutical industries. Admiral could not meet the ever-increasing demand for its product, and as a result, began investigating machine manufacturing companies to determine which company could best supply Admiral with the injection blow mold machines it needed to increase production. Paul Marcus, the chief engineer for Admiral, contacted Trueblood, a manufacturer of injection mold machines, and was informed that Trueblood had never built a blow mold machine, but would consider doing so if Admiral provided the specifications.

Marcus made several trips to True-blood's plant, the last preliminary meeting being on May 17, 1966. At this meeting Marcus described the features of the machine required by Admiral and stated that it would want Trueblood to *1337 build only the rear portion of the machine, in order to protect Admiral’s trade secrets. On May 24, 1966, Marcus called Trueblood, and asked for a firm quotation on the price of the machine. Trueblood quoted $39,750.00 per machine, and Marcus ordered three machines to be manufactured by Trueblood. Marcus stated that the written purchase order, the specifications, and a check for 25% of the total purchase price would be forthcoming.

By June 22, 1966, Trueblood had not received the purchase order, specification letter, or check from Admiral. Trueblood advised Marcus of this fact, and on June 28, Marcus informed True-blood that the purchase order had been written, but would not be sent until the middle of July, at the end of Admiral’s fiscal year. Thereafter, on July 20, 1966, Trueblood received from Admiral a check for $29,812.50, a six-page specification letter dated May 24, 1966, and the purchase order.

The specification letter stated that Trueblood would redesign (where necessary), manufacture, assemble arid test three injection blow molding machines and furnish all engineering drawings of the machine and that the delivery dates for the machines were November 1, November 15, and December 1, 1966. On July 21, 1966, Trueblood informed Admiral that there were discrepancies between the specification letter and the previous discussions with Marcus. After being assured that the specifications would be revised, Trueblood deposited Admiral’s check of $29,812.50, but did not sign the purchase order.

On August 25, 1966, Marcus visited Trueblood’s plant, and expressed concern over the lack of progress in the construction of the machines, and the fact that Trueblood had not forwarded the design drawings. Marcus was informed that the component parts had been ordered, and also that Trueblood had not received the revised specifications. Marcus revised the specifications upon his return to New York, and Trueblood received them on September 9, 1966. These revised specifications satisfied Trueblood, except for the terms of payment, and the fact that Trueblood considered the data on the machine’s automatic sequence of operation to be inadequate.

On October 19, 1966, an engineer of Admiral visited Trueblood’s plant, and discovered that little work had been done on the manufacture of the machines. Only one of the three machines ordered was in any stage of construction, and only to the extent of the basic weldment.

On October 26, 1966, Marcus informed Trueblood that one of the component parts ordered by Trueblood, the Egan re-ciproserew, was the wrong size, and that a larger one was required. Trueblood told Marcus that to reorder the part would entail added expense. Marcus instructed Trueblood to order the larger re-ciproscrew, and that Admiral would bear the added expense.

No design drawings of the machines were furnished to Admiral as of November, 1966. On November 11, 1966, a Trueblood official visited Admiral’s plant, to observe Admiral’s machines in operation, in order to aid Trueblood in the making of the design drawings. However, no drawings were ever furnished to Admiral.

On December 1, 1966, the Admiral engineer again visited Trueblood’s plant, and again observed little progress on the construction of the machines. He was informed that the earliest possible delivery date would be March 1, 1967. Thereafter, on December 8, 1966, Admiral’s attorney contacted Trueblood, asserting that Trueblood was in default, and threatened legal action unless Trueblood signed the purchase order. At this same time, Trueblood ceased work on the drawings and on the machines. No machine was ever delivered *1338 to Admiral, and Trueblood did not return the $29,812.50 down payment. 1 Both parties claimed substantial damages as the result of the other’s alleged lack of performance and breach of contract.

The District Court held that Admiral and Trueblood entered into a valid contract, under Ohio Rev.Code § 1302.07 (U.C.C. 2-204):

(A) A contract for sale of goods may be made in any manner sufficient to show agreement, including conduct by both parties which recognizes the existence of such a contract.
(B) An agreement sufficient to constitute a contract for sale may be found even though the moment of its making is undetermined.
(C) Even though one or more terms are left open a contract for sale does not fail for indefiniteness if the parties have intended to make a contract and there is a reasonably certain basis for giving an appropriate remedy.

With this there can be no dispute. The District Court recognized that the contract was one for the manufacture and sale of unique machines, in the designing of which neither company had any experience. It was understandable therefore, that certain terms were left unspecified and that difficulty was encountered in designing and producing the machines. This in no way detracts from the validity of the contract.

The nature of the contract made it imperative that both parties cooperate to the fullest extent in order for the machines to be successfully designed and built. The U.C.C. recognizes such situations where good faith and cooperation are necessary to the successful fulfillment of a contract. Ohio Rev.Code §§ 1301.09 and 1302.24 (U.C.C. 1-203 and 2-311).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlas Noble, LLC v. Krizman Enterprises
692 F. App'x 256 (Sixth Circuit, 2017)
In re Rezulin Products Liability Litigation
210 F.R.D. 61 (S.D. New York, 2002)
G/GM Real Estate Corp. v. Svisse Chalet Motor Lodge of Ohio, Inc.
4 Ohio App. Unrep. 80 (Ohio Court of Appeals, 1990)
The Mann And Parker Lumber Company v. Wel-Dri
579 F.2d 973 (Sixth Circuit, 1978)
Mann & Parker Lumber Co. v. Wel-Dri
579 F.2d 973 (Sixth Circuit, 1978)
Hayes v. Hettinga
228 N.W.2d 181 (Supreme Court of Iowa, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
436 F.2d 1335, 32 Ohio Misc. 25, 8 U.C.C. Rep. Serv. (West) 753, 58 Ohio Op. 2d 147, 1971 U.S. App. LEXIS 11920, Counsel Stack Legal Research, https://law.counselstack.com/opinion/admiral-plastics-corp-and-cross-appellant-v-trueblood-inc-and-ca6-1971.