Adkins v. State Road Commission

1 Ct. Cl. 280
CourtWest Virginia Court of Claims
DecidedSeptember 19, 1942
DocketNo. 107; No. 108; No. 109; No. 110
StatusPublished

This text of 1 Ct. Cl. 280 (Adkins v. State Road Commission) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adkins v. State Road Commission, 1 Ct. Cl. 280 (W. Va. Super. Ct. 1942).

Opinions

WALTER M. ELSWICK, Judge.

These four claims, heard together by agreement, are made upon a quantum meruit basis for work and services performed by the claimants, and for use of their four trucks in and about the construction of about five miles of road extending from the main state highway between Hamlin and West Hamlin in Lincoln county up Mud river toward the Logan county line. The work consisted of hauling stone from two to three miles for laying a rock base on this stretch of road. The work was being carried on under a commitment by the state road commission to sponsor for the works progress administration of the Federal Government a project commonly known in that vicinity as project No. 76 upper Mud river road, Lincoln county, West Virginia.

It appears from the evidence that each federal project must have a sponsor, which in all cases was the state, or a political subdivision such as a city, county or another federal agency. The state road commission on all state road projects was obligated to contribute from 20% to 25% of the total costs of the construction. The sponsor’s contribution in such instances was made by the use of equipment furnished by the state road commission, with operators, such as trucks, road graders, rollers, power shovels, etc. All labor on the project except the operators of the state road commission’s equipment, was furnished by the Federal Government. So long as the state road commission furnished sufficient equipment to equal the 20% to 25% as the case may be, of the total costs of the project for which it was obligated under its commitment, the Federal Government could then issue purchase orders for use of other or additional equipment such as trucks and operators from.its [282]*282fund known as “other funds.” But whenever the sponsor failed to keep a sufficient amount of equipment in use on the project to equal the proportion it was to supply it appears that the Federal Government could not issue purchase orders out of its “other funds” to supply the deficiency on the part of the sponsor. (Record pp. 45, 135, 164, 170, 175; Lunsford’s depositions pp. 18, 19).

It further appears from the evidence that the Federal Government regularly furnished the labor of about seventy-five men on this particular project (record pp. 168, 169). The costs of labor and equipment supplied by the Federal Government was compared with the sponsor’s contribution under its commitment from forms made out and signed by the sponsor’s agent, the project superintendent, the area engineer, and the timekeeper, the first mentioned being an employee of the state road commission, and the last three being employees of the Federal Government. These report forms were known as form 710, one copy of which was furnished to the sponsor, the state road commission, and another copy to the Federal Government. (Record p. 171).

It further appears from the evidence that the road being constructed was an important one running through the center of Lincoln county, from near its county seat to the Logan county line; that this part of the road was accepted when the rock base was laid and that the state road commission continued to sponsor other projects on the same road further on up the river and into Logan county, and surface treated all of the same. However, on or about the 27th day of August 1937, while the construction of the first five miles was in progress, certain officials of the works progress administration discovered that there was a marked shortage of equipment contributed by the road commission on the project, and an investigation was ordered. It was found that the Federal Government was spending more money for equipment than required, and that while the state road commission still operated certain equipment on the project, it was not sufficient to match the amount of .contribution under its commitment as sponsor of the road [283]*283work. The state road commission had taken the state trucks off the project in an emergency to take care of their regular maintenance of other roads (record p. 174) and the particular equipment needed at the time to make up the deficiency in its contribution was found to be trucks for hauling the base stone. The state road commission had only one truck on the project at the time of the investigation. The acting branch engineer of the works progress administration had received instructions that if it were impossible for the state road commission to furnish the additional trucks required, the work on this road should be discontinued until such time as proper equipment could be furnished. Under the commitment of the state road commission, if the work was closed down as much as three days, for lack of sufficient equipment, the project would be closed, and it would then be necessary to go through a lengthy procedure of making a new commitment as sponsor, which procedure usually required from three to four months to get such renewed sponsorship in operation. (Record p. 175).

The acting district engineer for the works progress administration, on August 29,1937 went to the project in Lincoln county and advised the superintendent of the project, and other officials in Lincoln county of the necessity of closing down the project unless additional trucks were supplied to comply with the sponsor’s commitment. The claimants, prior to this, had received purchase orders for the use of their trucks, from time to time, from the Federal Government. On certain occasions they had been instructed to proceed with their work prior to the time that they had received purchase orders, although it appears that the Federal Government had a rule not to pay for work on which a purchase order had not been issued prior to the time that it was performed (record pp. 28, 44, 66 and 147). While said engineer was in Lincoln county on this visit, it appears that Caudle Adkins, the county supervisor for the works progress administration, and Elza B. Adkins, its superintendent, contacted the claimants and secured their promises to use their trucks on the project a few days in order to hold the project intact, which they did, some beginning work during the last days in August 1937 and others beginning work in [284]*284September 1937. It appears that claimants received assurances from time to time by the works progress administration engineer and other members of its officials connected with the work that they would receive pay for their services. They continued on with their work with the use of their trucks until the 8th day of March 1938.

The road work progressed satisfactorily to all concerned, except the claimants, on the project until it was completed. It is not denied that each of the claimants performed the work for which they have filed claims, and that they have not been paid. In addition thereto these facts were fully established by the evidence. It also appears that the state road commission received credit on its commitment as sponsor of the project for the greater portion of these services performed by claimants. It also accepted the road and all benefits derived from the completion of the project. It appears from the reports made on form 710 showing contributions made by the sponsor as its proportionate part of its commitment that the claimants were contributing the work. It further appears from the evidence that they did not sign these reports or authorize them to be signed on their behalf, and that they were not aware of the fact that the state road commission was receiving. credit for their services on its sponsorship of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
1 Ct. Cl. 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adkins-v-state-road-commission-wvctcl-1942.