ADF International, Inc. v. Steelcon, Inc.

409 F. Supp. 2d 836, 2005 U.S. Dist. LEXIS 21576, 2005 WL 2396999
CourtDistrict Court, E.D. Michigan
DecidedSeptember 28, 2005
Docket04-72940
StatusPublished
Cited by1 cases

This text of 409 F. Supp. 2d 836 (ADF International, Inc. v. Steelcon, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ADF International, Inc. v. Steelcon, Inc., 409 F. Supp. 2d 836, 2005 U.S. Dist. LEXIS 21576, 2005 WL 2396999 (E.D. Mich. 2005).

Opinion

OPINION AND ORDER GRANTING CROSS MOTIONS FOR SUMMARY JUDGMENT

ROBERTS, District Judge.

I. INTRODUCTION

This matter is before the Court on the parties cross-motions for summary judgment. The Court GRANTS both motions.

II. BACKGROUND

This matter arises from the construction of the Detroit Lions Stadium at Ford Field, which the parties refer to as the Detroit Lions Ford Field Project (“the Project”). The general contractor on the Project was Hunt Construction Group, Inc. (“Hunt”). Plaintiff ADF International Inc. (“ADF”) was Hunt’s structural steel subcontractor. ADF subcontracted a portion of its work to Sova Steel, Inc. (“Sova”), which subcontracted some of its work to Defendant Steelcon, Inc. (“Steelcon”).

Three companies to which Steelcon subcontracted its work, Laramie, Inc. (“Laramie”) Midland Equipment Company of Michigan, Inc. (“Midland”), and AME, *838 Inc., d/b/a Eugenio Painting Company (“Eugenio”), sued Steelcon in two actions in Wayne County Circuit Court. 1 They alleged that Steelcon failed to pay them in full. In each suit, Hunt and its sureties, United States Fidelity and Guaranty Company (“USF & G”) and St. Paul Fire and Marine Insurance Company (“St.Paul”), were also sued for payment under the respective surety bonds. The USF & G and St. Paul surety bonds assured payment and performance of the obligations of Hunt and its subcontractors.

In Laramie’s case, the trial court granted Laramie’s motion for summary disposition against Hunt, USF & G and St. Paul and entered a judgment against them in the amount of $370,344.14. In Eugenio and Midland’s case, Steelcon filed a cross-claim against Hunt and its sureties and a third-party claim against the company that provided a surety bond on ADF’s behalf, American Casualty Company of Reading, Pennsylvania (“CNA”). ADF’s surety bond assured payment and performance of ADF’s obligations to its subcontractors. Steelcon alleged in the cross-claim that it had not been fully paid by ADF and, therefore, sought payment under the surety bonds. On the day of trial, Steelcon entered into a Consent Judgment with Eugenio and Midland, but proceeded to trial on its claims against Hunt, USF & G, St. Paul and CNA.

One issue in the trial was whether there was a contract between ADF and Steelcon. Initially, there was no direct contract between the parties. ADF subcontracted work to Sova, and Sova subcontracted work to Steelcon. However, ADF, Sova and Steelcon later entered into a joint agreement, called Addendum No. 1, wherein they agreed to modify their respective subcontracts on pricing. The jury returned a verdict in favor of Steelcon against USF & G, St. Paul and CNA. The jury also found that there was a contract between ADF and Steelcon and that the contract was breached by ADF. The jury awarded Steelcon $2 million in damages.

ADF subsequently filed this action against Steelcon asserting several claims under the Addendum No. 1 contract: indemnification (Count I), breach of contract (Count II), and unjust enrichment (Count III). ADF alleges that Steelcon breached various provisions of the contract regarding labor and materials; misappropriated payments made by ADF; and, caused ADF to incur liability via subcontractors Laramie, Eugenio and Midland’s (collectively “the subcontractors”) lawsuits. ADF claims Steelcon is obligated to reimburse ADF for this liability under Addendum No. 1. Steelcon filed a one-count counterclaim alleging that $3.5 million dollars was owed to it by ADF for work done on the Project. Because it only received $2 million in damages from the sureties via the jury award, Steelcon alleges that ADF owes the remaining $1.5 million.

ADF was not a party to either state court action. However, Steelcon contends that sureties USF & G, St. Paul and CNA were in privity with ADF and asserted ADF’s affirmative defenses, claims and charge-backs 2 against Steelcon. Per Steelcon, the sureties argued that they did not owe anything to Steelcon when all of ADF’s claims, defenses and charge-backs were credited. Instead, the sureties claimed that Steelcon owed $869,000 to ADF. Steelcon contends that ADF now makes the same .arguments on its own behalf in this action, which Steelcon argues is an inappropriate attempt to relitigate *839 claims that ADF essentially lost (via the sureties) in the state court action. Therefore, Steelcon moves for summary judgment alleging that res judicata and collateral estoppel bar ADF from relitigating any aspect of the claims decided in state court.

Because it was not a party to the state court litigation, ADF disputes Steelcon’s assertion that res judicata and collateral estoppel bar its (ADF’s) claims in this action. However, ADF asserts that Steel-con’s counterclaim is barred by res judicata because Steelcon already litigated the same claim for damages that it makes here.

III. STANDARD OF REVIEW

Under Fed. R. Civ. P 56(c), summary judgment may be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Copeland v. Machulis, 57 F.3d 476, 478 (6th Cir.1995). A fact is “material” and precludes a grant of summary judgment if “proof of that fact would have [the] effect of establishing or refuting one of the essential elements of the cause of action or defense asserted by the parties, and would necessarily affect application of appropriate principle^] of law to the rights and obligations of the parties.” Kendall v. Hoover Co., 751 F.2d 171, 174 (6th Cir.1984). The court must view the evidence in the light most favorable to the nonmoving party and it must also draw all reasonable inferences in the nonmoving party’s favor. Cox v. Kentucky Dept. of Transp., 53 F.3d 146, 150 (6th Cir.1995).

The moving party bears the initial burden of showing that there is no genuine issue of material fact. Snyder v. Ag Trucking, Inc., 57 F.3d 484, 488 (6th Cir.1995). To meet this burden, the movant may rely on any of the evidentiary sources listed in Rule 56(c). Cox, 53 F.3d at 149. Alternatively, the movant may meet this burden by pointing out to the court that the nonmoving party, having had sufficient opportunity for discovery, has no evidence to support an essential element of his or her case, and on which that party will bear the burden of proof at trial. Tolton v. American Biodyne, Inc., 48 F.3d 937 (6th Cir.1995); Street v. J.C. Bradford & Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
409 F. Supp. 2d 836, 2005 U.S. Dist. LEXIS 21576, 2005 WL 2396999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adf-international-inc-v-steelcon-inc-mied-2005.