ADB Companies, Inc. v. Socket Telecom, LLC

CourtMissouri Court of Appeals
DecidedFebruary 9, 2021
DocketWD83575
StatusPublished

This text of ADB Companies, Inc. v. Socket Telecom, LLC (ADB Companies, Inc. v. Socket Telecom, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ADB Companies, Inc. v. Socket Telecom, LLC, (Mo. Ct. App. 2021).

Opinion

IN THE MISSOURI COURT OF APPEALS WESTERN DISTRICT ADB COMPANIES, INC., ) ) Respondent, ) ) v. ) WD83575 ) SOCKET TELECOM, LLC, ) Opinion filed: February 9, 2021 ) Appellant. )

APPEAL FROM THE CIRCUIT COURT OF BOONE COUNTY, MISSOURI THE HONORABLE KEVIN CRANE, JUDGE

Division Two: W. Douglas Thomson, Presiding Judge, Lisa White Hardwick, Judge and Edward R. Ardini, Jr., Judge

Socket Telecom, LLC (“Socket”) appeals the judgment entered by the Circuit Court of

Boone County, after a bench trial, in favor of Respondent ADB Companies, Inc. (“ADB”) on

ADB’s claim of breach of contract. The trial court found that Socket breached its contract with

ADB by improperly withholding funds owed to ADB and that, as a result, ADB was entitled to

attorney’s fees and prejudgment interest under section 431.180, RSMo.1 For the reasons stated

below, we reverse and remand with instructions to the trial court to enter judgment in favor of

Socket.

1 All statutory references are to the Revised Statutes of Missouri 2016. Factual and Procedural Background

Socket is an internet service provider. Socket obtained a “loan/grant” from the Rural Utility

Service (“RUS”), an agency within the United States Department of Agriculture, 2 to lay a fiber

optic network that would enable Socket to provide broadband internet service to homes and

businesses in Callaway County, Missouri. Socket did not “have its own crews that go out and lay

fiber,” so, using a structured process controlled by the RUS, it invited bids from subcontractors to

perform that work. ADB submitted a bid and was awarded the contract.

On July 13, 2012, ADB3 and Socket entered into a contract wherein ADB was to place

“approximately 101 miles of fiber in the Fulton exchange in central Missouri” (the “Contract”).

The Contract required ADB to complete its work within “150 calendar days excluding Saturdays,

Sundays, and legal holidays from the contract commencement date,” however ADB was entitled

to an extension of this deadline for delays caused by Socket’s failure to provide necessary

materials, easements, or rights-of-way if ADB timely requested an extension in writing. The

Contract contained two provisions governing this deadline-extension procedure. The first

provision was located in the section of the Contract titled “Instructions to Bidders”:

18. [Socket] represents:

a) If by other provisions of the contract documents [Socket] shall have undertaken to furnish any materials for the construction of the Project, such materials are on hand . . . or if such materials are not on hand they will be made available by [Socket] to [ADB] before the time such materials are required for construction. b) That all items to be accomplished by [Socket] to facilitate construction have been accomplished or will be completed prior to construction activity. c) . . .

2 The original mission of the RUS was to extend rural electrification; currently it provides funds to extend fiber optic networks for internet access in rural areas. 3 The parties to the contract were Socket and American Directional Boring, Inc. d/b/a ADB Utility Contractors. American Directional Boring, Inc. was the previous legal name for Respondent ADB.

2 d) Easements and rights-of-way for the Construction Corridor used for the placement of buried cable have been obtained from property owners or public authorities. . . . e) . . . f) . . . g) . . . If [Socket] shall fail to comply with any of the undertakings contained in the foregoing representations or if any of such representations shall be incorrect, [ADB] will be entitled to extension of time of completion for a period equal to the delay, if any, caused by the failure of [Socket] to comply with such undertaking or by any such incorrect representation; provided [ADB] shall have promptly notified [Socket], in writing within ten (10) days, of its desire to extend the time of completion in accordance with the foregoing, and provided further that such extension, if any, of the time of completion shall be the sole remedy of [ADB] for [Socket’s] failure, because of conditions beyond the control and without the fault of [Socket], to furnish materials in accordance with subparagraph (a) hereof.

The second provision governing the deadline-extension procedure was located in Article II,

Section 1 of the Contract, titled “Time and Manner of Construction”:

The time for Completion of Construction set forth in [ADB’s] Proposal shall be extended for the period of any reasonable delay which is due exclusively to causes beyond the control and without the fault of [ADB], including acts of God, fires, floods, inability to obtain materials, and acts or omissions of [Socket] with respect to matters for which [Socket] is solely responsible: Provided, however, that no such extension of time for completion shall be granted [ADB] unless within ten (10) days after the happening of any event relied upon by [ADB] for such an extension of time [ADB] shall have made a request therefore in writing to [Socket], and provided further, that no delay in such time of completion or in the progress of the work which results from any of the above causes except acts or omissions of [Socket] shall result in any liability on the part of [Socket].

(emphasis in original).

Article VI, Section 2 of the Contract, titled “Liquidated Damages,” detailed the effect of

ADB’s failure to meet its deadline:

The time of the Completion of the Construction of the Project is of the essence of this Contract. Should [ADB] neglect, refuse or fail to complete the construction within the time herein agreed upon, after giving effect to extensions of time, if any, herein provided, then in that event and in view of the difficulty of estimating with exactness damages caused by such delay, [Socket] shall have the right to deduct

3 from and retain out of such moneys which may be then due, or which become due and payable to [ADB] the sum of [$2,500.00] per day for each and every day that such construction is delayed in its completion beyond the specified time, as liquidated damages and not as a penalty; . . . Provided, however, that [Socket] shall promptly notify [ADB] in writing of the manner in which the amount retained, deducted, or claimed as liquidated damages was computed.

(emphasis in original). The “Completion of Construction” referred to in the liquidated damages

provision was contractually defined as “full performance by [ADB] of [its] obligations under the

Contract and all amendments and revisions thereof[.]” Pursuant to the Contract, “[t]he Certificate

of Completion, signed by the Engineer[4] and approved in writing by [Socket] and the

Administrator,[5] shall be the sole and conclusive evidence as to the date of Completion of

Construction[.]”

Finally, as relevant to this appeal, the Contract contained a provision governing what the

parties refer to as “retainage,” located in Article III, Section 1 of the Contract, titled “Payments to

Contractor”:

Within the first fifteen (15) days of each calendar month, [Socket] shall make partial payment to [ADB] for construction accomplished . . . . Only ninety-five percent (95%) of each such invoice approved during the construction of the project shall be paid by [Socket] to [ADB] prior to completion of the Contract. Upon completion by [ADB] of the construction of the Project, the Engineer will prepare a Final Inventory [and] . . . will certify it to [Socket], together with a certificate of the total cost of the construction performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. Carron
536 S.W.2d 30 (Supreme Court of Missouri, 1976)
Star Development Corporation v. Urgent Care Associates, Inc.
429 S.W.3d 487 (Missouri Court of Appeals, 2014)
Richard Brown v. Susan Brown-Thill
437 S.W.3d 344 (Missouri Court of Appeals, 2014)
Anthony Arcese v. Daniel Schmitt & Company
504 S.W.3d 772 (Missouri Court of Appeals, 2016)
HCI Investors, LLC v. Fox
412 S.W.3d 424 (Missouri Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
ADB Companies, Inc. v. Socket Telecom, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adb-companies-inc-v-socket-telecom-llc-moctapp-2021.