Adams v. Georgia Power Company

682 S.E.2d 650, 299 Ga. App. 399, 2009 Fulton County D. Rep. 2580, 2009 Ga. App. LEXIS 812
CourtCourt of Appeals of Georgia
DecidedJuly 10, 2009
DocketA09A0759
StatusPublished
Cited by5 cases

This text of 682 S.E.2d 650 (Adams v. Georgia Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. Georgia Power Company, 682 S.E.2d 650, 299 Ga. App. 399, 2009 Fulton County D. Rep. 2580, 2009 Ga. App. LEXIS 812 (Ga. Ct. App. 2009).

Opinion

Doyle, Judge.

In a trespass suit against Georgia Power Company (“GPC”), Ronald Adams appeals from the grant of GPC’s summary judgment motion, contending that the trial court erred in concluding that *400 Adams could not maintain his action for damages and declaratory and injunctive relief. For the reasons that follow, we affirm.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant. 1

So viewed, the record shows that in 1953, GPC executed a 25-year lease with Adams’s predecessor authorizing GPC to install, maintain, and operate a power line across what is now Adams’s property in exchange for $34.25 per year. The lease was recorded, but GPC has no records of having made sufficient payments under the lease nor of having renewed the lease after it expired in 1978. However, the evidence shows that GPC operated a power line on the poles from at least 1991 through 2002. In 1999, Adams bought the property, which contained the wooden utility poles originally installed by GPC. In 2006, GPC offered to pay Adams to “update” its purported easement over the property in connection with a planned upgrade of the existing power line to a higher voltage line. No agreement was reached, but as part of the power line upgrade, the existing line was moved to new steel poles not located on Adams’s property. The wooden poles remained, and the new line passed over Adams’s property. 2

In 2007, Adams filed the present suit seeking damages for trespass (including $100,000 in compensatory damages and $1 million in punitive damages), a declaratory judgment that GPC lacked rights to occupy or enter his property, and an injunction prohibiting GPC from entering or occupying his property in the future. GPC answered and, after engaging in discovery, moved for summary judgment on statute of limitation and other grounds. The trial court granted the motion, and this appeal followed.

1. Although Adams argues on appeal that the trial court erred in ruling that GPC had acquired aft easement by prescription, GPC’s motion for summary judgment was not based on this rationale, and it does not appear that the trial court granted GPC’s motion for summary judgment on this basis. The trial court cited Webster v. *401 Snapping Shoals Elec. Membership Corp., 3 which addressed a landowner’s right to pursue a trespass action against an electric membership corporation. In that case, this Court concluded that the action, which was brought more than four years after the plaintiff purchased the property, was time-barred by the four-year statute of limitation in OCGA § 9-3-30, 4 which provides that “[a]11 actions for trespass upon or damage to realty shall be brought within four years after the right of action accrues.” As in Webster, the record here shows that Adams purchased the property after the original utility poles were installed and power lines were operating, and the poles remained on his property until the day he brought suit. 5 Furthermore, the lease purporting to grant GPC rights to operate the power line was recorded. Therefore, because Adams had notice that GPC already had made its initial entry onto his property when he acquired the property, he was required to bring any action for trespass, to the extent one was cognizable, within four years of his 1999 purchase date. 6 “If at all, [Adams’s] right of action accrued at the time of purchase in [1999]. Since [his] suit was not filed until [2007], [Adams] is barred by the statute of limitation of OCGA § 9-3-30. ” 7 Accordingly, we discern no error in the trial court’s grant of summary judgment to GPC on this ground.

2. Adams also contends that the trial court erred in granting summary judgment as to his claim seeking declaratory relief settling his exclusive title to the property and enjoining GPC from interfering with his title by operating or maintaining the power line. However, even assuming that GPC, a public utility having the right of eminent domain, knowingly and without compensation took Adams’s property for the use of installing, operating, and maintaining the existing power line, “[t]he right to the owner, by whatever method the land is taken, is compensation, which right he may expressly or by inaction waive. He may by inaction waive his right to the land[,]” leaving as his sole remedy a timely action for damages. 8 As stated in Division 1, it is undisputed that prior to the time Adams bought the property in 1999, GPC had already made its initial entry onto the property by installing utility poles. Thus, Adams was on *402 notice of the intrusion in 1999, eight years prior to filing the suit. 9

Decided July 10, 2009 Reconsideration denied July 27, 2009 Walter D. Adams, for appellant. Whelchel & McQuigg, J. Thomas Whelchel, for appellee.
If a landowner stands by and permits, without legal objection, a public utility company to appropriate his land to its necessary corporate use until such becomes a necessary and constituent part of its service to the public, and the rights of the public intervene to such extent that to oust the company would interrupt the service and deny it to the public, the landowner, not for the protection so much of the company but for the benefit of the public, will be estopped from recovering the land in ejectment or from enjoining its use for the service, but will, if he moves in time, be remitted to an appropriate action for damages. 10

As stated in Division 1, to the extent Adams’s claim is cognizable as an action for trespass, it is time-barred by the four-year statute of limitation for trespass. To the extent the claim is cognizable as one for inverse condemnation, it is likewise time-barred by the four-year statute of limitation in OCGA § 9-3-30. 11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CITY OF ATLANTA v. LOLA CARLISLE
Court of Appeals of Georgia, 2021
Land USA, LLC v. Georgia Power Company
773 S.E.2d 236 (Supreme Court of Georgia, 2015)
Mortgage Alliance Corporation v. Pickens County
Court of Appeals of Georgia, 2012
Mortgage Alliance Corp. v. Pickens County
730 S.E.2d 471 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
682 S.E.2d 650, 299 Ga. App. 399, 2009 Fulton County D. Rep. 2580, 2009 Ga. App. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-georgia-power-company-gactapp-2009.