Adams v. A.B. & A., Inc.

613 A.2d 858, 1992 D.C. App. LEXIS 118, 1992 WL 89156
CourtDistrict of Columbia Court of Appeals
DecidedMay 1, 1992
Docket89-CV-272
StatusPublished
Cited by8 cases

This text of 613 A.2d 858 (Adams v. A.B. & A., Inc.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. A.B. & A., Inc., 613 A.2d 858, 1992 D.C. App. LEXIS 118, 1992 WL 89156 (D.C. 1992).

Opinion

FERREN, Associate Judge:

In this home improvement contract case, plaintiff-appellant (the homeowner) seeks review of: (1) a partial directed verdict in favor of defendant-appellees (the contractor and its owner), (2) the denial of appellant’s motion for an award of treble dam *859 ages and attorney’s fees, and (3) an order granting appellees’ motion for judgment n.o.v., by which the trial court overturned a jury verdict awarding appellant damages totalling $17,900. Emphasizing this last alleged error, appellant argues that the trial court erroneously rejected her claims under the Consumer Protection Procedures Act, D.C.Code § 28-3904(n) and (x) (1991). The trial court concluded, after verdict, that these claims had not been sufficiently identified in the pleadings. Appellant counters that they had been set forth in her pretrial statement and incorporated by reference in the pretrial order, that they were actually litigated, and thus that they were properly sent to the jury. Rejecting appellant’s contentions, we affirm.

I.

Appellees failed to complete installation of a heating and air conditioning system in appellant’s house, as they had contracted to do. Appellant sued on four counts 1 : (1) breach of contract; (2) failure to obtain a home improvement license; (3) negligence and gross negligence; and (4) fraud. The trial court directed a verdict on the breach of contract claim on the ground that appellant had failed to present evidence on the proper measure of damages. The trial court also directed a verdict for appellees on the claim of failure to obtain a home improvement license, because licensed air conditioning mechanics are specifically exempted from the regulation requiring home improvement licenses, see 16 DCMR 899.1 (1987), and appellant presented no evidence to demonstrate that appellees were not covered by the exemption. The trial court likewise directed a verdict on the fraud count because no evidence of fraud had been presented. Appellant herself dismissed the negligence count.

During extensive discussions in chambers after the judge had directed the verdicts against appellant, appellees argued that the case was at an end while appellant argued that she had claims remaining— although they had not been specifically pleaded — under the Consumer Protection Procedures Act, D.C.Code §§ 283901, et seq. (1991). Appellant asserted that her remaining claims had been implied or “incorporated” in the paragraphs of her claims for breach of contract and failure to obtain a license. Specifically, appellant argued that she had implicitly pleaded violations of D.C.Code § 28-3904(n) and (x). 2 The trial court decided that the interests of justice would best be served by allowing these allegedly “implied” claims to go to the jury. 3 See Corley v. BP Oil Corp., 402 A.2d 1258, 1263 (D.C.1979).

The jury returned a verdict in favor of appellant, awarding damages totalling $17,- *860 900. Appellant moved for an award of treble damages and attorneys’ fees. Ap-pellees moved for a judgment n.o.v., which the trial court granted.

II. Directed Verdict.

Appellant claims the trial court erred in directing the verdict in appellees’ favor on the breach of contract claim. Viewing the facts in the light most favorable to the non-moving party, e.g., Washington v. A & H Garcias Trash Hauling, 584 A.2d 544, 545 (D.C.1990), the trial court concluded that appellant had presented “no evidence whatsoever” on the reasonable cost of completing the contract — the appropriate measure of damages here. We agree.

Appellant contends that this case is controlled by Robinson v. Sarisky, 535 A.2d 901 (D.C.1988), in which we affirmed an award of compensatory and punitive damages in the case of a wrongful eviction. She argues that appellees’ abandonment of the job of installing a heating system in mid-winter rendered her home uninhabitable and amounted to constructive eviction and an intentional infliction of emotional distress. We conclude, however, as did the trial court, that such a claim was not pleaded and was not supported by the evidence. We perceive no error in the trial court’s decision to grant appellees’ directed verdict motion on the breach of contract claim.

III. Judgment n.o.v.

The trial court granted appellees’ motion for judgment n.o.v. on the ground that “[n]ot even by the most strained reading in [appellant’s] favor can it be said that her Amended Complaint implicates or refers to violations of the Consumer Act.” Appellant argues that her pretrial statement superceded the pleadings. See Howard v. Kerr Glass Mfg. Co., 699 F.2d 330, 333 (6th Cir.1983) (issues presented at pretrial conference and incorporated in pretrial order supercede the pleadings). Although appellant argues that her statutory claims based on the Consumer Protection Procedures Act are contained within her pretrial statement and, thus, are within the pretrial order, we have examined both documents, as well as the pleadings, and we share the trial court’s surprise. Appellant’s second pretrial statement referred to the Consumer Protection Procedures Act only twice: first, in her request for treble damages pursuant to D.C.Code § 28-3905(k)(l) and, second, in Paragraph 10, requesting that the court judicially notice numerous statutes and regulations, among which was “D.C.Code §§ 28-3900, et seq." [sic]. Appellant never made specific reference in the pleadings or in the pretrial statement to § 28-3904(n) and (x), the statutory provisions on which the jury’s verdict was allegedly based. This scattershot approach at pretrial, where only one provision of a statute is specified and the rest of the statute in general is mentioned, without any focus on what the pleader expects the opponent to defend under the balance of the statute, will simply not do. A defendant is entitled to more notice than that.

“ ‘The purpose of the pretrial conference is to define the claims and defenses of the parties in order to narrow the issues, eliminate unnecessary proof and lessen the opportunity for surprise thereby expediting the trial.’ ” Daniels v. Beeks, 532 A.2d 125, 128 (D.C.1987) (emphasis added) (quoting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hobley v. Law Office of S. Howard Woodson, III
983 A.2d 1000 (District of Columbia Court of Appeals, 2009)
Malik Corp. v. Tenacity Group, LLC
961 A.2d 1057 (District of Columbia Court of Appeals, 2008)
Norried v. Caribbean Contractors, Inc.
899 A.2d 129 (District of Columbia Court of Appeals, 2006)
District of Columbia v. Shannon
696 A.2d 1359 (District of Columbia Court of Appeals, 1997)
Habtu v. Woldemichael
694 A.2d 846 (District of Columbia Court of Appeals, 1997)
Vector Realty Group, Inc. v. 711 Fourteenth Street, Inc.
659 A.2d 230 (District of Columbia Court of Appeals, 1994)
Bauldock v. Davco Food, Inc.
622 A.2d 28 (District of Columbia Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
613 A.2d 858, 1992 D.C. App. LEXIS 118, 1992 WL 89156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-ab-a-inc-dc-1992.