Adams and Associates, Inc. v. United States

120 Fed. Cl. 250, 2015 WL 525533
CourtUnited States Court of Federal Claims
DecidedFebruary 10, 2015
Docket14-1168C
StatusPublished
Cited by1 cases

This text of 120 Fed. Cl. 250 (Adams and Associates, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams and Associates, Inc. v. United States, 120 Fed. Cl. 250, 2015 WL 525533 (uscfc 2015).

Opinion

Bid protest; Job Corps Centers; Small Business Set-Asides; Statutory Construction; Workforce Investment Act

OPINION

BRUGGINK, Judge.

This bid protest, brought by Adams and Associates, Inc., (“Adams” or “plaintiff’), once again challenges the solicitation by the Department of Labor (“DOL”) for operation of the Shriver Job Corps Center (“Shriver”) in Massachusetts. The agency began the solicitation process in 2012 at a time when Adams was the incumbent on a contract set to expire in 2013. Adams previously protests ed this procurement in 2012. The basis of *251 that challenge, and the current one, is that DOL improperly set aside the procurement for small businesses, making Adams, a large business, ineligible to compete. The first protest was unsuccessful. We held that the agency had properly conducted a “rule of two” analysis and that the set-aside did not violate the Workforce Investment Act, Pub.L. No. 105 220, 112 Stat. 936 (1998) (“WIA”) (amending various sections codified throughout Title 29). Adams & Assocs., Inc. v. United States, 109 Fed.Cl. 340 (2013). That decision was affirmed on appeal. 741 F.3d 102 (Fed. Cir.2014). Adams’ effort to obtain rehearing en banc was also unsuccessful. Adams & Assocs., Inc. v. United States, Nos. 13-5077 & 13-5080 (Fed.Cir. Mar. 14, 2014) (order denying rehearing en banc).

When DOL, having weathered Adams’ challenge, began moving ahead with the procurement as a small business set-aside, Adams filed a protest in April 2014 with the Government Accountability Office (“GAO”). The thrust of the challenge was that, in the interim, Congress had taken certain legislative measures which directly impacted the procurement. The GAO rejected that challenge, in part because it viewed the new allegations as subject to res judicata; and because the allegations were or could have been brought before the Federal Circuit. Adams & Assoc., Inc., B-409680 et al., 2014 WL 1614214 (Comp.Gen. Apr. 22, 2014). Adams sought reconsideration, which was denied in November of 2014. Adams & Assoc., Inc., B-409680.2 et al. (Comp.Gen. Nov. 12, 2014).

On December 4, 2014, Adams filed the present suit, attempting to block DOL from moving forward with the procurement in the face of congressional instructions, issued subsequent to our prior decision, to consider award to “high-preforming incumbent contractors” such as Adams. Essential to Adams’ present complaint is its assumption that the agency’s delay in moving ahead with the procurement in 2013 or 2014, particularly in light of legislation affecting the Job Corps program, amounted to a de facto new procurement decision. We disagree.

Pending are plaintiffs motion for judgment on the administrative record, defendant’s cross-motion for judgment on the administrative record, or in the alternative, motion to dismiss for lack of jurisdiction, and defendant’s motion to strike the extra-record material offered by plaintiff. The motions are fully briefed, and we heard oral argument on February 5, 2015. 1 For the reasons explained below, we grant defendant’s motion to strike and its motion to dismiss. We deny plaintiffs cross-motion.

BACKGROUND

Given the extensive writing by three fora on the factual background of this procurement, we limit ourselves to the essentials and what plaintiff contends are developments after our first decision.

On December 14, 2012, DOL issued solicitation DOL12QA20003 for the operation of the Shriver center as a small business set-aside. AR at 3. By designating the contract for competition solely among small businesses, Adams, which is a large business, was excluded from competing. See 741 F.3d at 105; 109 Fed.Cl. at 346. The DOL solicitation and set-aside decision were upheld by this court, the Federal Circuit, and GAO. Adams is the incumbent operator for Shriver under contract DOLJ08QA00002, which originally ran from June 1, 2008 to May 31, 2013, but because of these protests, has been extended through bridge contracts until May 31, 2015.

On January 17, 2014, while the appeal to the Federal Circuit from our'first decision was pending, Congress passed the Consolidated Appropriations Act of 2014 (“the Act”), the purpose of which is to fund various governmental programs. Pub.L. No. 113-76, 128 Stat. 5. The Act provides the following: “[t]o carry out subtitle C of title I of the WIA ... $1,688,155,000, plus reimbursements, as follows: (1) $1,578,008,000 for Job Corps Operations, which shall be available for the *252 period July 1, 2014 through June 30, 2015.” 128 Stat. 349-50. It is undisputed that the appropriation involves funds that will be used to perform the contract in question. I.e., the legislation squarely affects this contract.

Section 4 of the Act provides as follows:

The explanatory statement regarding this Act, printed in the House of Representatives section of the Congressional Record on or about January 15, 2014 by the Chairman of the Committee on Appropriations of the House, shall have the same effect with respect to the allocation of funds and implementation of divisions A through L of this Act as if it were a joint explanatory statement of a committee of conference.

128 Stat. 7. The Joint Explanatory Statement (“JES”) referred to provides in relevant part that,

When evaluating contract renewals or rebids, due consideration should be provided to the federal investment already made in high-performing incumbent contractors as a part of a full, fair, and open competitive process. As part of this process, the Department of Labor (DOL) should consider documented past performances of student outcomes and cost-effective administration as important factors in Job Corps procurements.

160 Cong. Rec. H475 (daily ed. Jan. 15, 2014).

On the same day that the Act became law, DOL placed a special notice on a public website, FedBizOpps, whereby DOL released its “plan for all upcoming procurements for Job Crops center operations, Outreach and Admissions, and Career Transition Services ... in order to give contractors the opportunity to review the plan” and provide feedback. AR at 627 (emphasis supplied). DOL expressed an interest in input from potential bidders regarding the maximum and optimal number of proposals that contractors could prepare and submit. DOL emphasized that it sought “generalized feedback” and that it was “not seeking, nor will it entertain contractor input regarding the release date, closing date or award date of specific procurements.” AR at 628. Attached was a list of upcoming procurements with projected dates for requests for proposals (“RFP”). Because the RFP for Shriver already had been released, that facility was not included on the list. AR at 630.

After receiving feedback, DOL released a revised procurement plan on March 27, 2014, which included estimated dates by which DOL intended to release RFPs and then to make awards with respect to upcoming procurements. AR at 632.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McConnell Jones Lanier & Murphy, LLP v. United States
128 Fed. Cl. 218 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
120 Fed. Cl. 250, 2015 WL 525533, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-and-associates-inc-v-united-states-uscfc-2015.