Adamant Plaster Manufacturing Co. v. National Bank of Commerce

31 P. 634, 5 Wash. 232, 1892 Wash. LEXIS 42
CourtWashington Supreme Court
DecidedNovember 23, 1892
DocketNo. 551
StatusPublished
Cited by3 cases

This text of 31 P. 634 (Adamant Plaster Manufacturing Co. v. National Bank of Commerce) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adamant Plaster Manufacturing Co. v. National Bank of Commerce, 31 P. 634, 5 Wash. 232, 1892 Wash. LEXIS 42 (Wash. 1892).

Opinion

[233]*233The opinion of the court was delivered by

Hoyt, J.

Plaintiff and defendant entered into a contract in writing, which was substantially as follows:

“This memorandum of agreement, made this thirteenth day of August, 1890, witnesseth: That we, the undersigned, agree to and with the National Bank of Commerce, a corporation of the city of Tacoma, Washington, to plaster with adamant plaster their new building situated on the northeast corner of Pacific avenue and Thirteenth street, in the city of Tacoma, Wash., for the sum of thirty-five cents per yard of actual wall plaster, leaving out all openings, such as doors, windows, wainscoting, etc. The brick walls will receive two coats of adamant plaster and will be made straight and plumb. All the inside partitions will receive one coat of adamant plaster. All the plastering must be plumb, straight and all angles must be cut. All the plastering must be brushed and floated to the entire satisfaction of the architect. The ceiling of the banking room must be run at one time so as to avoid joints and be of a uniform color. All the banking room will be furred and lathed, and all of the plastering must be of extra fine finish so as to receive the decoration which is to be painted on said walls.
“We are to furnish all labor and materials and scaffolding for the above mentioned work, and we bind ourselves to have all the plastering completed in thirty days’ labor or thirty working days. We are to be responsible for all losses and accidents until the plastering is all completed and received by the architect. All the payments during the progress of the work will be made on certificate of the architect, which will not exceed 66 per cent, of the amount of the work done at the time said certificate is given; the remainder of the amount will be paid when the work is completed and accepted by the architect. All the adamant plaster must be composed of the best and pure materials, the sand must be clean, sharp sand, and must be free from sodium and nitrate of soda; such sand as obtained from the bay or sand that has been washed by salt water will not be used. All the work must be first class and to the entire [234]*234satisfaction of the bank directors and the architect. We agree to commence plastering as soon as the building will be ready for us, and we bind ourselves to complete the building in thirty working days. ’ ’

The plaintiff alleges that during the progress of the work under said contract, the defendant refused to allow it to proceed as it claimed the right to do, and that thereupon a supplemental contract was entered into between them in which it was agreed that the defendant should compensate the plaintiff for the increased cost of the work as required to be performed by the defendant over the cost of the work as contemplated by the contract as understood by the plaintiff. Upon the trial of the issues framed in regard to such extra compensation, plaintiff introduced proof tending to establish the making of such supplemental contract, while the defendant introduced proof which substantially contradicted that of the plaintiff. The direct proof upon this question on the part of the plaintiff was almost entirely made up of the testimony of one Holbrooke, its manager, and on the part of the defendant by the testimony of one Weatheri’ed, its vice px’esident. Upon this conflicting testimony the lower court fouxxd the issue in favor of the defendant. If this finding of the coxxrt was correct, its judgment must be affirmed.

It, thei’efore, becomes necessary for us to examine all of the proof offered by the respective parties, and by the aid thereof interpret the direct testimoxxy as to this issue. As a genei'al rule this court, even in an equity case, will not disturb a finding of fact made by the lower court unless it seems clear that it has made a mistake in regard thereto. If, however, oxx an investigation of the case hex’e it appears that the court below made a mistake in the law of the case as bearing upon the introduction of proofs, and that such mistake of law has in any manner contributed to its finding of the facts, such general rule will no longer have force, [235]*235and this court will enter upon an investigation of the facts upon all the proofs in the record as though it were a new question first presented here. This makes it necessary for us to examine certain legal questions presented to the court relating to the construction of the written contract above set forth. The plaintiff claimed, and offered to prove, that at the time of the execution of the said written contract there was an understanding and an agreement that the irregularities in the brick wall should be so far filled up and made plumb and straight with common lime mortar, that the application of the two coats of adamant for which the contract provided would make said walls straight' and plumb. If it were competent for the plaintiff to show this oral agreement, and it would have force as a part of the written contract, then the plaintiff was entitled to have proceeded to the completion of the work thereunder in the manner in which it was doing the same when interfered with by the defendant, and this fact would tend very strongly to establish the contention of the plaintiff that a supplemental contract had been entered into by which it was to receive additional compensation if it filled such irregularities in the brick wall entirely with adamant, as it is conceded that the substitution of adamant for lime mortar for such filling largely increased the total expense of the work. In fact, if the original contract was qualified by the oral agreement entered into at the time it was executed as contended for by the plaintiff, it is so unreasonable to suppose that the plaintiff would have voluntarily made such filling entirely with adamant instead of partly with common lime mortar without some agreement on the part of defendant for additional compensation, that this court would feel bound to find with the plaintiff as to said alleged supplemental contract.

The whole question, then, must, in our opinion, turn upon the construction of the written contract above set [236]*236forth, and as to whether or not under the conditions thereof it was competent for the plaintiff to prove the alleged oral agreement in explanation of its terms, and have such oral agreement given force as explanatory, and in aid of said written contract. The particular clause of such contract which it is necessary for us to interpret in coming to a decision as to these questions is this: “The brick walls will receive two coats of adamant plaster, and will be' made straight and plumb.” It is contended upon the part of the plaintiff that the language of this clause is ambiguous and uncertain, and that for that reason it is competent for it to-introduce proofs to show the full understanding of the parties at the time of the execution of said contract. On the other hand, it is contended upon the part of the defendant that said clause is certain, and that all agreements and understandings between the parties before and at the time of the execution of the contract had been merged therein, and that no oral proof in regard thereto could be introduced.

To properly determine this question the court must, so far as possible, put itself in the situation of the parties and come to as full an understanding of the subject matter of the contract as the parties must be supposed to have had at the time they entered into said contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. State
452 S.W.2d 317 (Supreme Court of Arkansas, 1970)
State v. Hall
383 P.2d 602 (Idaho Supreme Court, 1963)
Peyser v. Western Dry Goods Co.
102 P. 750 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
31 P. 634, 5 Wash. 232, 1892 Wash. LEXIS 42, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adamant-plaster-manufacturing-co-v-national-bank-of-commerce-wash-1892.