A.D.A.M. Land Development Corp. v. Conservation Commission

572 A.2d 364, 21 Conn. App. 122, 1990 Conn. App. LEXIS 86
CourtConnecticut Appellate Court
DecidedMarch 27, 1990
Docket7827
StatusPublished
Cited by14 cases

This text of 572 A.2d 364 (A.D.A.M. Land Development Corp. v. Conservation Commission) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.D.A.M. Land Development Corp. v. Conservation Commission, 572 A.2d 364, 21 Conn. App. 122, 1990 Conn. App. LEXIS 86 (Colo. Ct. App. 1990).

Opinion

Foti, J.

This appeal concerns the denial by the defendant Chester Conservation Commission (commission)1 of the plaintiffs application to construct a proposed roadway that would cross an inland wetland at two separate locations (hereafter referred to as the western crossing and the eastern crossing), and the plaintiff’s subsequent appeal to the Superior Court from that denial. The commission claims error in that portion of the Superior Court’s judgment that overruled its denial of the plaintiff’s application for the western crossing. The plaintiff has cross appealed from that portion of the judgment that upheld the commission’s denial of its application for the eastern crossing.

The commission claims that the trial court erred (1) in substituting its judgment for that of the defendant, [124]*124(2) in failing to remand the matter for further proceedings, and (3) in concluding as it did on the evidence before it. The plaintiff, in its cross appeal, alleges that the trial court erred (1) in determining that General Statutes § 22a-41 (b) applies to municipal inland wetlands agencies, and (2) in determining that General Statutes § 22a-41 (b) was legally applicable to the plaintiffs application. We find error in the trial court’s failure to remand.

On March 1, 1987, the plaintiff filed an application with the commission to construct a roadway that would cross an inland wetland at two separate locations some distance apart. The plaintiff asserts that this roadway would provide the only access to ten residential building lots on a piece of property containing approximately thirty-seven acres.

On July 1,1987, while the plaintiff’s application was pending, Public Acts 1987, No. 87-533, came into effect, making changes to the Wetlands and Watercourses Act including the addition of subsection (b) to General Statutes § 22a-41.2 The commission, acting as an inland wetlands agency, held a public hearing on July 6,1987. In its decision dated September 8,1987, following the guidelines of § 22a-41 (b), the commission held that it was unable to find that feasible and prudent alternatives to the proposed roadway did not exist.

The trial court dismissed the plaintiff’s appeal of the commission’s decision. Thereafter, however, the same court granted the plaintiff’s motion to open or set aside [125]*125the judgment, and sustained the plaintiffs appeal as to the western crossing, but maintained its dismissal of the appeal as to the eastern crossing.

I

The Defendant’s Appeal

A

The commission first claims that the court erred in substituting its judgment for that of the commission. The commission asserts that the court usurped its function in finding that it had acted illegally, arbitrarily or so unreasonably as to have abused its discretion in not having divided the application itself.

The record indicates that the commission and the soil conservation service made site inspections. After these inspections, the public hearing on the plaintiff’s application was held open for three weeks to allow written comments to be submitted by the commission’s engineers, Christman Associates, Inc, On August 5,1987, the plaintiff agreed to an extension of the commission’s thirty day deadline. On September 8,1987, Christman submitted a report based on a review of the applicant’s plans. The report briefly described four alternative routes over the eastern portion of the land with varying degrees of impact on the inland wetlands that were located within the subdivision. The route proposed by the plaintiff in his application was listed as the first alternative. The report indicated, however, that the fourth alternative would be the preferred route for the eastern crossing if the primary objective was to conserve inland wetlands.

The plaintiff’s application clearly sought two inland wetland crossings, however. It was not until the court reviewed the entire record a second time that it determined that the commission had considered only the alternate routes to the eastern crossing, and that the [126]*126western crossing had received no separate consideration in spite of the apparent approval of this crossing by the commission’s own engineer.3

Clearly, the application was never severed by the trial court as claimed by the commission. Rather, the court correctly found that the plaintiff sought permission for a single road that would make two separate crossings across an inland wetland. It further recognized that the commission’s own engineer had come to different conclusions as to each of the proposed crossings and, consequently, that the engineer’s report was, “in fact, evidence that no other prudent and feasible alternative existed with regard to this second or westerly most crossing of the wetlands.” The court finally determined that there are, in fact, two separate crossings, that the commission should have made a separate decision as to each of the wetland crossings and that, because the commission did not do so, its action was illegal.

It is our conclusion that the trial court properly based its holding on the record before it, and that, because the commission had never considered the feasibility of the western crossing, the court did not err when it sustained the plaintiff’s appeal as to the western wetland crossing.

B

The commission next claims that the trial court erred when it failed to remand the matter to the commission for further proceedings. We agree. After finding that the commission had failed to consider the western crossing, the trial court should have remanded the mat[127]*127ter to the commission with direction to consider and decide that wetland crossing separately, or, in other words, to remand for the commission to take action consistent with the trial court’s decision.

It is the function of the commission, first, to find facts as to whether evidence of the unavailability of possible and prudent alternatives was sufficiently persuasive to satisfy General Statutes § 22a-41 (b), second, in light of the criteria enumerated under § 22a-41 (a), to decide whether to grant or deny the application for the western wetland crossing, and, if granted, to determine whether that permit should contain special terms, conditions, limitations or modifications of the regulated activity, as provided for in § 22a-42a (d).

C

The commission’s final claim of error is that the trial court exceeded its authority by substituting its judgment for that of the commission. Specifically, the commission claims that the court erred when it concluded that the evidence supported a finding that no prudent and feasible alternative existed with respect to the western crossing. We cannot agree. The trial court’s decision does not “find as a fact” that no feasible and prudent alternative existed. Rather, the court merely concluded that the commission failed to consider separately specific evidence, i.e., its own engineer’s report as to the western wetland crossing, and, consequently, that it failed to decide separately that it could not find, on the basis of § 22a-41 (b), “that feasible and prudent alternatives do not exist” to that crossing before it denied the application.

The trial court properly discharged its duty to both parties by its review of the actions of the commission with respect to each crossing requested in the plaintiff’s application.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Anthony E., (Feb. 25, 1997)
1997 Conn. Super. Ct. 696 (Connecticut Superior Court, 1997)
Paige v. Planning Zoning Commission, No. 289197 (Nov. 25, 1996)
1996 Conn. Super. Ct. 9552 (Connecticut Superior Court, 1996)
Forsell v. Conservation Commission
682 A.2d 595 (Connecticut Appellate Court, 1996)
Ellenthal v. Inland wetland/watercourses, No. Cv93 0129782 S (Apr. 19, 1994)
1994 Conn. Super. Ct. 4672 (Connecticut Superior Court, 1994)
Grover v. Inland Wetlands Agency, Derby, No. Cv92-0041433s (Dec. 1, 1993)
1993 Conn. Super. Ct. 10395 (Connecticut Superior Court, 1993)
McNally v. Zoning Commission
621 A.2d 279 (Supreme Court of Connecticut, 1993)
Klug v. Inland Wetlands Commission
619 A.2d 8 (Connecticut Appellate Court, 1993)
Timber Trails v. Plan. Z. Comm'n, Sherman, No. 27 21 70 (Sep. 16, 1992)
1992 Conn. Super. Ct. 8675 (Connecticut Superior Court, 1992)
Milardo v. Inland Wetlands Commission
605 A.2d 869 (Connecticut Appellate Court, 1992)
Foster Farms v. Malborough Conserv., No. Cv90 0381699 (Mar. 9, 1992)
1992 Conn. Super. Ct. 2157 (Connecticut Superior Court, 1992)
Vom Saal v. Zoning Comm'n of Stratford, No. Cv91 27 90 21 (Dec. 30, 1991)
1991 Conn. Super. Ct. 10861 (Connecticut Superior Court, 1991)
McNally v. Norwalk Zoning Commission, No. Cv90-0111615 (Aug. 21, 1991)
1991 Conn. Super. Ct. 6801 (Connecticut Superior Court, 1991)
Fromer v. Reynolds Metals Development Corp., No. 51 41 51 (Jul. 15, 1991)
1991 Conn. Super. Ct. 5758 (Connecticut Superior Court, 1991)
Klug v. Torrington Inland-Wetlands, No. Cv88 004 78 17 (Sep. 5, 1990)
1990 Conn. Super. Ct. 2035 (Connecticut Superior Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
572 A.2d 364, 21 Conn. App. 122, 1990 Conn. App. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adam-land-development-corp-v-conservation-commission-connappct-1990.