Adam Associates International, Inc. v. William A. Berry & Son, Inc.

22 Mass. L. Rptr. 389
CourtMassachusetts Superior Court
DecidedMay 2, 2007
DocketNo. 050997BLS2
StatusPublished
Cited by2 cases

This text of 22 Mass. L. Rptr. 389 (Adam Associates International, Inc. v. William A. Berry & Son, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adam Associates International, Inc. v. William A. Berry & Son, Inc., 22 Mass. L. Rptr. 389 (Mass. Ct. App. 2007).

Opinion

Gants, Ralph D., J.

On March 12, 1997, the plaintiff Adam & Associates International, Inc. (“Adam”) entered into a letter Agreement with the defendant William A. Berry & Son, Inc. (“Berry”) concerning engineering, procurement, and advisoiy services that Berry agreed to perform with respect to a burn unit facility (“the Facility”) that was being created at the Sonatrach Medical Center in Algiers, Algeria. A joint venture, Brown & Root/Condor (“B&R/C”) had entered into an agreement with the Algerian entity building this Facility, Entreprise Nationale Sonatrach (“Sonatrach”), to manage the construction of the Facility and take responsibility for the selection, procurement, delivery, and installation of the medical equipment needed for the bum unit. B&R/C had subcontracted with Adam to design and equip the bum unit at the Facility, and Adam, in turn, had subcontracted with Beriy through the March 12, 1997 Agreement to provide the building systems, components, and materials needed for the Facility, along with various services. In paragraph 12 of this Agreement, Berty agreed that it would not undertake for Sonatrach, Brown & Root, or B&R/C “any engineering, procurement or construction contract for a health care facility in Algeria except through Adam.” Agreement at 8.

Paragraph 11 of the Agreement included the following arbitration provision:

If the parties are unable to resolve any dispute arising hereunder, whether sounding in contract, statute, tort or other legal theory, the dispute shall be resolved by arbitration in Boston, Massachusetts pursuant to the then-current rules of the American Arbitration Association (“the AAA”). If the matters in dispute involve claims aggregating Five Hundred Thousand Dollars ($500,000) or less, the arbitration shall be conducted by a single arbitrator engaged in the practice of law, who is knowledgeable about the subject matter of the dispute, but if the claims aggregate more than that amount, the arbitration shall be conducted by a panel of three (3) neutral arbitrators, one a certified public accountant who is a partner in a so-called “Big Six” accounting firm with an office in Boston, Massachusetts, one a mechanical engineer and the third an architect experienced in hospital design. The arbitrator(s) shall be selected in accordance with the AAA procedures from a list of qualified persons maintained by the AAA. The arbitrator(s) shall only have authority to award compensatory damages, and shall not have authority to award punitive damages, other non-compensatory damages or any other form of relief, the parties hereby waiving all rights to and claims for relief other than compensatory damages. Adam agrees that the maximum amount of compensatory damages for which Berry shall be liable hereunder shall be Two Hundred Fifty Thousand Dollars ($250,000). Each party shall bear its own costs and attorneys fees and the parties shall share equally the fees and expenses of the arbitrator(s). The decision and award of the arbitrator(s) shall be final and binding, and judgment upon the award may be entered in any court having jurisdiction thereof.

Agreement at 7-8.

[390]*390In the Complaint filed in this action, Adam alleged that Berry had violated paragraph 12 of the Agreement by contracting with B&R/C in June 2000 to design two military hospitals in Algeria, and in October 2001 to provide mechanical, electrical, and plumbing equipment and materials for these two hospitals. Berry moved to stay this action and to compel arbitration. On June 20, 2005, Judge Nonnie Burnes of this Court allowed the motion and ordered that the case be stayed pending arbitration. On June 21, 2005, Judge Burnes denied Adam’s emergency motion to file a supplemental brief to address issues not raised at the oral argument of the motion, noting that “[t]he issue of any limitation of damages may be dealt with later, if necessary.”

Adams then made a Demand for Arbitration. It claimed more than $500,000 in damages, so a panel of three arbitrators was selected in accordance with the Agreement. After hearing evidence over eleven days, the arbitration panel issued its Arbitration Award on February 5, 2007. The arbitrators found that Berry had violated what the arbitrators characterized as the covenant not to compete in paragraph 12 of the Agreement. In determining the amount of damages, the arbitrators examined the provision in the arbitration clause of the Agreement that appeared to limit Berry’s liability to Adam to $250,000 in compensatory damages. The arbitrators declared:

The parties’ agreement was ambiguous on its face in presenting both a $250,000 cap of some kind together with a $500,000 claim threshold for an enlarged and specialized panel of arbitrators. A $250,000 cap applicable to all breaches would have made the $500,000 threshold superfluous.

Arbitration Award at 16-17. Having found the arbitration provision ambiguous as to the limitation of liability, the arbitrators permitted parol evidence regarding the drafting of the Agreement and the intent of the parties. The arbitrators construed “the $250,000 cap limitation of the [Agreement] as a limitation on warranty recoveiy and not limiting the type or amount of damages awardable by any appropriate tribunal and not limiting the scope of arbitral jurisdiction in connection with contract breaches other than warranty breaches.” Id. at 17. In essence, the arbitrators found that the cap limited Berry’s liability only for breach of warranty, and did not limit its liability for any breach of the non-compete provision in paragraph 12. The arbitrators then awarded Adams $1,154,885 in what it characterized as “disgorgement damages” arising from Berry’s breach of the non-compete provision, finding that “Adam does deserve a remedy proportionate to a realistically appraised loss” and that the amount of damages awarded was “a fair appraisal of an appropriate substitute for the injunction effect Adam could have obtained if Berry honored the covenant.” Id.

The arbitrators found, “The circumstances do not warrant a disgorgement of Berry’s profits on its entire $US-110 million of construction services revenue, but only as to profits earned on these projects stated in (or before) the three year period after December 31, 1998.” Id. at 16. The arbitrators had earlier found that they would limit the duration of the covenant not to compete to “three years from the beginning of 1999,” id. at 15, which this Court understands to mean that the covenant would not apply to any competition by Beny on or after January 1, 2002. Therefore, the “disgorgement damages” appear to reflect the amount of Berry’s profits on its construction services revenue from B&R/C arising from the construction of the two Algerian military hospitals for the period from January 1, 1999 through December 31, 2002.

Berry now moves to vacate or modify the Arbitration Award, claiming that the arbitrators exceeded the scope of their authority (1) by awarding damages that were not “compensatory damages” and (2) by awarding damages in excess of the $250,000 limitation on Berry’s liability. Adam has cross-moved to confirm the Arbitration Award. After hearing, this Court DENIES Berry’s motion to vacate or modify the Arbitration Award, and ALLOWS Adam’s motion to confirm the arbitration award.

DISCUSSION

It is a well-established principle of law that “judicial review of arbitration awards is confined to certain narrow grounds.” City of Lawrence v. Falzarano, 380 Mass. 18, 28 (1980). The Uniform Arbitration Act, codified in Massachusetts at G.L.c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abdelnour v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
29 Mass. L. Rptr. 540 (Massachusetts Superior Court, 2012)
Essex County Sheriff's Department v. Essex County Correctional Officers Ass'n
27 Mass. L. Rptr. 487 (Massachusetts Superior Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
22 Mass. L. Rptr. 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adam-associates-international-inc-v-william-a-berry-son-inc-masssuperct-2007.