ADA-ES, Inc. v. Big Rivers Electric Corporation

District Court, W.D. Kentucky·Decided June 9, 2020·No. 4:18-cv-00016·Unknown

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF KENTUCKY OWENSBORO DIVISION CIVIL ACTION NO: 4:18-CV-00016-JHM ADA-ES, INC. PLAINTIFF V. BIG RIVERS ELECTRIC CORPORATION DEFENDANT MEMORANDUM OPINION AND ORDER This matter is before the Court on Defendant’s Motion for Partial Summary Judgment [DN 124]. Fully briefed, this matter is ripe for decision. For the following reasons, Defendant’s Motion for Partial Summary Judgment is GRANTED in part and DENIED in part. I. BACKGROUND According to the Complaint, Plaintiff ADA-ES, Inc. (“ADA”) contracted with Big Rivers Electric Corporation (“Big Rivers”) for the engineering, manufacturing, and delivery of equipment and materials for a Dry Sorbent Injection System (“DSI System”). [DN 20 ¶ 7]. Pursuant to a requirement of the Request for Quotes (“RFQ”), ADA posted an irrevocable standby letter of credit in the amount of $807,651.00 through CoBiz Bank (“Bank”) in Denver, Colorado, to serve as security for performance under the contract. [Id. ¶ 11]. Importantly, the letter of credit, by its express terms, was governed by Colorado law. [Id. ¶ 5]. In accordance with the contract, ADA engineered, manufactured, and delivered a DSI System, which was incorporated into a power plant owned by Big Rivers. [Id. ¶ 13]. The purpose of the system was to inject a powdered sorbent into the power plant system where exhaust gas is produced to bind with, capture, and sequester the pollutant, Sulfur Trioxide gas (“SO3”), created from the burning of fuel. [Id.]. In other words, the DSI System was to be used to reduce SO3 emissions to a specific level. [Id.]. According to contract documents—the RFQ, the contract, and the purchase order— “Performance Guarantee Test Procedures” were to be mutually agreed upon and provided by ADA 75 days after notice to proceed was granted by Big Rivers. [Id. ¶¶ 14–15]. These procedures were

to provide guidelines for Big Rivers’ testing of the DSI System after delivery and installation. On or about January 8, 2016, ADA provided Big Rivers with the DSI Performance Test Procedure. [DN 20-7]. Those guidelines were incorporated into the final protocol for the test program, named CleanAir Protocol. [DN 20-8, DN 20-9, DN 20-10]. In March 2016, after the DSI System was installed and the performance test guidelines were finalized, Big Rivers conducted its first performance test on the DSI System. [DN 20 ¶ 19]. Big Rivers claimed the system failed the test by failing to reduce the amount of SO3 emissions to less than five parts per million (ppm)—the contractually agreed upon reduction—when a specified amount of sorbent was consumed under specified conditions. [Id. ¶ 20]. Thereafter, Big Rivers

notified ADA of the failed test. ADA responded that “it disagreed with Big Rivers’ conclusions about the test, and informed Big Rivers that the way to cure the alleged problem was to use the High Reactivity Hydrated Lime as called for in the Test Procedures and the CleanAir Protocol.” [Id. ¶ 22]. Big Rivers conducted a second test in June 2016 using a sorbent it claimed satisfied the contract’s requirement and informed ADA that the system again failed the performance test. [Id. ¶ 23]. Based on the failed performance tests, Big Rivers issued a claim for damages in the amount of $605,458.78, “which constituted its quantification of damages and asserted a right to both actual and liquidated damages for the same alleged performance breach.” [Id. ¶ 24]. Big Rivers thereafter withheld $563,382.56 of contract payments. Additionally, Big Rivers withdrew the entire $807,651.00 letter of credit funds, using the same basis it used to justify the withheld contract payments. [Id. ¶ 27]. On May 11, 2017, ADA filed an Amended Complaint alleging Fraud (Count I), Unjust Enrichment (Count II), Breach of U.C.C. Warranties (Count IV), Breach of Contract (Count V),

and seeking Declaratory Judgment as to seven claims (Count III). [DN 20 ¶¶ 35–77]. On December 6, 2019, ADA moved for leave to amend its complaint and attached its proposed amended complaint. [DN 118; DN 118-9]. Big Rivers, in response, filed a Motion for Partial Summary Judgment on ADA’s claims for fraud and breach of U.C.C. warranties—two claims related to the letter of credit asserted in the operative complaint. [DN 124]. Therein, Big Rivers explained that its opposition to ADA’s Motion for Leave to Amend required it to brief the legal and factual issues related to the draw on the letter of credit. [Id. ¶ 7]. That being the case, Big Rivers stated “[t]hat discussion of letter of credit law [would] necessarily show that ADA’s fraud and breach of U.C.C. warranties claims fail as a matter of law.” [Id. ¶ 9]. Accordingly, Big Rivers sought, and was granted, the right to file a combined memorandum in opposition to ADA’s Motion to

Amend as well as in support of its independent Motion for Partial Summary Judgment on ADA’s pending letter of credit claims. [DN 156; DN 124; DN 125]. Although the Court permitted Big Rivers’ arguments regarding the Motion to Amend and Motion for Partial Summary Judgment to be filed together in a single memorandum, the Court addresses these two motions independently as they require the application of different standards of review. Turning to the instant motion, Big Rivers argues that it is entitled to summary judgment on two of ADA’s existing claims. [DN 124; DN 125]. Big Rivers’ primary basis for its motion is the contention that its draw on the letter of credit was proper as a matter of law. [DN 125 at 41–49]. Accordingly, Big Rivers argues it is entitled to summary judgment. [Id.]. ADA responds that understanding Big Rivers’ draw is not as simple as Big Rivers’ briefing makes it seem. Further, ADA argues that questions of material fact pervade each of its claims such that summary judgment is improper. [DN 136]. II. STANDARD OF REVIEW AND LAW

Before the Court may grant a motion for summary judgment, it must find that there is no genuine dispute as to any material fact and that the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). The moving party bears the initial burden of specifying the basis for its motion and identifying the portion of the record that demonstrates the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). Once the moving party satisfies this burden, the non-moving party thereafter must produce specific facts demonstrating a genuine issue of fact for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247–48 (1986). Although the Court must review the evidence in the light most favorable to the non-moving party, the non-moving party must do more than merely show that there is some “metaphysical

doubt as to the material facts.” Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986). Instead, the Federal Rules of Civil Procedure require the non-moving party to present specific facts showing that a genuine factual issue exists by “citing to particular parts of materials in the record” or by “showing that the materials cited do not establish the absence . . . of a genuine dispute[.]” Fed. R. Civ. P. 56(c)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

ADA-ES, Inc. v. Big Rivers Electric Corporation, (W.D. Ky. 2020).

ADA-ES, Inc. v. Big Rivers Electric Corporation (ADA-ES, Inc. v. Big Rivers Electric Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United Fire & Casualty Co. v. Nissan Motor Corp. in U.S.A.
433 P.2d 769 (Supreme Court of Colorado, 1967)
Colorado National Bank of Denver v. Board of County Commissioners
634 P.2d 32 (Supreme Court of Colorado, 1981)
CenTra, Inc. v. Estrin
538 F.3d 402 (Sixth Circuit, 2008)
West Virginia Housing Development Fund v. Sroka
415 F. Supp. 1107 (W.D. Pennsylvania, 1976)
Intraworld Industries, Inc. v. Girard Trust Bank
336 A.2d 316 (Supreme Court of Pennsylvania, 1975)
Vinton v. Virzi
2012 CO 10 (Supreme Court of Colorado, 2012)
Coors v. Security Life of Denver Insurance Co.
91 P.3d 393 (Colorado Court of Appeals, 2004)
Coors v. Security Life of Denver Insurance Co.
112 P.3d 59 (Supreme Court of Colorado, 2005)
Kunz v. Warren
725 P.2d 794 (Colorado Court of Appeals, 1986)
Chacon v. Scavo
358 P.2d 614 (Supreme Court of Colorado, 1960)
Metzger v. Baker
24 P.2d 748 (Supreme Court of Colorado, 1933)
Rocky Mountain Exploration, Inc. v. Davis Graham & Stubbs LLP
2018 CO 54 (Supreme Court of Colorado, 2018)
Brodeur v. American Home Assurance Co.
169 P.3d 139 (Supreme Court of Colorado, 2007)
Bristol Bay Productions, LLC v. Lampack
2013 CO 60 (Supreme Court of Colorado, 2013)