ACS Const Co Inc v. General Power Corp
Opinion
IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT
No. 98-60491
ACS CONSTRUCTION CO., INC. OF MISSISSIPPI, Plaintiff-Appellee,
V.
GENERAL POWER CORPORATION, ET AL, Defendants,
VENGROFF, WILLIAMS AND ASSOCIATES, INC., Defendant-Appellant.
Appeal from the United States District Court Northern District of Mississippi Civil Action No. 4:96-CV-35-WB-B
December 30, 1999
Before DAVIS and JONES, Circuit Judges, and LEMELLE*, District Judge.
DAVIS, Circuit Judge:** Appellant Vengroff, Williams and Associates, Inc. ("Vengroff Williams") appeals the money judgment of the district court entered on a jury verdict. Appellant contends that the district court erred in determining it had personal jurisdiction based on the
*
District Judge of the Eastern District of Louisiana, sitting by designation.
**
Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.
contract prong of the Mississippi long-arm statute. In particular, Vengroff Williams argues that the district court's determination that it had personal jurisdiction was erroneous because the evidence was insufficient to establish that a contract was perfected in the meeting between Appellee ACS Construction Company, Inc. of Mississippi ("ACS") and Vengroff Williams. Appellant further argues that even if a contract was formed at the Greenwood, Mississippi meeting, none of the contract was performed in Mississippi. We conclude that no enforceable contract was entered into at the Greenwood, Mississippi meeting and that the district court erred in finding that it had personal jurisdiction under the "contract prong" of the Mississippi long-arm statute. We therefore reverse the judgment of the district court.
I.
This case arises from a government contracting job gone awry. In 1994, ACS sought two government building contracts, one at Fort Bragg in North Carolina and one at Fort Campbell in Kentucky. General Power Corporation (“General Power”), a South Carolina corporation, submitted bids to ACS to perform the electrical work for both projects. General Power was 50 percent owned by Albert B. Cialone. Vengroff Williams--whose principals are Harvey Vengroff and Robert Williams--and Sheldon Electric Co., Inc (“Sheldon Electric”)--whose principal is Barry J. Beil-- each owned 25 percent shares in General Power. ACS used General Power’s pricing in its bid to the government for both projects.
ACS was awarded both contracts and opened discussions with General Power about awarding General Power the electrical subcontract. When General Power informed ACS that it was unable to provide a performance bond, as it had agreed to do, ACS became concerned with General Power’s stability and began to look elsewhere for an electrical subcontractor. In an effort to allay these concerns, General Power invited ACS’s principals to a meeting in New York. ACS declined the invitation and instead invited General Power to attend a meeting at ACS’s headquarters in Greenwood, Mississippi.
General Power was well represented at the meeting with ACS in Greenwood, Mississippi. The General Power representatives were Al Cialone, Barry Beil, and critically for purposes of this appeal, Harvey Vengroff, representing his company Vengroff Williams. General Power met with ACS for approximately one and a half hours. The main topics discussed were the technical aspects of the electrical work that General Power would perform if it obtained the subcontracts from General Power. The subject turned briefly to General Power’s financial ability to perform the subcontracts. Mr. Vengroff assured ACS that his company was an investor in General Power and that it would provide the necessary financial support to assure completion of the subcontract.
No contracts were signed at the Greenwood, Mississippi meeting, but later in North Carolina, ACS and General Power signed electrical subcontract agreements covering the two government construction projects.
In the course of completing the electrical work at the construction sites, General Power ran into a series of difficulties. By all accounts, Cialone failed miserably as an administrator, and Vengroff Williams and Sheldon Electric came to his assistance. Despite Vengroff Williams’ infusion of approximately $800,000 into General power and Mr. Williams’ assumption of management duties at the Fort Bragg project, General Power continued losing money and it eventually filed for bankruptcy. ACS then commenced the present suit, alleging that, by allowing General Power to default on the subcontract, Vengroff Williams failed to perform as it had promised.
ACS initiated this action against General Power, Al Cialone;
Vengroff Williams, Harvey Vengroff and Robert Willams; Sheldon Electric and Barry Beil. ACS sued the parties under several theories, including breach of contract against General Power and breach of implied-in-fact contract against Vengroff Williams and Mr. Vengroff and Mr. Williams, individually. ACS also sued Vengroff Williams, Sheldon Electric, and the individual principals of these firms for the torts of trover, conversion, and material misrepresentation and fraud.
Shortly before trial ACS’s trover and conversion claims were dismissed pursuant to summary judgment. At this time, Vengroff Williams and other parties to the suit filed motions to dismiss for lack of personal jurisdiction until the close of plaintiff’s case. The district court postponed ruling on the motions for lack of personal jurisdiction. At the conclusion of ACS’s case-
in-chief, the district court (1) dismissed ACS’s fraud and misrepresentation claims, and (2) determined that it had personal jurisdiction over Vengroff Williams.
The district court allowed ACS’s breach of contract claim against Vengroff Williams to go to the jury, which returned a verdict for $83,000 in favor of ACS and against Vengroff Williams. This appeal followed.
II.
In a federal diversity action, personal jurisdiction is determined by a two-step inquiry addressing: (1) the forum state's long-arm statute, and (2) federal due process. Allred v. Moore & Peterson, 117 F.3d 278, 281 (5th Cir. 1997). If the state long-arm statute is not first satisfied, the federal due process question is never reached and jurisdiction fails. Cycles v. Digby, 889 F.2d 612, 616 (5th Cir. 1989). The Mississippi long-arm statute provides in relevant part:
Any nonresident person, firm, general or limited partnership, or any foreign or other corporation not qualified under the Constitution and laws of this state as doing business herein, who shall make a contract with a resident of this state to be performed in whole or in part by any party in this state ... shall by such acts be deemed to be doing business in Mississippi and shall thereby be subjected to the jurisdiction of the courts of this state.
Miss. Code Ann. § 13-3-57 (Supp.1998). Thus, the existence of an enforceable contract is a prerequisite to a finding of personal jurisdiction under the "contract prong" of the Mississippi long arm
statute.
We therefore turn to the principal argument on appeal: whether the evidence is sufficient to support the jury’s finding that a contract was perfected. In order to find that a contract exists, a fact finder must determine that both parties agreed to all of the essential terms. See Ham Marine, at 459; Knight v. Sharif, 875 F.2d 516, 525 (5th Cir. 1989). Because the alleged contract arose from the parties’ conversations at the Greenwood meeting, Mississippi contract law governs.
The district court held that the contract prong of the long-
Free access — add to your briefcase to read the full text and ask questions with AI
ACS Const Co Inc v. General Power Corp (ACS Const Co Inc v. General Power Corp) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.