Acreage Estates Co. v. Shelley

275 A.D.2d 842

This text of 275 A.D.2d 842 (Acreage Estates Co. v. Shelley) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acreage Estates Co. v. Shelley, 275 A.D.2d 842 (N.Y. Ct. App. 1949).

Opinion

In our opinion, respondent’s [843]*843grantee did not agree to complete the road improvements within a reasonable time after the making of the contracts or the transfer of title, but rather within sixty days after the completion óf an apartment house to he constructed on the parcel. However, she may not escape her obligation and prevent the commencement of the sixty-day period by failing to complete or even commence construction of the apartment building. In view of the fact that the contract of November 5, 1947, did not specify a date for completion of the building, at which time the sixty-day period was to commence, we are of opinion that the parties thereto contemplated the construction of the building to be completed, and, therefore, the sixty-day period to commence, within a reasonable time after the making of that contract or the closing of title. The complaint does not allege that a period of sixty days" has elapsed after the passing of reasonable time for construction of the building, but only that more than a reasonable time has elapsed for completion of both the building and the road improvement. It is our further opinion that the complaint, as pleaded, does not show that the promise to improve the road went “ to the root of the contract ”, by any factual allegations. (See Callanan v. Keeseville, Ausable Chasm, & Lake Champlain R. R. Co., 199 N. Y. 268, 284.) Johnston, Acting P. J., Adel, Sneed, Wenzel and MacCrate, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Callanan v. Keeseville, Ausable Chasm & Lake Champlain Railroad
199 N.Y. 268 (New York Court of Appeals, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
275 A.D.2d 842, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acreage-estates-co-v-shelley-nyappdiv-1949.