Opinion

Opinion op .the Court by

Judge Willis

Affirming.

The Acme Mills, of Hopkinsville, was visited by a disastrous fire, and its milling plant totally destroyed. The management was concerned to get the plant rebuilt with the greatest possible dispatch. The plan pursued was to invite various responsible contractors to submit both specifications and a bid for a completely restored plant. Several propositions were under consideration, but the variations in the prices 'suggested caution. M. G-. Moore is a contractor and engineer, and claims that *722 he was employed by appellant to render expért advice in choosing a contractor, negotiating a contract for the new structure, and in superintending the execution of the work. It is appellant’s claim that Moore was a friendly volunteer who endeavored to have all bids rejected to the end that he might be employed to erect the plant on a cost-plhs basis. Moore was not allowed to superintend the construction of the new plant. He sued the appellant to recover $2,200 for the services rendered, and to be rendered under the contract as he claimed it to be. He averred a breach of the contract in that he was denied the right to superintend the work, and was not paid anything for his services. The answer of appellant contained a specific denial of every allegation of the petition. The jury returned a verdict in favor of the plaintiff for $1,100 which the court reduced to $800, and rendered judgment accordingly. The Acme Mills has prosecuted an appeal. It is admitted that the issues respecting the existence and terms of the contract with Moore were ones of fact addressed necessarily to the jury whose verdict for plaintiff is sufficiently supported by the evidence. But it is earnestly insisted for appellant that the circuit court erred in the admission of certain evidence for plaintiff, in giving the first' instruction to the jury, and in refusing a requested instruction.

1. The complaint as regards incompetent evidence is confined to a criticism of testimony tending to show that appellant already had made a contract with a Chicago concern when Moore first appeared in the picture, and to the introduction of a letter written by appellant’s president and published in a trade magazine. It is argued that the evidence was inconxpetent and prejudicial because it had no relevancy to the issues to be tried and tended to prejudice the appellant by indicating its readiness to break contracts. The construction superintendent of the Chicago concern testified that he was advised his company had submitted a bid of $48,750 for the work, and that he had been told that the offer of his company had been accepted by telephone. He did not testify that any contract was actually made, but that he was so advised, and was in Hopkinsville to go over details and to bring the matter to a conclusion. Moore was presented to him by appellant’s president as its engineer to check over the,plans and to report on the reasonableness of the offer. Moore did examine the proposed plans and thought the proposed price too high. He endeavored to *723 induce the submission of a lower bid. It is obvious that the situation confronting Moore had to be developed in order that the jury could appreciate the conduct and relative positions and attitudes of the parties. The witness made it quite clear to the jury that he had no personal knowledge of the prior negotiations, and was proceeding upon the information given him. The fact that appellant was seriously considering and actually contemplating acceptance of the offer of the Chicago concern was relevant to illustrate the value of Moore’s services in ascertaining and advising that a better contract could be obtained. In fact a much better one was obtained resulting in substantial saving to appellant. The testimony of appellant’s president made it clear beyond controversy that no contract was ever closed with the Chicago company. We are unable to concur with counsel that the jury could have been prejudiced by the testimony. It merely showed that, before actually concluding a contract, appellant’s president desired to be assured that the offer was a fair and suitable one. Moore’s advise was given in the exigency, and it was proper for the jury to know the circumstances under which he and appellant acted. The letter to the magazine was not offered as substantive evidence. It was introduced in contradiction of statements made on the witness stand by tlie president, possessed some probative tendency in that direction, and was clearly competent for that purpose. No request was made for an admonition to the jury respecting the purpose of the evidence, but it was so apparent that no admonition was thought necessary at the time. Indeed, the letter could not be construed otherwise. It merely explained how the ultimate contract had been concluded with another contractor, and that it had been satisfactorily performed. There was no error in the rulings of the court regulating the admission of testimony.

2. The criticism of the first instruction relates to the concluding sentence which directed the jury, if the issues thereby submitted were found in favor of the plaintiff, to allow him “the reasonable value of said services, not exceeding the sum of $2,200.00, the amount claimed in the petition.” It is argued that the utmost recovery authorized by the proof was $1,100 and that the instruction should have confined the jury to that sum rather than to the sum claimed in the plaintiff’s pleading. In Louisville & N. R. Co. v. Ashley, 169 Ky. 330, *724 183 S. W. 921, 925, L. R. A. 1916E, page 763, this court directed that an instruction to he given on another trial should limit the jury to the damages shown by the evidence saying: “While in the light of the other instructions given we would not reverse the judgment on account of the defect complained of, upon another trial the instruction should be so written as to free it from such defect.” It is apparent from the statement of the court and the authorities cited to support it that the instruction as given had failed to require the jury to base the amount of damage upon the evidence adduced. In Davis, Agent, v. Rhodes, 206 Ky. 340, 266 S. W. 1091, this court reversed a judgment because an instruction to the jury respecting special damages authorized the jury to find an amount claimed in the petition, instead of confining it to the amount shown by the evidence, which was materially less than the amount claimed therefor in the petition. The judgment was in gross, and the court under those conditions, deemed the error prejudicial. In Consolidated Coach Corporation v. Hopkins, 228 Ky. 184, 14 S. W. (2d) 768, the question was fully discussed and the rules regulating the matter carefully explained. In Georgia, S. & Florida Ry. Co. v. Makeever, 228 Ky. 492, 15 S. W. (2d) 293, a judgment was reversed because the jury was authorized by the instruction to allow, and had in fact allowed, the full amount of damages claimed, notwithstanding the fact that, the maximum damage shown by the proof was only 8Ó per cent, of the amount allowed. The plaintiff in the present case was not claiming special damages. He was seeking to recover reasonable compensation for services rendered and to be rendered, and the proof introduced, coupled with the knowledge of the jury respecting the value of professional services, made it unnecessary for the court to limit the amount otherwise than as claimed, in the petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Austin v. Portland Traction Co.
182 P.2d 412 (Oregon Supreme Court, 1947)
Blue Diamond Coal Company v. Robertson
31 S.W.2d 701 (Court of Appeals of Kentucky (pre-1976), 1930)

Cite This Page — Counsel Stack

Bluebook (online)
22 S.W.2d 106, 231 Ky. 720, 1929 Ky. LEXIS 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acme-mills-v-moore-kyctapphigh-1929.