Acme Lumber Co. v. Board of Com'rs of Port

69 So. 739, 137 La. 899, 1915 La. LEXIS 1776
CourtSupreme Court of Louisiana
DecidedJune 29, 1915
DocketNo. 21123
StatusPublished
Cited by1 cases

This text of 69 So. 739 (Acme Lumber Co. v. Board of Com'rs of Port) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acme Lumber Co. v. Board of Com'rs of Port, 69 So. 739, 137 La. 899, 1915 La. LEXIS 1776 (La. 1915).

Opinion

O’NIELL, J.

In December, 1912, the board of commissioners of the port of New Orleans advertised for sealed proposals to furnish and deliver to the board such lumber as might be ordered for repairs, etc., during a period of one year. A circular accompanied the advertisement, informing bidders that the board would require approximately 1,700,-000 feet, board measure, and stated approximately the quantity of each of the principal dimensions that would be needed during the year.

Bids were invited per thousand feet, board measure, of yellow pine lumber of “B” grade, as defined by the classification of the Contractors’ & Dealers’ Exchange of New Orleans. The specifications provided that the contractor should furnish all the lumber or[901]*901dered by the superintendent, which should meet the requirements of the specifications, and that the contractor should furnish all possible conveniences for the inspection of the lumber by the superintendent or his representative. The specifications declared that the term “superintendent,” as used therein, meant, not only the superintendent of the board, but also his duly authorized representative. It was stipulated that all of the lumber should be subject to the approval of the superintendent, who should be the sole judge of the quality thereof and the measurements, and that, if any lumber should be rejected, it had to be removed at once by the contractor and replaced as soon as possible by proper material, and that the superintendent should be the sole judge of the meaning of the specifications wherever they were silent or inexplicit on any subject. Payments were to be made monthly on bills for lumber actually furnished and approved by the superintendent or his authorized representative.

The specifications required that the lumber should be delivered by the contractor at such •places on the river front, between Peters avenue and Poland streets, as might be designated in the orders of the superintendent or his authorized representative, in such sizes and quantities as might be ordered. And, as to orders for a ear load of 10,000 feet, it was stipulated that, in the event of nonshipment within 24 hours after an order was delivered to the contractor or his authorized representative, the superintendent should have the right to order the lumber from other parties and deduct the excess of the cost from the monthly bills of the contractor, a corresponding delay being allowed the contractor to fill orders for larger quantities than one car load. Orders were not to be given for less than a oar load of 10,000 feet of lumber; but an order might require the delivery of a car load at several points and ■impose the expense of switching and hauling upon the contractor. All lumber delivered was to be unloaded by the contractor at the places of delivery stated in the orders. The contractor was required to keep on hand at all times, ready for delivery, at least 100,000 feet of lumber of the dimensions stated in the specifications. The specifications contained other provisions not pertinent to the issues involved in this case.

The plaintiff, being the lowest bidder, was awarded the contract at the opening of the proposals on the 8th of January, 1913; and, on the 18th of that month, the parties signed a contract submitted by the board. This contract was on a printed form that was intended for contracts for the construction of buildings and other works, and it contains many provisions that are irrelevant to the contract that was entered into by the board’s acceptance of the lumber company’s proposal or bid.

The plaintiff made shipments of lumber in February, March, and April, for which payments were made promptly on the 10th of each month succeeding the month of delivery, according to the contract.. In the meantime, there was a change in the membership of the board of commissioners; and, in May, 1913, one of the new members inspected the wharves and discovered, as he thought, that the lumber inspectors employed by the superintendent had accepted a considerable quantity of lumber that was not up to “B” grade. An investigation followed, and resulted in a proposition being made by the board to the lumber company to have the lumber reinspected, which the lumber company declined. In the meantime, orders for 166,712 feet of lumber, amounting to $3,-593.54, were filled in the month of May, for which the board refused to pay on the 10th of June, when the bill was due, at which time the contractor had filled orders in June for 54,170 feet of lumber, amounting to $1,-104.74, for which the board also declined to [903]*903make payment unless the contractor would consent to a reinspection of the lumber that had been accepted. The board refused to allow the contractor to unload two car loads of lumber which had been set out on the river front, and which the lumber company was finally compelled to remove and dispose of elsewhere. After several meetings and considerable correspondence between the representatives of the lumber company and the board, the contractor formally put the board in default and thereafter instituted this suit to recover $3,593.54 for the lumber delivered in May; $1,104.74 for the lumber delivered in June; $519.40 for expense of storing, belting, and demurrage on 20 cars of lumber which the plaintiff had held at the port and was prevented by the defendant’s employés from delivering for inspection; $2,907.12 for loss of profit, at $2.97 per thousand feet, on 978,889 feet of lumber, ordered by the board, but not delivered by plaintiff, on account of the alleged breach of the contract by the defendant board; and $10,24S.61 for loss of profit, at $5.97 per thousand feet, on 1,716,702 feet of lumber, estimated as the quantity of lumber which the defendant board would have ordered during the remaining 6% months if the contract had been carried out, in proportion to the quantity ordered and delivered during the first 5% months.

In answer to the petition, the defendant alleged that it was justified in refusing to pay for the lumber delivered in May and June, 1913, because the receipt of the lumber was, as defendant alleged, unauthorized, because it was not inspected by the superintendent of the board, nor by his authorized representative. The defendant alleged that the plaintiff had, in bad faith and with a desire to take advantage of the fact that some of the so-called lumber inspectors of the defendant board were incompetent and inexperienced, ordered from the mills in Mississippi a grade of lumber there called “square edge and sound,” including a large proportion of sap and very little “B” grade lumber. The defendant alleged that:

“By faulty and imperfect, incomplete, and erroneous inspections by defendant’s inspectors, much of said inferior lumber was passed by said inspectors, which inspection was subsequently not approved as to the May bills of 1913 by the engineer of the board, then acting as superintendent of these lumber deliveries, by special resolution of this board.”

The defendant asserted a demand in reconvention for damages in the sum of $5,000 for the expense of maintaining a large force of laborers without a sufficient supply of “B” grade lumber to keep them occupied, and in the sum of $3,000 for the excess cost of the lumber purchased elsewhere after June, 1913, above the prices at which the plaintiff contracted to furnish “B” grade lumber.

Judgment was rendered in favor of the plaintiff for $8,077.75, with legal interest on $3,593.80 from June 10, 1913, on $1,057.33 from July 10,1913, and on the items of $519.-40 and $2,907.12 from judicial demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles v. Town of Jeanerette, Inc.
234 So. 2d 794 (Louisiana Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
69 So. 739, 137 La. 899, 1915 La. LEXIS 1776, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acme-lumber-co-v-board-of-comrs-of-port-la-1915.