Acme Glass Co. v. Woods-Lloyd Co.

182 A.D. 538, 170 N.Y.S. 448, 1918 N.Y. App. Div. LEXIS 7893
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 27, 1918
StatusPublished
Cited by3 cases

This text of 182 A.D. 538 (Acme Glass Co. v. Woods-Lloyd Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acme Glass Co. v. Woods-Lloyd Co., 182 A.D. 538, 170 N.Y.S. 448, 1918 N.Y. App. Div. LEXIS 7893 (N.Y. Ct. App. 1918).

Opinion

De Angeles, J.:

This is an action for breach of an implied warranty in a contract of sale.

The plaintiff is a domestic corporation whose principal place of business is in the city of Olean where it conducts one of its glass factories and employs about 100 men.'

The defendant is a foreign corporation of the city of Pittsburgh, in the State of Pennsylvania, and is engaged in manufacturing and selling flux blocks and other blocks and material used in the construction and maintenance of furnaces for melting the constituents of glass, referred to herein as glass furnaces.

The facts (some of which are conceded and many of which are established by uncontradicted evidence) which the jury were justified in finding are as follow:

The defendant and its predecessors up. to and including the year 1911 had for many years furnished the plaintiff with flux blocks and other material for use by the plaintiff in the construction, reconstruction and maintenance of its glass furnaces. These blocks are made of clay and resemble great bricks. Among the usual sizes of such blocks are those twelve by twenty-four by eighteen inches and twelve by twenty-four by thirty-six inches. The plaintiff was engaged in manufactur[540]*540ing glass bottles at its factory in the city of Olean where it maintained and operated a tank glass furnace continuously, day and night, for.ten months in each year, to wit, for each month except July and August. The tank is about twenty-nine feet long and fourteen or eighteen feet wide and its sides are about three feet high. The bottom, the sides and ends are made of these clay blocks. The sides are made of flux blocks twelve by eighteen by twenty-four inches. Each side has two tiers of these blocks, laid one on the top of the other and that part of each block whose dimension is eighteen inches is vertical, making each side thirty-six inches high and twelve inches thick. On the top of the upper tier are tiles - twenty-four inches long and twelve inches square, laid lengthwise, horizontally, with intervals for port holes for the introduction of gas from which heat is supplied for the melting process hereinafter described. The roof of the furnace is an arch made of silica bricks. ' A steel framework is used to support and strengthen the structure. In this tank, sand, lime and soda are melted to form the liquid glass from which the bottles are blown. These constituents of glass are subjected to a heat of about 2,200 degrees Fahrenheit, and are introduced into the tank in prepared batches containing proper proportions. The heat of the greatest intensity comes in contact with the blocks forming the sides of the tank. These blocks need to be made of the best German clay and in the most careful manner because of their subjection to . such intense heat and they are known in the trade and business as flux blocks for that reason. The life of such blocks is from one to two years and at least one season.

After the construction or reconstruction of one of these furnaces, the first material introduced into the tank and subjected to the heat is cold glass to be melted for the purpose of glazing the flux blocks to prepare them to resist more effectively than otherwise they could the intensity, of the heat to which they are to be subjected in the process of melting the sand, lime and soda.

In this same- building where the furnace just described is located, there is a much smaller furnace used by the plaintiff as auxiliary to the work of the large furnace in the busier part of the season.

[541]*541In March, 1911, plaintiff’s president notified the defendant that this large furnace would need reconstruction in the rest period which would begin on the first of July, and about that time one of the defendant’s officers inspected the furnace and conferred with the plaintiff’s president regarding the number of flux blocks and other material that would be needed in the reconstruction. Later the defendant furnished the plaintiff with a blue print indicating the proposed work of reconstruction and the necessary number and location of flux blocks to be used therein. Such flux blocks with the other material were shipped by the defendant to the plaintiff in the latter part of June and thereafter paid for. The amount paid for the flux blocks was about $629. In the summer .of 1911 the work of reconstruction was completed and the flux blocks received from the defendant formed the sides of the tank. In the latter days of August the interior of the tank was glazed by the melting of cold glass which operation occupied about two weeks, at the conclusion of which the process of melting sand,- lime and soda began and then continued day and night until the 30th day of March following (1912) when it became necessary to turn off the heat and stop the use of the tank. Thereupon the contents of the tank were permitted to get cool and the glass was chopped out and it was discovered that many of the flux blocks had crumbled off so as to leave but an inch in thickness; that they had a spongy and honeycombed appearance, and that they contained numerous crevices permitting the fluid glass to penetrate and cause them to disintegrate. These defects were not discovered by the plaintiff before the thirtieth day of March, and were not discoverable by the plaintiff through the means of any system of inspection before the blocks were used in the reconstruction and operation of the furnace. The discovery of this condition led to the stopping of the operation of the furnace. The furnace had to be entirely tom down and a new furnace constructed in its place. The furnace that was torn down had been properly constructed and from the completion of the reconstruction up to March 30, 1912, operated properly and in the usual and customary manner and the necessity for tearing it down and the construction of a new furnace was due solely to the defective condition just [542]*542described. The new furnace cost about $3,100 and was not ready for use until about the 18th day of May, 1912. There was an interruption of the plaintiff’s business for the interval between the thirtieth day of March and the eighteenth day of May, except that the smaller furnace was operated from about the ninth day of April. The plaintiff lost in profits by reason of the interruption of its business an amount which the jury might have found to be in the neighborhood of $3,000.

When the defendant furnished to the plaintiff the flux blocks in question it knew the exact situation of the plaintiff’s plant in Olean, its facilities and limitations; that if this large furnace should go out of commission the plaintiff’s business would be substantially at a standstill, and that if the flux blocks in question should prove tp be defective, as they did prove to be, plaintiff’s loss by the interruption of its business and the expense of a new furnace would be great, and, probably, no less than the jury found it to have been.

The jury rendered a verdict for $4,000 which does not seem to be excessive.

Our Sales of Goods Act (Laws of 1911, chap. 571, in effect Sept. 1, 1911, adding to Pers. Prop. Law [Consol. Laws, chap. 41; Laws of 1909, chap. 45], §§ 82-158) has no application here because the cause of action accrued before September 1, 1911. So that this controversy must be decided under the common law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cramerton Mills, Inc. v. Nathan & Cohen Co.
231 A.D. 28 (Appellate Division of the Supreme Court of New York, 1930)
Dickson v. Niles
122 Misc. 818 (New York Supreme Court, 1924)
Hettrick Manufacturing Co. v. Barish
120 Misc. 673 (Appellate Terms of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
182 A.D. 538, 170 N.Y.S. 448, 1918 N.Y. App. Div. LEXIS 7893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acme-glass-co-v-woods-lloyd-co-nyappdiv-1918.