Acme Brick Co. v. Hamilton

238 S.W.2d 658, 218 Ark. 742, 1951 Ark. LEXIS 414
CourtSupreme Court of Arkansas
DecidedApril 16, 1951
Docket4-9447
StatusPublished
Cited by12 cases

This text of 238 S.W.2d 658 (Acme Brick Co. v. Hamilton) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acme Brick Co. v. Hamilton, 238 S.W.2d 658, 218 Ark. 742, 1951 Ark. LEXIS 414 (Ark. 1951).

Opinion

Griefin Smith, Chief Justice.

Orville E. Hamilton and his wife contracted with Bralei Homes, Inc., for the construction of a brick-veneered home for $10,254. All materials and work were to be provided by Bralei, but the prospective homeowners were given the right to designate the brick type, with particular reference to color. Acme Brick Company, of Malvern, maintains a showroom in Little Rock. The Hamiltons were informed that they should make the selection and convey their preference to the contractor for inclusion in the written agreement. Brick displays, including four color shades, were arranged for convenient inspection in Acme’s showroom, with assigned numbers or labels.

The Hamiltons alleged in’ their suit against Bralei and Acme that Nos. 743 to 746M were selected, but were not supplied; nor did the color of the bricks that were delivered to Bralei correspond with those shown in the display panel. The discrepancy was not discovered until, the walls had been finished and cleaned by removing surplus mortar, etc. When the vice was observed and Bralei declined to make satisfactory adjustments, suit was filed. The complaint alleged that it would cost $1,381 to remove the off-color veneer and replace it with brick the contract called for. It was estimated that in other respects the construction as a whole was $3,653 short of completion. A temporary impasse resulted and work was stopped. Damages based on rentals at $50 per month paid by the Hamiltons were alleged, to which was added interest charged on money borrowed to pay the contractor. Bralei entered a denial and also cross-complained against Acme.

Acme’s defenses were multiple, (a) The Hamiltons failed to notify the company that a mistake had been made; (b) after inspection of the walls in their uncompleted form the color variations should have been discovered, therefore the mistake was waived; (c) the bricks delivered, in respect of color, were substantially like the samples upon which, the order was based, and (d) there was no privity of contract between Acme and the Hamiltons. In its cross-complaint Acme contended that Bralei knew, or ought to have known, that the error had been made, hence as between Acme and Bralei the latter had waived any right to recover. Specifically it was urged that a printed form, used by Acme as an invoice in lieu of delivery tickets, contained a provision for prompt inspection and notification of error on penalty of waiver.

The decree gave the Hamiltons $1,300 to compensate removal and replacement of the veneer, and interest and rental costs aggregating $201.27 — a total of $1,501.27 adjudged against Acme. Bralei, on its cross-complaint, was given judgment for $157.71 against Acme. The Hamilton complaint against Bralei and Acme’s cross-complaint were dismissed. Acme appealed here, as did the Hamiltons.

First — Relationship Between the Parties. — Acme contends that the Hamiltons were merely incidental beneficiaries of its contract with Bralei and therefore have no cause of action. One of the most recent cases dealing with rights of a third party beneficiary was decided on January 10th of this year by the Maryland Court of Appeals, Marlboro Shirt Co. v. American Dist. Tel. Co., 77 Atl. 2d 776. The three kinds of third party beneficiaries are discussed — donee, creditor, and incidental. Marlborough Shirt Co. sued American District Telegraph Company. The Shirt Company had leased part of a building owned by Rosenbloom. After the Shirt Company’s occupancy began Rosenbloom contracted with the Telegraph Company to install and maintain as part of an existing sprinkler system an automatic signaling device designed to register in the Telegraph Company’s office any leakage that might occur. A substantial leak developed and the signal service failed to function, with consequential damage to goods stored by the Shirt Company. The trial court sustained a demurrer to the complaint and the order of dismissal was upheld on appeal.

In the opinion written by Judge Grayson the question was stated in this way: Was the demurrer properly sustained where the facts alleged showed negligence on the part of [the Telegraph Company] and where the facts further show that the contract in question of necessity had to be for the benefit of [the Shirt Company?] The Telegraph Company’s contention was that the contract was not intended to benefit the Shirt Company. The Maryland decisions, said Judge Grayson, have receded from the common law rigidity requiring privity of contract before an action can be maintained, even though the contract is for the benefit of a third party: . . . “[The old rule] has gradually relaxed, so that now, in this state, a person for whose benefit a contract is made can maintain an action upon it. But before one can do so it must be shown that the contract was intended for his benefit; and, in order for a third party beneficiary to recover for a breach of contract it must clearly appear that the parties intended to recognize him as the primary party in interest and as privy to the promise.” See Restatement, Contracts, § 133. (Acme has cited § 147 of the Restatement.)

A hypothetical relationship where a cause of action does not lie is given by the Maryland court: “If A enters into a contract with B and [B?] does not know that A intends C to be the beneficiary under the contract, C cannot enforce the promise made by A, for it would not appear that A and B recognized C as the primary party in interest and as privy to the promise. . . . [But] there are cases where the name of the beneficiary is not stated, but where he can recover under the contract. In such cases the facts and circumstances surrounding the transaction show clearly that a particular person (though not named) is the beneficiary. Williston on Contracts, Revised Ed., vol. 2, § 378.”

When tested by these rules did Acme owe to the Hamiltons a duty of more than incidental importance?

The Brick Company admits that it did not supply Bralei from stock corresponding with the identifying numbers displayed. Nor is it denied that the Hamiltons were told that better results would be obtained if they inspected houses where the identical colors represented by numbers 743 to 746M had been used. Bralei had built extensively and is a substantial Acme patron; but, according to the Hamiltons, they had a right to select from stocks offered by Acme or the Hope Brick Company. An Acme salesman, in furtherance of an obvious purpose to procure the order — and also being anxious to extend any reasonable accommodation that might prove helpful— mentioned three houses where the bricks had been used.

Orville E. Hamilton testified that the Acme office manager urged him and Mrs. Hamilton to inspect the houses mentioned — “He insisted that we go to these sites to help us in deciding which brick we wanted”. The manager explained that the office samples would not look exactly like a finished wall would appear, hence the importance of viewing a completed house. The manager for Acme, with commendable forthrightness, admitted error in writing the order after the selection had been made from the inspections referred to and from samples. It appears conclusive, therefore, that at a time when the Hamiltons had a right under their contract with Bralei to designate either Acme or Hope Brick Company products, they were urged into a course of moderate inconvenience in consequence of which Acme hoped to procure the order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jin Ok Choi v. Chase Manhattan Mortgage Co.
63 F. Supp. 2d 874 (N.D. Illinois, 1999)
Corrugated Paper Products, Inc. v. Longview Fibre Co.
868 F.2d 908 (Seventh Circuit, 1989)
Cox v. Fremont County Public Building Authority
415 F.2d 882 (Tenth Circuit, 1969)
Mullray v. Aire-Lok Co.
216 So. 2d 801 (District Court of Appeal of Florida, 1968)
Rhodes Pharmacal Co. v. Continental Can Co.
219 N.E.2d 726 (Appellate Court of Illinois, 1966)
Canute v. Burnett
373 S.W.2d 143 (Supreme Court of Arkansas, 1963)
Fairchild Stratos Corp. v. Siegler Corp.
225 F. Supp. 135 (D. Maryland, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
238 S.W.2d 658, 218 Ark. 742, 1951 Ark. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acme-brick-co-v-hamilton-ark-1951.