Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

GERALD ACKERMAN and MARK SHAYKIN,

Plaintiffs, Civil Case No. 13-14137 v. Honorable Linda V. Parker

HEIDI WASHINGTON,

Defendant. _________________________/

OPINION AND ORDER DENYING PLAINTIFFS’ MOTIONS

In this class action lawsuit, prisoners approved for a religious (kosher) diet claimed that their federal rights were violated by the Michigan Department of Corrections’ provision of a one-size fits all vegan diet. The matter is again before the Court on several post-judgment motions filed by Plaintiffs. Two of the motions are filed pro se by members of the Class (ECF Nos. 299, 309), even though they are represented by counsel. As this is improper, see In re Pertuset, 492 B.R. 232, 246 (S.D. Ohio. 2012) (citing cases interpreting 28 U.S.C. § 1654), the Court is striking those motions. Class counsel did file two motions: (i) “Plaintiff[s’] Motion for an Order Finding that Defendant’s Certification of Prison Kitchens is not in Compliance with the Settlement Agreement and Judgment that these Kitchens are to be Certified Kosher Kitchens” (ECF No. 297) and (ii) “Motion to Engage in Discovery in Support of Motion to Enforce Settlement Agreement” (ECF No. 298). The motions have been fully briefed. (ECF Nos. 302,

304, 307, 308.) Plaintiffs’ motions arise from the parties’ settlement agreement, which provides in relevant part:

14. If Defendant provides Kosher meals produced inside Defendant’s facilities, such meals shall be produced inside a Certified Kosher kitchen. Once a facility kitchen is Certified Kosher, Defendant will provide written notice to Plaintiffs’ counsel. Plaintiffs’ counsel and their expert(s) will have 21 days from the date of receiving the written notice to inspect the Certified Kosher kitchen. If, after inspection, Plaintiffs’ counsel does not agree that a kitchen is operating in a Certified Kosher manner, Plaintiffs may move this Court to enforce this Agreement.

(ECF No. 213 at Pg ID 2179-80.) In February 2020, the kitchens of several MDOC facilities were certified kosher through Kosher Michigan, LLC, and Defendant notified Plaintiffs’ counsel of the certifications. (See ECF No. 297-3 at Pg ID 3170-74; ECF No. 297-7 at Pg ID 3185.) Plaintiffs assert that Defendant breached the terms of the parties’ settlement agreement by not obtaining an Orthodox Jewish agency to certify the kitchens, which would have mandated certain requirements not currently followed in the kitchens (e.g., the necessary involvement of Jewish individuals in the preparation of the food).1 Plaintiffs maintain that because the kitchens were not properly certified in the first instance,

there was no reason for their counsel and/or expert to inspect the kitchens in accordance with the process contemplated in the settlement agreement.2 Plaintiffs also seek discovery to assess the adequacy of Kosher Michigan’s

certification. (ECF No. 298.) For example, Plaintiffs want to find out how long Kosher Michigan’s rabbi spent inspecting the kitchens, the equipment the rabbi used to kosherize the kitchens, and who was present. (Id. at Pg ID 3189-90.) This is the second time Plaintiffs have asked the Court to find that the

certifications violated the settlement agreement because they were performed by a Conservative rather than an Orthodox Jewish rabbi. On February 25, 2020, Plaintiffs filed a motion to enforce the settlement agreement contending that

Defendant had obtained “illegitimate” kosher certifications of the prison kitchens.

1 In their reply brief, Plaintiffs raise two concerns regarding the kosherization of the kitchens at the Ionia (ICF) and Carson City (CRF) Correctional facilities. (See ECF No. 307 at Pg ID 3336-38.) Specifically, there was an incident involving the frying of a chicken in the kosher kitchen at CRF after the kitchen was certified kosher, which would result in it no longer being kosher until it was kosherized again. The oven used to prepare kosher food at ICF is outside the vegan area. These incidents or matters were not presented in Plaintiffs’ initial motion, however. A reply brief is not the proper place to raise entirely new arguments. See Scottsdale Ins. Co. v. Flowers, 513 F.3d 546, 553 (6th Cir. 2008). 2 Plaintiffs list other reasons for not inspecting the kitchens within the time provided in the settlement agreement, such as the closure of MDOC’s prisons due to the COVID-19 pandemic (see ECF No. 297 at 3155); however, the reasons are not relevant to deciding their motion. (ECF No. 249.) The Court denied Plaintiffs’ motion less than two weeks before they filed their current motions. (ECF No. 296.)

The Court denied the motion because it found “no indication that [certification in accordance with Orthodox Jewish beliefs] was the intent of the Settlement Agreement, []or this lawsuit ….” (ECF No. 296 at Pg ID 3149.) As the

Court noted, the Class certified is not limited to Orthodox Jews and Plaintiffs never argued that this litigation is only about the religious beliefs of Orthodox Jews or that Orthodox certification was required. (Id.) Perhaps most importantly, the word “Orthodox” appears nowhere in the settlement agreement, much less in reference

to the type of certification required. (Id.) Under Michigan law, “‘an agreement to settle a pending lawsuit is a contract and is reviewed by the legal principles applicable to contract construction and

interpretation.’” Mich. Mut. Ins. Co. v. Indiana Ins. Co., 637 N.W.2d 232, 235 (Mich. Ct. App. 2001) (quoting Walbridge Aldinger Co. v. Walcon Corp., 525 N.W.2d 489, 491 (Mich. Ct. App. 1994)). “‘The primary goal in the construction or interpretation of any contract is to honor the intent of the parties.’” Sault Ste.

Marie Tribe of Chippewa Indians v. Engler, 271 F.3d 235, 238 (6th Cir. 2001) (quoting Rasheed v. Chrysler Corp., 517 N.W.2d 19, 29 n. 28 (Mich. 1994)). The court must “‘look for the intent of the parties in the words used in the instrument[.]’” Id. (quoting Mich. Chandelier Co. v. Morse, 297 N.W. 64, 67 (Mich. 1941)).

The words in a contract should be given their plain ordinary meaning. MLW Assoc. v. Certified Tool & Mfg. Corp., 106 F. App’x 307, 312 (6th Cir. 2004) (citing Bandit Indus. Inc. v. Hobbs, Int’l, Inc., 620 N.W.2d 531, 533 (Mich. 2001);

Rasheed, 517 N.W.2d at 24; Bianci v. Auto Club of Mich., 467 N.W.2d 17, 20 (Mich. 1991)). Courts may refer to dictionary definitions to ascertain the plain and ordinary meaning of undefined terms. Coates v. Bastian Bros., Inc., 741 N.W.2d 539, 544 (Mich. Ct. App. 2007) (citing Cole v. Auto Owners, Inc., 723 N.W.2d

922, 924 (Mich. Ct. App. 2006)). “Importantly, however, a word is not ambiguous simply because dictionary definitions differ.” Cole, 723 N.W.2d at 924 (citing Koontz v. Ameritech Servs., Inc., 645 N.W.2d 34, 42 (Mich. 2002)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koontz v. Ameritech Services, Inc
645 N.W.2d 34 (Michigan Supreme Court, 2002)
Bandit Industries, Inc. v. Hobbs International, Inc.
620 N.W.2d 531 (Michigan Supreme Court, 2001)
Scottsdale Insurance v. Flowers
513 F.3d 546 (Sixth Circuit, 2008)
Michigan Mutual Insurance v. Indiana Insurance
637 N.W.2d 232 (Michigan Court of Appeals, 2001)
Rasheed v. Chrysler Corp.
517 N.W.2d 19 (Michigan Supreme Court, 1994)
Bianchi v. AUTO CLUB OF MICH.
467 N.W.2d 17 (Michigan Supreme Court, 1991)
Cole v. Auto-Owners Insurance
723 N.W.2d 922 (Michigan Court of Appeals, 2006)
Walbridge Aldinger Co. v. Walcon Corp.
525 N.W.2d 489 (Michigan Court of Appeals, 1994)
Coates v. Bastian Brothers, Inc
741 N.W.2d 539 (Michigan Court of Appeals, 2007)
Michigan Chandelier Co. v. Morse
297 N.W. 64 (Michigan Supreme Court, 1941)
In re Pertuset
492 B.R. 232 (S.D. Ohio, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Ackerman v. Washington, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ackerman-v-washington-mied-2021.