Ace Hamm & Dana Hamm v. Steve Vaughn, Individually and D/B/A Vaughn Construction
This text of Ace Hamm & Dana Hamm v. Steve Vaughn, Individually and D/B/A Vaughn Construction (Ace Hamm & Dana Hamm v. Steve Vaughn, Individually and D/B/A Vaughn Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NO. 07-10-0118-CV
IN THE COURT OF APPEALS
FOR THE SEVENTH DISTRICT OF TEXAS
AT AMARILLO
PANEL B
OCTOBER 18, 2010 ______________________________
ACE and DANA HAMM,
Appellants v.
STEVE VAUGHN, individually and d/b/a VAUGHN CONSTRUCTION,
Appellee _______________________________
FROM THE 121st DISTRICT COURT OF TERRY COUNTY;
NO. 18258; HON. DAVID GLEASON, PRESIDING _______________________________
Memorandum Opinion _______________________________
Before QUINN, C.J., and CAMPBELL and HANCOCK, JJ.
Pending before this court is the appeal of Ace and Dana Hamm from a judgment
denying them recovery against Steve Vaughn d/b/a Vaughn Construction and awarding
Vaughn damages against the Hamms. The latter had sued Vaughn to recover
damages for his alleged failure to complete the construction of their home. The default
purportedly resulted in the Hamms suffering “economic and non-economic damages.”
Vaughn, in turn, sued the Hamms for breach of contract. The jury rendered a verdict in
favor of Vaughn, and the trial judge entered judgment based on that verdict. The Hamms now question the legal and factual sufficiency of the evidence
underlying that portion of the verdict finding that they breached first and that their
breach was unexcused. We affirm the judgment.
According to evidence of record, the Hamms and Vaughn executed a written
“bid” contract under which Vaughn agreed to construct them a home for $569,750.
Though the parties had talked about it, Vaughn explicitly refused to execute a “cost-
plus” agreement. Construction began in November of 2007, and proceeded without
incident for several months. Then, in March of 2008, Ace demanded that Vaughn
deliver to him the invoices of Vaughn’s subcontractors and suppliers. Vaughn was told
by Ace that the latter wanted to “know what . . . this job [was] costing” him. Vaughn
then told Ace that he did not disclose his invoices on jobs performed under bid contracts
but rather only on those done under cost plus agreements. To that, Ace responded
with: “. . . if you don't show me your invoices, I'm going to let you go.”
Though Vaughn disclosed to Ace the specification sheets containing an
itemization of the “allowances” involved, Ace nonetheless persisted in his demand for
invoices. So too did he inform Vaughn that “I got friends that can help me finish this
home if you don't show me your invoices.”
That the contract between the parties contained no clause requiring disclosure of
the invoices went undisputed. Nor did anyone deny that Vaughn was contractually
obligated to furnish the Hamms with a “disbursement statement” each time he
requested a draw or payment. That statement was to contain the name and address of
each subcontractor or supplier that the builder intended to pay with the requested funds.
And, though it appears that Vaughn seldom if ever provided the Hamms such a
2 statement when he solicited a draw, Vaughn testified that the Hamms never requested
one.
The motivation behind Ace's demand for invoices was the subject of debate.
Ace suggested that he wanted to see if the subcontractors and suppliers were being
paid. Yet, the invoices themselves did not show that. And, as previously mentioned,
Ace never asked for a “disbursement statement” which would have identified those who
were to be paid. Moreover, the construction was proceeding as contemplated, and the
relationship between the parties was amicable until the invoices were demanded. Ace
also acknowledged that he encountered no instance of Vaughn omitting to pay any
supplier or subcontractor.
Nonetheless, Ace did complain to a third party that the job would have cost him
a “million dollars” if he “had not run (Vaughn) off the job,” though he cited no instance of
any cost overrun. Indeed, Vaughn testified that under a bid contract, any overruns were
his responsibility anyway; his customers were not charged for them. Ace also disclosed
to a witness that he “wanted to see all of the invoices . . . to see if . . . Vaughn was
charging him too much or having too much markup . . . .” Apparently, Ace thought
Vaughn was only entitled to a markup of ten to fifteen percent despite having executed
a bid, as opposed to a cost-plus contract. This same witness, who happened to be a
lawyer, also informed Ace that irrespective of what the cost of construction actually was,
Vaughn could only charge him the price specified in the contract.
As represented, Ace did bar Vaughn from completing the job because Vaughn
refused to deliver his invoices. And, within four days of doing so, Ace had his own
employees and subcontractors finishing the project; this incidentally contradicted his
3 own testimony that he waited several weeks before assuming the task. Additionally,
Ace completed the construction at a cost which was approximately $40,000 less than
the bid price he agreed to pay Vaughn. But, despite having saved money, he sued
Vaughn for damages, fraud, and deceptive trade practices.
The law provides that a material breach of contract by one party relieves the
other from performing. PAJ, Inc. v. Hanover Ins. Co., 243 S.W.3d 630, 633 (Tex. 2008).
Of course, the breach may be excused. Hanks v. GAB Bus. Servs., Inc., 644 S.W.2d
707, 708 (Tex. 1982). And, if it is, then the non-breaching party must perform his
obligations. Id.
Here, the jury found that both the Hamms and Vaughn “fail[ed] to comply with the
agreement,” that the Hamms failed to do so first, and that their failure was not excused
but that of Vaughn was. These findings could be reasonably based upon the above
recitation of the evidence. Indeed, a rational juror could reasonably infer from it that
Ace cared not that he accepted a bid contract, that he agreed to pay a set price for the
house, or that Vaughn provided no “disbursement statements” when seeking periodic
payment. Jurors could also infer from the evidence that Ace did not actually care about
whether the suppliers or subcontractors were being paid. Instead, they could have
reasonably deduced that he simply opted not to pay the sum agreed to and instigated
means to avoid that promise by unilaterally deriving some way to rid himself of Vaughn.
Simply put, the jury was free to discredit the veracity of Ace's testimony given that he
contradicted it himself at times and rejected his bona fides. After all, it heard about how
Ace sued Vaughn for damages even though less was spent on completing the house
than the sum he bound himself to pay. Dunn v. Bank-Tec. South, 134 S.W.3d 315, 324
4 (Tex. App.–Amarillo 2003, no pet.) (stating that jurors are free to choose who to believe
and disbelieve). Finally, reasonable minds could also deduce that one party to a
contract that illegitimately prevents another from performing materially breaches the
accord. Case Corp. v. Hi-Class Business Systems of America, Inc., 184 S.W.3d 760,
770 (Tex. App.–Dallas 2005, pet. denied) (stating that a party to a contract implicitly
obligates himself not to interfere with the other's performance); Mustang Pipeline Co. v.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Ace Hamm & Dana Hamm v. Steve Vaughn, Individually and D/B/A Vaughn Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-hamm-dana-hamm-v-steve-vaughn-individually-and-texapp-2010.