ACCURATE CONSTRUCTION COMPANY, INC. v. Dobbs Houses, Inc.

269 S.E.2d 494, 154 Ga. App. 605, 1980 Ga. App. LEXIS 2308
CourtCourt of Appeals of Georgia
DecidedMay 13, 1980
Docket59467
StatusPublished
Cited by7 cases

This text of 269 S.E.2d 494 (ACCURATE CONSTRUCTION COMPANY, INC. v. Dobbs Houses, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACCURATE CONSTRUCTION COMPANY, INC. v. Dobbs Houses, Inc., 269 S.E.2d 494, 154 Ga. App. 605, 1980 Ga. App. LEXIS 2308 (Ga. Ct. App. 1980).

Opinion

Sognier, Judge.

Dobbs Houses, Inc. leased certain real property to Hutch Enterprises, Inc. Under the terms of the lease Hutch was required to make improvements to the real property, pay the cost therefor and thereafter operate a restaurant on the premises. Under specific provisions of the lease, Hutch was not to allow the filing of liens against the property; it was required to discharge any lien at its cost; and lastly, Dobbs Houses could cancel the lease if liens were filed. Hutch contracted with Accurate Construction Co., Inc. for improvements on the leased property, failed to pay for same and went bankrupt. Upon these occurrences Accurate filed a lien against the real estate and seeks in this action to have this lien declared a special lien against the property of Dobbs Houses. Dobbs Houses moved for summary judgment and the lower court granted its motion; Accurate appeals, contending the trial court erred in granting summary judgment to Dobbs Houses.

No contract is alleged or claimed between Accurate and Dobbs Houses. A contract for improvements between a lessee and a materialman does not subject the interest of the lessor to a lien unless a contractual relationship exists between the lessor and the materialman as well. Capital Mechanical, Ltd. v. Dobbs Houses, Inc., 151 Ga. App. 142 (259 SE2d 147) (1979). No express or implied consent of Dobbs Houses to the contract for improvements appears. Mere knowledge by the lessor of the improvements does not give rise to the lien. Stevens Supply Co. v. Stamm, 41 Ga. App. 239 (152 SE 602) (1930).

Judgment affirmed.

Deen, C. J., and Birdsong, J., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F & D Electrical Contractors, Inc. v. Powder Coaters, Inc.
567 S.E.2d 842 (Supreme Court of South Carolina, 2002)
Anatek, Inc. v. CSX Realty Development, LLC
532 S.E.2d 115 (Court of Appeals of Georgia, 2000)
D & N Electric, Inc. v. Underground Festival, Inc.
414 S.E.2d 891 (Court of Appeals of Georgia, 1991)
F. S. Associates, Ltd. v. McMichael's Construction Co.
399 S.E.2d 479 (Court of Appeals of Georgia, 1990)
NUNLEY CONTRACTING COMPANY, INC. v. Four Taylors, Inc.
384 S.E.2d 216 (Court of Appeals of Georgia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
269 S.E.2d 494, 154 Ga. App. 605, 1980 Ga. App. LEXIS 2308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/accurate-construction-company-inc-v-dobbs-houses-inc-gactapp-1980.