Accident Prevention Division v. Stadeli Pump & Construction, Inc.

525 P.2d 170, 18 Or. App. 357, 1974 Ore. App. LEXIS 977
CourtCourt of Appeals of Oregon
DecidedAugust 12, 1974
StatusPublished
Cited by5 cases

This text of 525 P.2d 170 (Accident Prevention Division v. Stadeli Pump & Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Accident Prevention Division v. Stadeli Pump & Construction, Inc., 525 P.2d 170, 18 Or. App. 357, 1974 Ore. App. LEXIS 977 (Or. Ct. App. 1974).

Opinions

THORNTON, J.

This is an administrative appeal which arises out of a Citation and Notice of Proposed Penalty issued by the Accident Prevention Division (APD) of the Workmen’s Compensation Board concerning an [360]*360alleged violation, by Stadeli Pump and Construction, Inc. (Stadeli), of a provision of the Oregon Safety Code. The code was promulgated pursuant to the provisions of the Oregon Safe Employment Act, ORS 654.071. Among other things the code requires that all trenches over four feet in depth be shored to prevent eave-in accidents.

Stadeli appeals, seeking relief from an order by a referee of the Hearings Division of the Workmen’s Compensation Board, affirming the above citation and approving and assessing a penalty of $200 against Stadeli.

The alleged violation was described in the citation as follows:

“There is 1600 feet of trench that is from four (4) to fourteen (14) feet in depth at eleven (11) locations on the job site that is not shored or the sides sloped to the angle of repose.”

The issue before this court is whether the order of the APD and the referee is (1) lawful in substance and procedure and (2) supported by “reliable, probative and substantial evidence in the whole record * * ORS 183.480 (7).

Stadeli contends that the order of the Hearings Division is invalid for the following reasons:

(1) The hearing officer failed to consider evidence that Stadeli’s subcontractor had control and responsibility for carrying out that portion of the project work involving installation of eight-inch lateral pipe, and where part of the violation allegedly occurred; and

(2) There was no evidence that the portion of the project (the main trench) over which Stadeli contends it had exclusive control was an unshored trench [361]*361where employes were currently working or where employes would be working at some future time without benefit of shoring in violation of pertinent safety code provisions.

The essential facts are: Stadeli was engaged in installing sewer lines and manholes on a project near Albany, Oregon. The president of Stadeli testified that the firm of “Lord Brothers” was the general contractor on the project; that “Lord Brothers” had subcontracted a portion of the sewer work to Stadeli ; and that Stadeli in turn subcontracted a portion of its work to Marvin Ferris. The job involved the installation of a main-line or trunk sewer and a network of lateral lines. The trunk sewer line was 12-ineh pipe, 1,900 feet long. The lateral lines were of three smaller sizes: four-inch, six-inch and eight-inch pipe. The work also included the installation of concrete manholes where the lateral lines joined the trunk line.

Stadeli excavated its trenches for the system with a power backhoe. The soil throughout the site was hard-packed clay. The sides of the trench were vertical. All the trenches were approximately 30 inches in width. The main trench varied in depth from 14 feet to 19% feet. The manhole excavations were 9 feet wide by 10 feet long, and were as deep as the main trench. The lateral trenches were shallower. Stadeli used hand labor in laying all the pipe and in setting, with grout, the. concrete manholes.

On August 27, 1973, a field inspector for the APD inspected the site. He was accompanied on his inspection by Marvin Stadeli, who was superintendent on the job. Mr. Stadeli identified the work being done by his firm. Together the two men measured the depths [362]*362of the excavation in the various parts of the project. According to the testimony Marvin Stadeli made no mention at this time of the existence of any subcontract.

Stadeli was then in the final stages of the job. All the excavating had been done. The 12-ineh pipe in the main line had been laid. The four-inch pipe and the six-inch pipe had been laid. Some, but not all, of the eight-inch pipe had been laid. Portions of the trenches had been backfilled with gravel; other sections were being backfilled on that day. The concrete manholes were still to be installed. The remainder of the main trench could not be backfilled until the manholes were in place, which in turn required the completion of the laying of the eight-inch laterals.

At the time of the inspection on August 27, some 1,600 feet of trench remained, all greater in depth than four feet, which had not been backfilled. There was no shoring in any of the trenches or manhole excavations. No shoring was in evidence at the job site. Shoring had been used earlier, however, during the installation of the 12-inch trunk line. It was moved forward progressively as the 12-ineh pipe was laid. The inspector testified that he saw this shoring in use during an earlier inspection on July 27. There was no evidence that shoring had been used in the lateral trenches for the eight-inch pipe, and Marvin Stadeli acknowledged this fact during his testimony at the hearing.

The inspector observed no workmen in the trenches during his inspection. There was, however, hand labor still to be done in the trenches in laying the remainder of the eight-inch laterals, in hooking them up with the concrete manholes and in setting the manholes.

[363]*363There was testimony that two days previously, on August 25, Marvin Stadeli and his brother had worked in lateral trenches which were not shored, and that at some time immediately prior to August 27 another Stadeli employe had worked in an unshored section, spreading backfilled gravel.

Stadeli makes no contention that “Lord Brothers,” the general contractor, has any legal responsibility as to any of the alleged violations involved here.

We begin our analysis by noting that the Oregon Safe Employment Act places the burden of providing a safe place of employment on the employer. ORS 654.010.

ORS 654.005 (3) defines “employe” as

“* * * any individual, including a minor whether lawfully or unlawfully employed, who engages to furnish his services for a remuneration, financial or otherwise, subject to the direction and control of an employer, and includes * * * any individual who is provided with workmen’s compensation coverage as a subject workman pursuant to ORS chapter 656, whether by operation of law or by election.”

ORS 654.005 (4) defines “employer” as

“* * * any person who has one or more employes, or any sole proprietor or member of a partnership who elects workmen’s compensation coverage as a subject workman pursuant to ORS 656.128.”

We can find nothing in the Act to provide us with any specific indication of legislative intent concerning who is liable for compliance with job safety laws when one employer subcontracts part of a project to a subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oregon Occupational Safety & Health Division v. Moore Excavation, Inc.
307 P.3d 510 (Court of Appeals of Oregon, 2013)
Leupold & Stevens, Inc. v. City of Beaverton
138 P.3d 23 (Court of Appeals of Oregon, 2006)
Flores v. Metro MacHinery Rigging, Inc.
783 P.2d 1024 (Court of Appeals of Oregon, 1989)
Hoskinson v. Public Employes Retirement Board
542 P.2d 157 (Court of Appeals of Oregon, 1975)
Accident Prevention Division v. North American Contractors, Inc.
540 P.2d 391 (Court of Appeals of Oregon, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
525 P.2d 170, 18 Or. App. 357, 1974 Ore. App. LEXIS 977, Counsel Stack Legal Research, https://law.counselstack.com/opinion/accident-prevention-division-v-stadeli-pump-construction-inc-orctapp-1974.