ACC Bldg. 1, LLC v. Texas Instruments Incorporated

CourtDistrict Court, D. Massachusetts
DecidedAugust 19, 2019
Docket4:16-cv-40011
StatusUnknown

This text of ACC Bldg. 1, LLC v. Texas Instruments Incorporated (ACC Bldg. 1, LLC v. Texas Instruments Incorporated) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACC Bldg. 1, LLC v. Texas Instruments Incorporated, (D. Mass. 2019).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

________________________________________________ ) ACC BLDG. 1, LLC, ) Plaintiff, ) ) ) ) CIVIL ACTION v. ) NO. 16-40011-TSH ) ) TEXAS INSTRUMENTS, INCORPORATED, ) Defendant. ) ________________________________________________)

ORDER August 19, 2019

Background

ACC Bldg. 1, LLC and ACC Bldg. 12 & 5, LLC (“Plaintiffs”)1 brought this action against Texas Instruments, Incorporated (“Defendant” or “TI”) seeking damages under Mass.Gen.L., ch. 21E (“Chapter 21E”), §5. Defendant has moved to dismiss the property claims asserted in Counts II, III and IV of the Plaintiffs’ First Amended Complaint pursuant to Fed. R. Civ. P. 12(b)(6) for

1 In the original Complaint, ACC Bldg. 1 a, LLC and ACC Bldg. 12 & 5, LLC were named as plaintiffs in both the caption and body of the pleading. The First Amended Complaint, while including both entities in the body of the pleading, names only ACC Bldg. 1, LLC in the caption, which is a violation of Fed.R.Civ.P. 10(a) (in complaint, title of action shall include all parties): see also Ware v. Gary Cmty. Sch. Corp., No. 2:15-CV-42-PRC, 2015 WL 6756870, at *4 (N.D. Ind. Nov. 4, 2015)(“Rule 10(a) applies not only to an original complaint but also to an amended complaint because an amended complaint supersedes the original complaint, rendering the original complaint of no legal effect.”) and cases cited therein. Plaintiffs shall have two weeks from the date of this Order to rectify this technical deficiency or the claims of ACC Bldg. 12 & 5, LLC shall be dismissed. failure to state a claim2. For the reasons stated below, the Renewed Motion to Dismiss For Failure To State A Claim Upon Which Relief Can Be Granted (Docket No. 38) is denied. Facts TI owned approximately 260 acres of land near Forest and Pleasant Streets and Perry Avenue in Attleboro, Massachusetts (the “Site”). The groundwater at the Site has been impacted

by a release of volatile organic compounds, primarily trichloroethylene (“TCE”). The site is a “disposal site” under the supervision of the Massachusetts Department of Environmental Protection (“DEP”). As a responsible party, TI has and continues to perform response actions under DEP’s Massachusetts Contingency Plan (“MCP”) regarding the release of TCE and other hazardous materials at the Site. In September 2001, TI submitted to DEP a Class C Response Action Outcome (“RAO”) Statement for a Temporary Solution. In accordance with the RAO, TI installed and operates a system for treating contaminated groundwater pumped from wells and collected from storm drains at the Site and continues to provide periodic review reports pursuant to the MCP.

In 2010, TI sold parcels from the Site to Plaintiffs. Included in those parcels are facilities which I will hereafter refer to as “Building #1” and “Building #5”. The entirety of the property purchased by the Plaintiffs shall hereafter be referred to as the “Property.” Neither Building #1 nor Building #5 was occupied, and Plaintiffs purchased the Property with full knowledge of the contaminated water-- the purchase price reflected the environmental problems. Plaintiffs purchased the Site with the caveat that TI would continue to perform response

2 In Counts I and V of its First Amended Complaint, Plaintiffs assert claims against the Defendant under Chapter 21E and 42 U.S.C. §§ 9601 et seq. (“CERCLA”) to recover alleged response action costs. TI does not seek dismissal of these claims. actions required by the MCP, including sampling and monitoring of groundwater and construction of a new groundwater treatment system. In 2013, DEP issued a new fact sheet detailing the Environmental Protection Agency’s (“EPA”) new TCE toxicity values and implications for chronic and short-term exposure to TCE, highlighting the hazards posed by TCE by vapor inhalation in occupied buildings. In March 2013,

DEP issued a revised fact sheet defining what concentrations of TCE in the air would pose an imminent hazard in occupied commercial buildings. In April 2013, Plaintiffs informed TI that based on their previous models, indoor air concentration of TCE in Buildings #1 and #5 would be more than 100 times DEP’s new action level. On November 21, 2013, DEP issued TI a Request for Immediate Response Action Plan for the soil gas and sub-slab soil gas samples collected in the previous periodic review reports. According to the soil gas sampling taken in March 2014, the TCE levels in Building #1 were above DEP’s threshold values for indoor air for commercial buildings. The April 2014 indoor air sampling for Building #1 showed levels of TCE above DEP’s imminent hazard standard for

indoor air if the building was occupied. Because Building #1 was not occupied, TI was not required by the MCP to conduct Immediate Response Actions to reduce concentrations or address these vapor intrusions. In Building #5, the March 2014 soil gas sampling showed levels above DEP’s threshold values for indoor air for commercial buildings. Additional indoor air sampling in October 2014 showed levels above the DEP threshold value for indoor air for commercial buildings, but below the imminent hazard standard for indoor air. In December 2014, Plaintiffs began negotiations with Sensata Technologies, Inc. (“Sensata”) to lease Building #1. As a result and pursuant to the MCP, TI began plans to renovate the building for occupancy, including plans to install a sub-slab depressurization system to control vapor conditions in the building and eliminate Imminent Hazard conditions. Sensata chose not to lease from Plaintiffs. Since the building was not going to be occupied, TI halted MCP compliance plans and installations required for occupancy. Plaintiffs claim the release of TCE vapor intrusions is the reason why they have been unable to lease Building #1 or Building #5. Standard of Review

To survive a Rule 12(b)(6) motion to dismiss, a complaint must allege “a plausible entitlement to relief.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 559, 127 S.Ct. 1955 (2007). The complaint “must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937 (2009). The standard “requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Twombly, 550 U.S. at 555, 127 S.Ct. 1955. The Court “must assume the truth of all well-plead[ed] facts and give the plaintiff the benefit of all reasonable inferences therefrom.” Rhodes v. Ocwen Loan Servicing, LLC, 44 F.Supp.3d 137, 139 (D.Mass. 2014) (quoting Ruiz v. Bally Total Fitness Holding Corp., 496 F.3d 1, 5 (1st Cir. 2007)). A claim is

facially plausible if the factual content ‘allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Iqbal, 550 U.S. at 665, 129 S.Ct. 1937. Discussion TI asserts, generally, that through this action, Plaintiffs, who knowingly bought contaminated property, seek to unfairly shift to TI the consequences of this business decision, which they now regret.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Ruiz v. Bally Total Fitness Holding Corp.
496 F.3d 1 (First Circuit, 2007)
Rhodes v. Ocwen Loan Servicing, LLC
44 F. Supp. 3d 137 (D. Massachusetts, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
ACC Bldg. 1, LLC v. Texas Instruments Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acc-bldg-1-llc-v-texas-instruments-incorporated-mad-2019.