A&C Construction & Installatio v. Zurich American Insurance Com

Procedural entryThis page is a short order in A&C Construction & Installatio v. Zurich American Insurance Com. Read the opinion of the Court — 963 F.3d 705
Court of Appeals for the Seventh Circuit·Decided June 30, 2020·No. 19-3325·Published

Opinion

In the

United States Court of Appeals For the Seventh Circuit

No. 19-3325 A&C CONSTRUCTION & INSTALLATION, CO. WLL, Plaintiff-Appellant,

v.

ZURICH AMERICAN INSURANCE COMPANY and THE INSURANCE COMPANY OF THE STATE OF PENNSYLVANIA, Defendants-Appellees.

Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 17-cv-04307 — Harry D. Leinenweber, Judge.

ARGUED MAY 26, 2020 — DECIDED JUNE 30, 2020

Before FLAUM, SCUDDER, and ST. EVE, Circuit Judges. ST. EVE, Circuit Judge. The Miller Act, 40 U.S.C. § 3131 et seq., seeks to protect subcontractors against nonpayment for work performed on federal government construction projects by requiring the prime contractor to provide a payment bond on which the subcontractor can then make a claim for payment . A&C Construction & Installation, Co. WLL was a subcontractor on an air base project in Qatar and claims that it 2 No. 19-3325

was not paid approximately $8.5 million for work it performed on the project, so it filed this action against the prime contractor’s two sureties, Zurich American Insurance Company and The Insurance Company of the State of Pennsylvania . As strict preconditions to payment, however, the Miller Act requires that subcontractors provide a notice of nonpayment within ninety days after the last day of work performed and then file suit within one year of the last date of work. The district court found that A&C missed both deadlines and granted summary judgment in favor of the sureties. Because A&C did not meet the Miller Act’s notice requirement, we affirm the judgment.

I. Background

This dispute arises from a federal construction project with the United States Army Corps of Engineers for the construction of two billets on the Al Udeid Air Base in Qatar. The Miller Act provides that on any contract of more than $100,000 for “the construction, alteration, or repair of any public building or public work of the Federal Government” the contractor must supply “[a] payment bond with a surety satisfactory to the officer for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person.” 40 U.S.C. § 3131(b)(2). Amec Foster Wheeler Environment & Infrastructure , Inc., was the prime contractor on the Qatar air base project . As such, Amec Foster Wheeler, as principal, and defendants Zurich American Insurance Company and The Insurance Company of the State of Pennsylvania, as sureties, executed and delivered to the Army Corps the required payment bond.

Amec Foster Wheeler awarded certain work on the project to a subcontractor, Black Cat Engineering & Construction

No. 19-3325 3

WLL—first mechanical work and later additional fire suppression work. Black Cat, in turn, subcontracted with A&C for some of that work. A&C, therefore, was the sub-subcontractor or second-tier subcontractor on the project. On January 31, 2013, Black Cat and A&C entered into a contract for A&C to perform portions of the mechanical, electrical, and plumbing services that Amec Foster Wheeler awarded to Black Cat (the “MEP Agreement”). On July 1, 2013, Black Cat and A&C entered into a second contract for A&C to perform portions of the fire suppression work awarded to Black Cat (the “Fire Suppression Agreement”). Together, the work for these two contracts forms the basis of this lawsuit.

A&C later subcontracted some of the ductwork under the MEP Agreement to Raymond Nahra for Electrical & Mechanical Works Co., W.L.L. (“RNC”). Thus, on the project, RNC was a third-tier subcontractor. From all accounts, RNC performed work on the project through the project’s completion date in February 2017.

The relationship between Black Cat and A&C eventually deteriorated. On December 16, 2015, Black Cat terminated A&C from the Fire Suppression Agreement. The sureties contend that A&C had already stopped most of its work related to the MEP Agreement in November 2015 and that A&C last performed any work on the project on May 16, 2016. A&C disputes this characterization, primarily as it relates to the date it last performed any work on the project. Specifically, A&C insists that, despite the termination, it continued to provide labor and equipment after that date because its equipment remained on the site for Black Cat’s use, and it continued to provide supervision of one of its subcontractors (RNC) through the project’s completion on February 28, 2017. Accordingly, 4 No. 19-3325

A&C asserts that the date it last performed labor or supplied material for the project was February 28, 2017.

It is undisputed, however, that A&C provided its notice under the Miller Act on August 16, 2016. That notice claimed that Black Cat owed A&C $8,449,710 for “Mechanical, Electrical and Plumbing and Fire Suppression works.” As to the “[d]ate on which the last of the labor, services, equipment or materials were furnished,” A&C stated that “[c]ertain A&C equipment remains onsite.”

A&C filed its complaint on June 7, 2017, alleging a single Miller Act claim against the sureties for payment on the bond in the amount of $8,637,423. After discovery, the sureties moved for summary judgment, arguing that A&C’s last day of work was—at the latest—May 16, 2016. The notice date, August 16, 2016, is ninety-one days after May 16, 2016, and outside of the mandatory ninety-day notice period. A&C also did not file suit until June 7, 2017, more than one year after the sureties allege A&C last provided labor or material on the project. A&C disputed the May 16, 2016, date and instead argued that it leased equipment to Black Cat that was utilized on the project up until its conclusion on February 28, 2017, and its subcontractor RNC also continued to provide labor until the completion date. Thus, A&C countered, it filed the lawsuit within one year of that date. Further, as to the fact that its Miller Act notice was served far more than ninety days before its alleged last day of work, A&C simply argued that it “provided too much notice” and there was nothing that barred it from providing the notice earlier than required.

The district court granted the sureties’ motion for summary judgment. The court found that even if A&C was able to use leased equipment to Black Cat as its claimed last day of

No. 19-3325 5

work performed as a legal matter, the argument still failed because A&C did not provide notice “within 90 days” of that date (February 28, 2017). As to the “too much notice” argument , the district court similarly rejected it because it did “not meet with the requirement that the limitations periods constitute conditions precedent and are to be strictly construed.”

Based on some admitted misstatements in the district court’s opinion, A&C filed a post-judgment motion pursuant to Federal Rule of Civil Procedure 59(e) to alter or amend the judgment, alleging that the decision rested on “a manifest error of fact.” In three places, the opinion erroneously stated that A&C did not file its complaint within one year of its Miller Act notice. (E.g., “If Plaintiff is to rely upon its 90-day notice , then it needed to bring suit with one year or by August 19, 2017 [sic] …. It did not do so. In fact, its Complaint, which was filed on June 7, 2017, ….”). But A&C in fact had—the notice date was August 16, 2016, and the lawsuit was filed ten months later on June 7, 2017. The problem for A&C, though, is that the one-year limitation does not run from the notice date. Both the notice period and lawsuit period run from the last day of claimed work. So the district court’s miscalculated time period was irrelevant.

Free access — add to your briefcase to read the full text and ask questions with AI

A&C Construction & Installatio v. Zurich American Insurance Com, (7th Cir. 2020).

A&C Construction & Installatio v. Zurich American Insurance Com (A&C Construction & Installatio v. Zurich American Insurance Com) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related