Abrams v. City of Seattle

23 P.2d 869, 173 Wash. 495, 1933 Wash. LEXIS 656
CourtWashington Supreme Court
DecidedJuly 13, 1933
DocketNo. 24116. En Banc.
StatusPublished
Cited by14 cases

This text of 23 P.2d 869 (Abrams v. City of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abrams v. City of Seattle, 23 P.2d 869, 173 Wash. 495, 1933 Wash. LEXIS 656 (Wash. 1933).

Opinions

Blake, J.

This action was brought to enjoin the defendants from issuing warrants on the light department construction fund, in the amount of $189,000, in favor of certain persons who advanced money, performed labor and furnished material in connection with the construction of a substation on property owned by the city, and located on Third avenue, between Madison and Spring streets. After issue joined, and trial had, the court entered judgment dismissing the action. From this judgment, plaintiff appeals.

On and prior to January 21, 1930, the city was the owner of the entire half block fronting on Third av- *497 eime between Madison and Spring streets. It had begun the acquisition of this tract in 1925, with the purpose of erecting a substation thereon in connection with the extension and improvement of its light and power system. The original plan contemplated the erection by the city of a building of two or three stories and basement, in which could be housed machinery and equipment of a substation, and in which could be consolidated the various offices of the light and power department — the latter being scattered among three different buildings. For reasons which seemed expedient to the city council, this plan was not carried out. A plan was evolved to erect upon the property a twenty-four story building. It is the attempt to carry this plan into effect that gives rise to this litigation.

The method used to carry out the plan was quite complicated. We do not think, however, it is necessary to pursue it step by step. For the purpose of disposing of the questions here raised, it will suffice to give a general outline of the plan.

On January 21, 1930, the city council, by ordinance, authorized a lease of the property, under terms therein specifically set out, to be entered into with one L. A. DeCou for a term of fifty years. There was no rent reserved in the lease. The consideration to the city was the erection by DeCou of a twenty-four story building on the property, the basement and subbasement of which was to belong to the city. From the Third avenue level up, the building was to belong to DeCou for the term of his lease, at the expiration of which that portion of the building would also become the property of the city. Under the terms of the lease, DeCou acquired no rights in the ground. It was provided that no liens should attach to the ground or to the basement or subbasement.

*498 In other words, the city Was to get its substation erected without cost to it, in consideration to DeCou of the right to erect over it a superstructure twenty-four stories in height. In addition, the city reserved the right to occupy certain portions of the superstructure at specified rentals. The lease fixed the time limit for the erection of the entire building at eighteen months from the date of execution of the lease, and provided for forfeiture in case it was not so completed. The expiration of the time for the completion of the building would have occurred October 28,1931.

DeCou was without sufficient means to carry out the enterprise, so a group of persons who were interested in seeing it consummated, organized a corporation known as the City Light Building Company. This corporation was also without means, but it took an assignment of the lease, having in mind the construction of the building by financing arrangements much in vogue at, and prior to, that time.

Arrangements were made with a St. Louis house to loan $1,250,000 on a structure to cost approximately $1,750,000. This arrangement was conditioned, however, upon the building company first arranging for the balance of the financing. In other words, before the St. Louis people would be obligated to advance any money, the building company must have an investment of $500,000 to $600,000 in the building. This secondary financing was arranged for with a savings and loan association of Portland. This contemplated the issuance of preferred stock by the building company, of the par value of one hundred dollars, which would be sold at eighty dollars per share to the savings and loan association, and passed on by it to Seattle investors at one hundred dollars per share.

These arrangements made, contracts were let for the construction of the building, and work was com *499 menced on October 24, 1930. All went well until the spring of 1931, when the savings and loan association failed to advance money on the preferred stock. In the meantime, however, preferred stock had been sold by it to investors in the amount of $105,000. The building company had received from the savings and loan association an amount in excess of that, all of which went into the structure which now stands on the property.

Construction work ceased on or about April 26,1931. At that time, the basement and subbasement were practically completed. According to the testimony, it would require an expenditure of less than $8,000 to make it ready for occupancy as a substation — the purpose, it is to be remembered, for which the property was originally acquired.

Subsequent to April 24, the building company endeavored to make other arrangements for financing, but was unable to do so in time to complete the building by October 28, 1931, the time limited by the lease. The building company wanted an extension of time for the completion of the building; and its officers assert,, with some show of probability, that new arrangements for financing could have been made, had such extension been given by the city and approved by the court. The city, however, preferred to abandon the entire enterprise, but it was willing to pay the building company the reasonable value of the structure the latter had placed upon the property. The building company claimed the improvement was worth $235,000. The city appraised it at $189,000, and there is no evidence that it is not worth at least that much.

So we have this situation: The building company has erected on the city’s property a building worth $189,000, which has cost the city not a cent, but for which it is willing to pay, and for which it, in good *500 conscience, ought to pay. To that end, the building company made a written proposal to the city to assign to the latter its lease for $189,000, and furnish certificate showing good title in the city, free of all liens and encumbrances whatsoever. (In passing, it should be noted that liens in excess of $130,000 had been filed against the property.) The city accepted the proposal, and undertook to carry it out by the passage of ordinance No. 61,679. By this ordinance, it appropriated from the city light construction fund $189,000 for that purpose; and authorized the issuance of warrants aggregating that amount to various lien claimants and bona fide purchasers of the preferred stock of the City Light Building Company.

The appellant contends that the city has no power to issue warrants for such purpose or to such persons. Counsel’s argument in support of the contention may be divided under two heads: (1) That the lease to DeCou was ultra vires

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. O'CONNELL
523 P.2d 872 (Washington Supreme Court, 1974)
Shafer v. State
521 P.2d 736 (Washington Supreme Court, 1974)
Finch v. Matthews
443 P.2d 833 (Washington Supreme Court, 1968)
Edwards v. City of Renton
409 P.2d 153 (Washington Supreme Court, 1965)
Warburton v. Tacoma School District No. 10
350 P.2d 161 (Washington Supreme Court, 1960)
State Ex Rel. Russell County v. Fourth National Bank
117 So. 2d 145 (Supreme Court of Alabama, 1959)
Christie v. the Port of Olympia
179 P.2d 294 (Washington Supreme Court, 1947)
School Dist. No. 37, Clark County v. Isackson
92 F.2d 768 (Ninth Circuit, 1937)
State Ex Rel. Washington Navigation Co. v. Pierce County
60 P.2d 16 (Washington Supreme Court, 1936)
State Ex. Rel. Wash. Nav. Co. v. Pierce County
51 P.2d 407 (Washington Supreme Court, 1935)
Gehr v. Ferry County
36 P.2d 71 (Washington Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
23 P.2d 869, 173 Wash. 495, 1933 Wash. LEXIS 656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abrams-v-city-of-seattle-wash-1933.