Abramowski v. Wm. Kilps Sons Realty, Inc.

259 N.W.2d 306, 80 Wis. 2d 468, 1977 Wisc. LEXIS 1209
CourtWisconsin Supreme Court
DecidedNovember 1, 1977
Docket75-418
StatusPublished
Cited by18 cases

This text of 259 N.W.2d 306 (Abramowski v. Wm. Kilps Sons Realty, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abramowski v. Wm. Kilps Sons Realty, Inc., 259 N.W.2d 306, 80 Wis. 2d 468, 1977 Wisc. LEXIS 1209 (Wis. 1977).

Opinion

DAY, J.

This is an appeal from an order dated September 9, 1975, sustaining a demurrer to the complaint. The plaintiff, Mr. Harold Abramowski, alleged that the defendant, Wm. Kilps Sons Realty, Inc., contracted with Irma F. Zerneeke and her late husband to design and build a single family residence for them at Franksville, Racine County. According to the complaint, it was understood between the Zerneckes and the defendant that in the construction of the house, defendant was to exercise “ordinary care” or “the same degree of care exercised by similar building contractors” in the vicinity. The contract was made in March of 1962 and the house was completed by the defendant in the fall of 1962.

Plaintiff alleged that the defendant builder negligently constructed the dwelling in that no drainage tiles were placed along the north walls, various bleeder tiles were blocked by concrete, other bleeder tiles were inadequately *471 spaced, no stone was laid over the tile system around the home and the home was constructed over an unsuitable and inadequate soil base. The plaintiff further alleges that the defendant knew or should have known of such negligent construction and could have constructed the house so as to prevent the damages complained of.

The plaintiff purchased the house from Mrs. Zernecke in November 1971. Plaintiff alleges that as a result of the defendant’s negligence, in 1974 the basement walls and foundation cracked and caved in and damaged other parts of the house.

The defendant demurred to the complaint on the ground that under sec. 893.19(3) and 893.19(5), Stats. 1 the six year statute of limitations had run.

The questions raised are:

1. Is either sec. 893.19(3), Stats, or sec. 893.19(5), Stats, the proper statute of limitations governing a claim alleging negligent design and construction of a residential building?

2. When does the statute of limitations on a claim of negligent design and construction of a residential building begin to run?

Plaintiff argues that the statute that was meant to apply, sec. 893.155, 2 Stats. (1973) was declared un *472 constitutional in Kallas Millwork Corp. v. Square D Co., 66 Wis.2d 382, 225 N.W.2d 454 (1974), and thus there is no statute of limitations for actions concerning' improvements to real property. 3 The plaintiff contends that sec. 893.19(3) and (5), Stats, do not control because they are more general in scope and cannot take precedence over sec. 893.155, Stats, which applied specifically to to improvements to real property.

The defendant builder originally based its demurrer on sec. 893.19(3) and (5), Stats.

Sec. 893.19(3), Stats, applies to an action based on a contractual obligation but there is no claim of a contract between plaintiff and the defendant since the complaint states the contract was between defendant and the Zerneckes. Thus 893.19(3) would not apply. There is no mention in this complaint that the plaintiff was a party to the contract between the Zerneckes and the defendant. The plaintiff can not base his claim on that contract because a contract can not be enforced by a person not a party to it. State Dept. of Public Welfare v. Schmidt, 255 Wis. 452, 39 N.W.2d 392 (1949); Williams v. Eggleston, 170 U.S. 304, 309, 18 S. Ct. 617, 619, 49 L. Ed. 1047 (1898). 4 Sec. 893.19(3), Stats, does not *473 apply because the plaintiff does not have an enforceable contract claim. 5

Sec. 893.19(5), Stats, applied to actions involving improvements to real property before sec. 893.155, Stats, became law and we hold it applies here since the latter section had been declared unconstitutional. Sec. 893.155, Stats, was created by Ch. 412 of the Laws of 1961. Sec. 893.19(5), Stats, antedated it, appearing in its present form in Ch. 435, Laws of 1957.

The prior sec. 330.19(5), Stats., which was similar to sec. 893.19(5), was found applicable to a claim involving an improvement to real estate in School District v. Kunz, 249 Wis. 272, 24 N.W.2d 598 (1946); In Hartford Fire Ins. Co. v. Osborn Plumbing, 66 Wis.2d 454, 225 N.W.2d 628 (1975), the defendant raised sec. 893.155, Stats, as a bar to a claim for damages caused by a defective heater installed by one of the defendants. The trial court declared sec. 893.155, Stats, unconstitutional and applied sec. 893.19(5), Stats. This court agreed that sec. 893.155, Stats, was unconstitutional citing Kallas, supra, and discussing the case in terms of sec. 893.19(5), Stats.

The plaintiff’s second argument is that the six year statute of limitations does not begin to run until “. . . a cause of action has accrued” 6 and that no cause of action accrued until the plaintiff suffered damage in 1974 when his basement walls caved in. Previous eases of this court support that position.

*474 “A cause of action accrues where there exists a claim capable of present enforcement, a suable party against whom it may be enforced, and a party who has a present right to enforce it.” 7

In School District v. Kunz, supra, the plaintiff school district sued for the cost of a retaining wall necessitated by the defendant’s excavation that removed lateral support from the plaintiff’s land. The applicable statute of limitations 8 was six years. The action was commenced more than six years from the time of excavation, but less than six years from the time the damage to the plaintiff’s land occurred. Both the trial court and this court found that the time of completion of the excavation was not material and that the action was not barred. “The statute did not begin to run until the respondent suffered an injury.” 9

In Hartford Fire Insurance Co. v. Osborn Plumbing, 66 Wis.2d 454, 225 N.W.2d 628 (1975), a building was fire damaged because of a faulty heater. The building’s insurer brought a subrogation suit against the architect, the heater manufacturer, the installer and a maintenance man.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Design Basics, LLC v. Best Built, Inc.
223 F. Supp. 3d 825 (E.D. Wisconsin, 2016)
Kontowicz v. American Standard Insurance Co. of Wisconsin
2006 WI 48 (Wisconsin Supreme Court, 2006)
MacIolek v. Mers
2006 WI 10 (Wisconsin Supreme Court, 2006)
Estate of Plautz v. Time Ins. Co.
525 N.W.2d 342 (Court of Appeals of Wisconsin, 1994)
Goossen v. Estate of Standaert
525 N.W.2d 314 (Court of Appeals of Wisconsin, 1994)
State Ex Rel. Journal/Sentinel, Inc. v. Pleva
456 N.W.2d 359 (Wisconsin Supreme Court, 1990)
Young Radiator Co. v. Celotex Corp.
881 F.2d 1408 (Seventh Circuit, 1989)
Lamb v. Manning
427 N.W.2d 437 (Court of Appeals of Wisconsin, 1988)
Wisconsin Natural Gas Co. v. Ford, Bacon & Davis Construction Corp.
291 N.W.2d 825 (Wisconsin Supreme Court, 1980)
Cubito v. Kreisberg
69 A.D.2d 738 (Appellate Division of the Supreme Court of New York, 1979)
Crawford v. Shepherd
272 N.W.2d 401 (Court of Appeals of Wisconsin, 1978)
Tallmadge v. Skyline Construction, Inc.
272 N.W.2d 404 (Court of Appeals of Wisconsin, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
259 N.W.2d 306, 80 Wis. 2d 468, 1977 Wisc. LEXIS 1209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abramowski-v-wm-kilps-sons-realty-inc-wis-1977.