Abra Construction Corp. v. White Street Development Associates, L. L. C.
This text of 272 A.D.2d 138 (Abra Construction Corp. v. White Street Development Associates, L. L. C.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
—Orders, Supreme Court, New York County (Alice Schlesinger, J.), entered February 4 and February 14, 2000, [139]*139which reduced the amount of the mechanic’s lien filed by plaintiff to $64,889.12, unanimously modified, on the facts, to adjust the amount to $68,909.12, and otherwise affirmed, without costs.
The amount claimed in plaintiffs lien was obviously excessive since the contract admittedly was only 35% performed (Lien Law § 9 [4]). The revised amount that plaintiff then claimed, in response to the court’s order to submit a statement of “actual labor performed and materials delivered,” improperly included retainage, which under the parties’ contract was not due until the project was substantially completed, site supervision, which was covered under the General Conditions portion of the parties’ contract and should not have been separately stated, and work that plaintiff allegedly performed after defendant allegedly directed it to stop.
We modify simply to correct an apparent arithmetic error. Concur — Sullivan, P. J., Rosenberger, Ellerin, Lerner and Friedman, JJ.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
272 A.D.2d 138, 708 N.Y.S.2d 853, 2000 N.Y. App. Div. LEXIS 5419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abra-construction-corp-v-white-street-development-associates-l-l-c-nyappdiv-2000.