ABL Plumbing & Heating Corp. v. Bladen County Board of Education

623 S.E.2d 57, 175 N.C. App. 164, 2005 N.C. App. LEXIS 2728
CourtCourt of Appeals of North Carolina
DecidedDecember 20, 2005
DocketCOA05-14
StatusPublished
Cited by8 cases

This text of 623 S.E.2d 57 (ABL Plumbing & Heating Corp. v. Bladen County Board of Education) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ABL Plumbing & Heating Corp. v. Bladen County Board of Education, 623 S.E.2d 57, 175 N.C. App. 164, 2005 N.C. App. LEXIS 2728 (N.C. Ct. App. 2005).

Opinion

McGEE, Judge.

ABL Plumbing & Heating Corporation (plaintiff) entered into a contract with the Bladen County Board of Education (the Board of Education) on 15 December 1999. Under the contract, plaintiff agreed to perform plumbing work on the East Bladen High School construction project (the project) for the Board of Education. Sigma Construction Company (Sigma) was the original general contractor for the project. Shuller Ferris Lindstrom & Associates (Shuller) was the architect for the project and the Board of Education’s representative throughout the project.

Sigma filed a petition in bankruptcy and defaulted on its obligations as general contractor on 1 March 2001. The Board of Education declared Sigma to be in default in April 2001. Plaintiff continued to work on the project through 13 April 2001, when the Board of Education halted work on the project. Plaintiff submitted its first claim to the Board of Education on 24 April 2001 in the amount of $223,252.37. The claim was for damages allegedly suffered as a result of Sigma’s default and was to be submitted to Sigma’s surety. Plaintiff did not receive a response to its claim.

The Board of Education directed plaintiff to resume work on the project on 11 June 2001. However, plaintiff informed the Board of *166 Education on 18 June 2001 that it would not resume work until issues concerning “the job completion date, schedule and change order amount for damages incurred” by plaintiff were resolved by the Board of Education or by Sigma’s surety.

Plaintiff and the Board of Education entered into a remobilization agreement on 31 July 2001. The remobilization agreement stated that “[plaintiff] intended] to file a claim against [the Board of Education] regarding the alleged damages” incurred by plaintiff “as a result of Sigma’s default on the [p]roject and the subsequent suspension of work.” Paragraph seven of the remobilization agreement specified that if plaintiff wished to pursue a claim related to Sigma, it would submit a formal claim to the Board of Education by 31 August 2001. The remobilization agreement also provided that “[t]his agreement shall not be construed as a release of any claims or defenses [the Board of Education] and [plaintiff] have or may have in the future relating to damages incurred on the [p]roject.” Plaintiff resumed work on the project in August 2001.

Plaintiff submitted a second claim to the Board of Education in the amount of $261,456.83, on 31 August 2001. The amount of plaintiff’s 31 August 2001 claim differed in amount from the 24 April 2001 claim. However, the categories of the damages in the two claims were the same. The Board of Education rejected plaintiff’s second claim on 28 September 2001.

Plaintiff filed a complaint on 26 August 2003 alleging various claims against the Board of Education and Shuller. However, plaintiff voluntarily dismissed its claims against Shuller on 28 October 2004.

Plaintiff alleged the Board of Education breached its contract with plaintiff by failing to properly supervise Sigma. Specifically, plaintiff alleged that

[the Board of Education] and Shuller... were aware that [Sigma] was in breach of its contract with [the Board of Education] and that said breach included but was not limited to abandoning the project schedule, performance of its work without plan or coordination, and the presence of project-wide evidence of defective workmanship.

Plaintiff further alleged “[the Board of Education] and Shuller . . . failed to respond to [Sigma’s] Breach of Contract in a timely manner by allowing [Sigma’s] material breach to continue.” Plaintiff also alleged the Board of Education breached its contract *167 by failing to pay the contract balance to plaintiff in June 2002. Plaintiff also alleged that “[p]rior to and after [Sigma’s] bankruptcy filing, the [Board of Education] . . . failed to adequately monitor the project’s progress. . . . Such failures included] ... [a] failure to provide adequate contract drawings and specifications.” Accordingly, plaintiff alleged that the Board of Education breached an implied warranty because the “drawings, plans, specifications and bidding documents furnished by [the Board of Education] were not sufficient for their intended purpose.”

The Board of Education filed a motion for summary judgment dated 15 October 2004. In support of its motion, the Board of Education argued, inter alia, that plaintiff’s claims were barred by the applicable statute of limitations. The trial court granted partial summary judgment for the Board of Education on plaintiff’s breach of contract claim. The trial court noted that “[w]ith respect to Plaintiff’s Breach of Contract Claim, the sole issue remaining for trial [was] whether Plaintiff [was] entitled to its contract balance.” The trial court granted summary judgment for the Board of Education on plaintiff’s entire breach of warranty claim. Plaintiff appeals.

I.

Plaintiff argues the trial court erred in granting partial summary judgment for the Board of Education on plaintiff’s breach of contract claim to the extent the trial court ruled that plaintiff’s claim was barred by the applicable statute of limitations. The parties do not dispute the applicable statute of limitations period was two years. See N.C. Gen. Stat. § 1-53(1) (2003) (stating that a two-year limitations period applies to “[a]n action against a local unit of government upon a contract, obligation or liability arising out of a contract, express or implied”). The parties disagree as to the accrual date of plaintiff’s breach of contract claim.

Summary judgment is proper when “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.” N.C. Gen. Stat. § 1A-1, Rule 56(c) (2003). On an appeal from a grant of summary judgment, our Court must determine “whether there is any genuine issue of material fact and whether the moving party is entitled to a judgment as a matter of law.” Bruce-Terminix Co. v. Zurich Ins. Co., 130 N.C. App. 729, 733, 504 S.E.2d 574, 577 (1998). We must view the evidence in the light most favorable to the *168 nonmoving party. Id. If a plaintiffs claim is barred by the running of the applicable statute of limitations, summary judgment in favor of a defendant is appropriate. McCutchen v. McCutchen, 170 N.C. App. 1, 5, 612 S.E.2d 162, 165 (2005).

It is a well-settled rule in North Carolina that a cause of action for breach of contract accrues, and the statute of limitations period begins to run, “[a]s soon as the injury becomes apparent to the claimant or should reasonably become apparent[.]” Liptrap v. City of High Point, 128 N.C. App. 353, 355, 496 S.E.2d 817, 819, disc. review denied, 348 N.C. 73, 505 S.E.2d 873 (1998) (citing Pembee Mfg. Corp. v. Cape Fear Constr. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Corvias Group, LLC
E.D. North Carolina, 2023
Kennedy v. Caliber Home Loans
E.D. North Carolina, 2019
Lockerman v. S. River Electric Membership Corp.
794 S.E.2d 346 (Court of Appeals of North Carolina, 2016)
Gr&s Atlantic Beach, LLC v. Hull
2012 NCBC 52 (North Carolina Business Court, 2012)
Royster v. McNamara
723 S.E.2d 122 (Court of Appeals of North Carolina, 2012)
Williams v. HOUSES OF DISTINCTION, INC.
714 S.E.2d 438 (Court of Appeals of North Carolina, 2011)
State Employees Credit Union v. HENDRYX
689 S.E.2d 244 (Court of Appeals of North Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
623 S.E.2d 57, 175 N.C. App. 164, 2005 N.C. App. LEXIS 2728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abl-plumbing-heating-corp-v-bladen-county-board-of-education-ncctapp-2005.