Abhe & Svoboda, Inc. v. Bell Bci Co.

520 F. Supp. 2d 701, 2007 U.S. Dist. LEXIS 83310, 2007 WL 3299276
CourtDistrict Court, D. Maryland
DecidedOctober 30, 2007
DocketCivil L-05-498
StatusPublished

This text of 520 F. Supp. 2d 701 (Abhe & Svoboda, Inc. v. Bell Bci Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abhe & Svoboda, Inc. v. Bell Bci Co., 520 F. Supp. 2d 701, 2007 U.S. Dist. LEXIS 83310, 2007 WL 3299276 (D. Md. 2007).

Opinion

MEMORANDUM

BENSON EVERETT LEGG, Chief Judge.

This is a contract dispute involving the construction and painting of two jet fuel *702 tanks for the Department of the Navy. BELL BCI Company (“BELL”), the general contractor on the project, hired Abhe & Svoboda, Inc. (“ASI”) to paint the tanks after their construction pursuant to a subcontract dated June 27, 2003 (the “Subcontract”). When confusion over whether the tanks had been constructed in accordance with the specifications issued by the Navy delayed the project, ASI incurred unexpected costs. Although ASI contends that it fully performed under the Subcontract despite the project’s uncertainties and delays, BELL disagreed and notified ASI’s surety that ASI was in breach of its contractual duties. This lawsuit followed.

ASI claims that BELL’s failure to pay ASI in full for its work (i) violates the Miller Act, 40 U.S.C. § 3131 et seq.; (ii) breaches the terms of the bond guaranteeing BELL’s performance under the Subcontract; and (iii) breaches the Subcontract. ASI also claims that BELL is liable for the allegedly defamatory statements made to ASI’s surety. Now pending is BELL’s motion for partial summary judgment on these claims. 1 Because issues of material fact preclude summary judgment for BELL, the Court will, by separate order, deny BELL’s motion and set a date for trial.

I. BACKGROUND

In June 2001, the Navy hired BELL as the general contractor for the construction of two jet fuel storage tanks at the Patuxent River Naval Air Station in St. Mary’s County, Maryland. 2 BELL’s contract required it to construct the tanks in accordance with detailed specifications provided by the Navy, and to periodically submit work plans to the Navy showing how these specifications were to be followed.

Constructing the tanks involved welding metal together in various places. The Navy’s specifications entitled “Weld Inspection” provided that the welds were to be inspected in accordance with an industry standard called the American Petroleum Institute’s Standard 650 (“API 650”). Another section of the Navy’s specifications that concerned the installation of a flexible membrane liner, however, stated that the tanks’ interior surfaces — including the welds — were to be finished in accordance with a more exacting industry standard known as NACE RPO-178. 3

BELL submitted a work plan on October 22, 2001 informing the Navy that the welds would be constructed to conform to API 650. The Navy approved this work plan on November 1, 2001. Accordingly, the tanks were constructed in accordance with API 650. Following its final inspection on April 2, 2002, the Navy approved the tanks’ construction and gave the go-ahead for the tanks’ painting to begin. BELL hired ASI as a subcontractor shortly thereafter. 4

The Subcontract provided that ASI would provide the necessary labor and ma *703 terials to complete the tanks’ painting. In the event that ASI failed to perform under the Subcontract and failed to remedy any contractual deficiencies after receiving notice of default, BELL was entitled to notify ASI’s surety and to charge the cost of remedying the deficiency to ASI.

In addition, the Subcontract included a “Disputes Provision” governing the parties’ conduct in the event that ASI expended additional time or incurred additional costs not included in the Subcontract’s base $995,000.00 price. This provision stated that ASI must give BELL written notice of any claims for additional payment, and that:

If Subcontractor’s claim involves the [Navy,], BELL shall be permitted to pass Subcontractor’s claim(s) to the [Navy], as it deems appropriate. The [Navy’s] decision on Subcontractor’s claim shall be final and conclusive as between BELL and Subcontractor, and BELL shall have no liability to Subcontractor therefore. Subcontractor’s recovery is limited to what BELL may recover on Subcontractor’s behalf.

In August 2003, before beginning the process of painting the tanks, ASI wrote to BELL seeking clarification on the preparation of the tanks’ surfaces. ASI noted that the Navy’s specifications required the tanks’ surfaces to be free from “weld splatter, sharp fins, sharp edges, burning slag, scabs, slivers, etc.” before painting could begin, and ASI acknowledged that these preparations were its responsibility under the Subcontract. Citing the NACE RPO-178 standard in the Navy’s specifications, however, ASI contended that it was not responsible for preparing the tanks’ surfaces to bring the welds into compliance with this higher standard. 5

In response to ASI’s letter, BELL submitted a Request for Information to the Navy asking whether NACE RPO-178 applied to the tanks’ welds. On August 27, 2006, BELL received the Navy’s response that the architect/engineer “believes ‘no’ is the answer.... ROICC 6 concurs. Welds shall be inspected as per API 650.” BELL communicated this decision to ASI.

Approximately three weeks later, however, the Navy reversed itself, notifying BELL that, “[u]pon further review and consideration, the government believes that the NACE RPO-178 standard does apply to the welds.” In a letter received by BELL on September 17, 2003, a Navy representative noted that “[t]he final decision of the Navy in this matter should ... come as no surprise, as the NACE RPO standard is the only requirement in the specifications that addresses the condition of the welds and their suitability for coating.” The letter also informed BELL that, because “the work to ensure that the welds meet the NACE RPO-178 standard ... should have been included in the base contract price,” “the Navy rejects any compensation for additional work.”

Notwithstanding this conclusion, BELL notified the Navy on September 24, 2003 that conforming the welds to the higher standard would significantly delay the painting process. 7 BELL also created an *704 “Extra Work Order” to track the costs associated with bringing the tanks into compliance, and included the additional costs submitted by ASI in the work order’s running tally. Although BELL submitted this extra work order to the Navy when the project was completed, the Navy refused to provide any additional compensation for the costs and delays associated with the additional work.

ASI completed its work on the tanks in February 2004. BELL subsequently requested that ASI return to perform touch-up work on the tanks. 8 When ASI refused to do so, BELL notified ASI’s surety that ASI was in default of the Subcontract. Ultimately, ASI agreed to return to perform the touch-up work, and BELL agreed to pay ASI for its costs to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
520 F. Supp. 2d 701, 2007 U.S. Dist. LEXIS 83310, 2007 WL 3299276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abhe-svoboda-inc-v-bell-bci-co-mdd-2007.