ABEC, INC. v. EAT JUST, INC.

CourtDistrict Court, E.D. Pennsylvania
DecidedApril 30, 2024
Docket5:23-cv-01091
StatusUnknown

This text of ABEC, INC. v. EAT JUST, INC. (ABEC, INC. v. EAT JUST, INC.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ABEC, INC. v. EAT JUST, INC., (E.D. Pa. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA ABEC, INC., CIVIL ACTION Plaintiff, v. EAT JUST, INC. AND GOOD MEAT, NO. 23-cv-1091 INC., Defendants. MEMORANDUM OPINION Plaintiff ABEC and Defendants Eat Just, Inc. and Good Meat, struck a deal—the Bioreactor Agreement (“the Agreement”)—regarding the fabrication of machines to grow cultivated meat. Pursuant to the Agreement, ABEC undertook to build and deliver to Defendants certain cultured-meat-bioreactor equipment.1 The relationship soon turned rancid and ABEC sued Eat Just, Inc. and Good Meat (henceforth together “Counterclaimants”). They in turn asserted counterclaims, the following of which ABEC now seeks to dismiss pursuant to Federal

Rule of Civil Procedure 12(b)(6): breach of contract, conversion; replevin, and a request for declaratory judgment that the parties never actually entered intocertain amendments to the Agreement. For the following reasons, ABEC’s Motion will be granted in part and denied in part. FACTUAL BACKGROUND The Agreement divided the project into five stages and provided that “[u]pon completion

1Specifically, bioreactor trains and associated materials and support equipment, raw materials and components for bioreactor fabrication, and additional equipment. 1 of each Stage (or earlier as [Good Meat] and ABEC agree), ABEC w[ould] confirm pricing and [Good Meat] w[ould]provide formal approval and funding to proceed to subsequent stages.” Under the Agreement, according to the Counterclaimants, “ABEC promised to provide a price for each Stage that will align with the value ABEC would typically attribute to a partner-based product development and execution effort.” Counterclaimants allege that they have now paid

ABEC approximately $80,369,066 for equipment but ABEC has not delivered any of it. Counterclaimants also allege that as the project progressedthey began to face “financing hurdles” and so recommended reevaluating the parties’ approachto the project. Although all parties agree that they began to negotiatepotential amendments to the Agreement (“the Amendments”) they disagree as to the upshot of those negotiations: Counterclaimants maintain that the Amendments were never finalized and executed; ABEC (in its claims) alleges they were. LEGAL STANDARD “To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal,

556U.S.662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550U.S.544, 570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. “Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice.” Id. The same standard is used when analyzing a plaintiff’s motion to dismiss a defendant’s counterclaims. Patel v. Dhaduk, 839 F. App’x 715, 720 (3dCir. 2020) (“In analyzing a 12(b)(6) motion to dismiss, we accept as true the well-pleaded facts of the counterclaim and disregard legal conclusions.”) (citing Davis v. Wells Fargo, 824F.3d333, 341, 351 (3dCir. 2016)). The lens to construe the countercomplaint is “in the light most favorable to

2 the [counterclaim] plaintiff[,]” Fowler v. UPMC Shadyside, 578F.3d203, 210 (3dCir. 2009), with a view to answering the question as to “whether, under any reasonable reading of the complaint, the [counterclaim] plaintiffmay be entitled to relief.” Id. The Court “tak[es] note of the elements [that]must [be] plead to state a claim[,]” Oakwood Lab’ys LLC v. Thanom,999 F.3d 892, 904 (3d Cir. 2021) (quotation omitted) (alteration in original) then—taking all non-

conclusory well-pleaded facts as true—determines whether those facts state a “plausible claim for relief.” Fowler, 578 F.3d at 210-11. DISCUSSION A. Counterclaim I: Breach of Contract (Failure to Deliver) Counterclaimants’breach-of-contract claim is premised on their allegation that although they have paid ABEC over eighty million dollars, and althoughABEC has the equipment Counterclaimants say they paid for, ABEC has refused to deliver it. This,Counterclaimants maintain, is a breachofthe Agreement. In Delaware,2 the elements of a breach-of-contract claim are: (1) a contractual obligation;

(2) a breach of that obligation; and,(3) resulting damages. Interim Healthcare, Inc. v. Spherion Corp., 884A.2d513, 548 (Del.Super. 2005), aff’d,886A.2d1278 (Del. 2005). As to the first requirement, the parties do not dispute that the Agreement boundthem and obligated them in certain ways. And the third requirement—resulting damage—is adequately pled: Counterclaimants say that they paid $80,369,066 under the Agreement and received nothing for it. Counterclaimants allege that Stage 5 of the project had not yet begun when the venture fell

2The Bioreactor Development Agreement states that it “shall be governed by the substantive laws of the State of Delaware,” a provision that the Amendments ratified. As explained in the Court’s December 21, 2023, opinion, the Court will honor the choice of law of the parties as set forth in the agreement. 3 apart. The Agreement priced Stage 1 (a feasibility analysis) and Stage 2 (conceptual design) together at $2,200,000 total. Counterclaimants say that Stage 5 (full-scale construction) never began. It is reasonable here to infer that Counterclaimants allegedly paid ABEC the remaining $78,169,066 for something under Stage 3 (design validation) and Stage 4 (construction and testing of the first bioreactor) pursuant to the Agreement. They have alleged damages that are

“causally related” to the breach and “warrant[] a remedy[.]” Garfield on behalf of ODP Corp. v. Allen, 277 A.3d 296, 328 (Del. Ch. 2022). The focus, thus, is on whether Counterclaimants have sufficiently alleged the second element: breach of a contractual obligation. Their claim boils down to this: The Agreement obligated them to pay ABEC, and it obligated ABEC to build and deliver certain property; they paid, but ABEC delivered nothing. They highlight one particular provision from the Agreement. ABEC, they allege, agreed to: “timely prepare and provide to [Counterclaimants] all Prototypes, other Deliverables and/or other results of the Project.”

In its Motion to Dismiss ABEC makes two central contentions and two supporting contentions. Its first central contention is that it did not breach the Agreement because no delivery obligation under the Agreement ever vested. ABEC acknowledges the Agreement’s requirement that it “timely prepare and provide to [Counterclaimants] all Prototypes, other Deliverables and/or other results of the Project,” but it contends the Agreement did not obligate it to deliver anything until Stage 5 of the project (which the parties had not reached by the time the venture dissolved) because in the Agreement’s Statement of Work only Stage 5 contemplates “shipping.” Although Counterclaimants grant that Stage 5 in the Statement of Work calls for the “shipping” of certain property, they respond that earlier stages necessarily required delivery of some 4 property (for instance, Stage 4 contemplated “construction” and “installation,” which Counterclaimants argue could not occur without delivery). Counterclaimants’ reading is plausible enough to withstand a motion to dismiss: It is reasonable to infer that “installation” of certain property would require delivery of that property, given that because the provision “must be construed in the light most favorable to the non-moving party.” VLIW Tech., LLC, 840 A.2d

at 615. Counterclaimants’ reading—that under the Agreement their payment entitles them to the delivery of some “[d]eliverables”—is plausible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Werwinski v. Ford Motor Company
286 F.3d 661 (Third Circuit, 2002)
McTernan v. City of York, Penn.
577 F.3d 521 (Third Circuit, 2009)
Hoechst Celanese Corp. v. National Union Fire Insurance
623 A.2d 1133 (Superior Court of Delaware, 1992)
VLIW TECHNOLOGY, LLC v. Hewlett-Packard Co.
840 A.2d 606 (Supreme Court of Delaware, 2003)
Gannett Co., Inc. v. Board of Managers
840 A.2d 1232 (Supreme Court of Delaware, 2003)
Bruno, D., Aplts. v. Erie Insurance
106 A.3d 48 (Supreme Court of Pennsylvania, 2014)
Garber v. Whittaker
174 A. 34 (Superior Court of Delaware, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
ABEC, INC. v. EAT JUST, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/abec-inc-v-eat-just-inc-paed-2024.